Calstate Construction - San Ysidro Park Rec. Building Remodel - Change Order No. 9To contract for: San Ysidro Park
Cite of O frog
Public Works Department - Engineering Division
7351 Rosanna St., Gilroy, CA 95020
Phone (408) 846 -0451; Fax (408) 846 -0429
CHANGE ORDER NO. 9
City Project No.: 12 -PW -194
Contractor: Calstate Construction Inc, Contract Date: 1/6/2012
This order shall become effective when it has been signed by the City Administrator, City Engineer, Project Engineer, and
Contractor. All copies forwarded to Contractor for signature shall be returned to the City of Gilroy properly filled out. Upon
acceptance by the City, the Contractor's copy will be returned to him as his authority to proceed with the work.
Description of Work
Furnish and Install I ea new 3'x6' kitchen aluminum Milguard window to match existing. Match existing new window criteria
as submitted in submittal #31. To supply and install 8 "' 20 gauge flashing metal to the activites room at the mudsill bottom
plate to eliminate potential water damage. To meet ADA requirements Calstate to furnish and install new barbacue grill in
accessible picnic area. Post to be imbedded in 3' of concrete. To remove and replace 4 ea 4'x9'x5/8" exterior siding to
southern building due to water damage. To remove and replace 4 ea 2x6x10 resawn redwood trims. Calstate is to remove
and reinstall the existing HVAC unit from the roof including the angle stand. Replace damaged plywood roof sheating.
Install new sleepers as detailed and directed in response to RFI #41. Calstate to install additional structral framing as
directed by the structural engineer on sheer wall at wall soffit, as directed in RFI # 32.1.
All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this
Change Order. The contract time shall not extend unless expressly provided for in this Change Order.
By signing this Change Order, Contractor acknowledges and agrees that the adjustments to cost and time contained herein
are in full satisfaction and accord, and are accepted as payment in full, for any and all costs and expenses associated with
this Change Order, (the "Extra Work "), including but not limited to labor, materials, overhead and profit, delay, disruption,
loss of efficiency and any and all other direct and /or indirect costs or expenses associated with the Extra Work and hereby
waives any right to claim any further cost and time impacts at any time during and after completion of the Contract
associated with the Extra Work.
► All Extra Work authorized under this Change Order
must be billed separately from the original contract. All
bills for work done under this Change Order shall
reference this Change Order No. 9.
I (We) agree to make the above change subject to the
terms of this Change Order for a NET INCREASE not to
exceed $10,104.28.
Calstate Construction, Inc.
CONTRACTOR
RECOMMENDED BY:
ACCEPTED BY.
Cost Percentage Initial
Original Contract Price
$771,744.00
Previous Change Orders
$105,153.04 13.63%
Total to Date
$876,897.04
This Change Order
$10,104.28
Total Change Orders to Date $115,257.32 14.93%
Revised Contract Price $887,001.32
Date: 5/10/12
6 lt
Construction Man
Date
Vic// Z
Proje n /P ject r
Date
J
ngin r
dministrator
Date
San Ysidro Park Recreation Bldg Remodel # 12 -PW -194
Project No. 12-001 DATE: 5/8/2012
San Ysidro Park #12 -PW -194 CONTRACTOR: Calstate Construction, Inc.
CONTRACTOR COST PROPOSAL #. 24
POTENTIAL CHANGE ORDER (PCO) - COST PROPOSAL - PRIME CONTRACTOR
DESCRIPTION OF CHANGE: Additional framing per RFI#32.1
ITEM DESCRIPTION
MATERIAL sales tax included
OR tfully encumbered
QUANTITY
UNIT
UNIT COST
EXTENSION
QUANTITY
HOURS
RATE
EXTENSION
QUANTITY
UNIT COST
EXTENSION
Su ordinate work/Subs
0
0
J 2
$82.00
$164.00
0
$0.00
$
carpenter
8
$82.00
$ 656.00
Lumber
$100
SUBTOTAL
Lms
6 100.00
$ 820.00
$ _
A ARK-UP
$ 15.00
$ 123.00
$
TOTALS
115.00
$ 949.00
$ _
Option A
MATERIAL + 15% $115.00
LABOR + 15% $943.00
EQUIPMENT + 15% $0,00
PRIME CONTRACTOR TOTAL 1 $1,058.00
Sub Contractor Costs from Attached Cost Proposal(s)
SUBCONTRACTOR SUBTOTAL DIRECT COSTS �— 50,00
PRIMARY 5% FEE ON SUBCONTRACTORS COST r $0,00
SUBCONTRACTOR TOTAL PEE $0.00
PRIME TOTAL $1,058.00
SUBTOTAL COR $1,058.00
BOND ( not to exceed 2% of sub total) $ 21.16
TOTAL 1 $1,079.16
PREPARED & SUBMITTED BY: Jim Lyons
COMPANY: Calstate Construction, Inc. TITLE: PM
Cost Proposal
alstate
(rcCONSTRUCTION INC.
8UBJECTInterior Sheer Well at Kitchen
REQUEST FOR INFORMATION
No: 00032.1
Dato: 04/18/12
Paps: 1 of 1
DATE: 04/12/12 PRIORITY: Normal
STATUS: Closed
JOB: San Ysktro Park Recreation (#12-001) C.O.9. WA
Project No. 12-PW -194 TRACK a: WA
7700 Munray Ave
Gilroy, CA 96020
TO: Judy Hemingway FROM: Jared Perry
HemingwayorStocc Inc Calstats Construction, Inc.
939 Rellet Station Rd 13:510.657.1800 FS10.657.1810
Lafayette, CA 945" 4165 Business Center Drive
Fremont, CA 94538
QUEBTWN .
After opening up the upper section of wail for the new shear wall above, it was discovered the existing framing is a
bit afferent than the way it Is sketched on " Section at WsMof lr. There Is no existing bottom plate on the upper
section, and the existing solid blocking is not on to double plates of the lower wall. The upper studs are toe nalled
to the double top plate or kx %w wall, directly over the lower studs, and the solid blocking Is not over the lower wan
but 1/2" off the wall. And in lieu of an existing sE plate an the upper wall, there are solid 2x blockinng.
Would it be possible to use vertical straps between the upper and lower studs for the shear Do? Or use AWs to
connect the existing SB to the lower double plate and the upper 2x blocking? Please Advise
Provide framing as shown in the attached sketch, SKI.
Sc ed. Imped
Coat hopaat
COR 0
REQUEST FOR INFORMATION
Nw. 00=1
No., W2112
Calstate P"W I d I
(rCCON,TR.CT,.. INC.
UXL=Mftrlor Show Wd at Kldm DIRE: W2A2 MOWN. Normal
SVM- Su bmNed
im San YWft Pork Rowmftn 012-MI) CA* WA
Pf*ot N% 12.PW-104 TPACK& WA
7700 MwwAvo
G&W CA OM
Tm Hwnkvw FAA: Jared Ps"
I em lta*ftdnx* Inc C&Wde C61*ucdm kc.
030 RslW 8Ww Rd P010A6 ASM P510.6P.1810
Lmkyoft, CA 945" Fram4165 BuMnift Corder Drive
GK CA "M
After . i o up to OW subn d
O for the now wail sbw% I was ftmued the adsft *wft Is a
t*d%w dm the vmYkfa *"Iml" 0n'Ss0&m6l%VmW$W-Tb"l9fw 0. H'9 bottom Phmcn the &"w
wdb� aid the o3&ft w0d bh*rl Is rM On the ftdft 00109 Of the kmw WdL The upper OW& Rm bo Mad
to fie "A* mp omto of bAw Wd. &4* mw ft Imm shift ww " =W.Wdft b M mw Me kxm vml
W Igo of to wd. W. to lieu ct an ao 1 0 io A Oft dh ft w;w MO, MOM we GON 2N bloddnp.
Would t be p=W* lo use vwVW Skullb M%mm the upper and kwir-Muds far On show fo7 Or Lou AM ID
omrvd #0 odo" so to to bww dmt* pkft mW the upper 2x Mo~ Please Adobe
tpwlol*l *. � I
8d" W"at
cost kuped
Cwt
7-4
Pp4P^lbL F12AM04 AS
A PrA"" SV-A"r-i�t )
si4wij tj TNo-
sv-t I
• 1 .
im )SP36
MBA STRUCTURAL ENGINEERS, INC. Wwom
1717 N. California Blvd. #2A
Walnut Creek, CA 94596 VAm
CHBCMOV- DATE
go"
L
2f
ED
Ll i
44-1- J.
fill
j_ J__
_41
JI"
4 +
1
-
13
j
77-i-
od- -
y-I- I
U i I I I_j_I,(,_i_I_i+ .-i I_! I I Y
_601
J-1
-I :•i ,
Ti
44
Aill
A-L.
-y-
141
j
j-
1 !T71 J7 I
1 1-17!
T .,D_
(-i'_; j
F-1-1
A... A J_
7L ,
i T
-j
7"
.................... ...............
Project No. 12 -001
San Ysidro Park 912 -PW -194
San Ysidro Park Recreation Bldg Remodel # 12 -PW -194
DATE: 5/8 /2012
CONTRACTOR: Calstate Construction, Ina
CONTRACTOR COST PROPOSAL #: 22
POTENTIAL CHANGE ORDER (PCO) - COST PROPOSAL - PRIME CONTRACTOR
DESCRIPTION OF CHANGE: Per FO#19 and FIR #41 Calstate is directed to remove and reinstall the eAsting HVAC unit from the roof including the angle stand. Remove
and replace damaged plywood roof shaatin . Install new sleepers as per Architect drawl ,
ITEM DESCRIPTION
MATERIAL sales tax Included
LABOR (ffuliNy anoumbered
QUANTITY
UNIT
UNITCOST
EXTENSION
QUANTITY
HOURS
RATE
EXTENSION
QUANTITY
UNITCOST
ExTENS10N
SurveAsymIlCoordlimte work/Subs
0
0
-
2
$82.00
$164.00
0
$0.00
Laborer
5
$59.42
$297.10
Carpenter
6
2.00
$ 656.00
Wood Material
$100
Fab and Install Sleeper Caps, 110 Step
Shingles, 2 sleeper top saddles and 2
bottom saddles
$1,435
SUBTOTAL
$ 1535.00
$ 1,117.10
$
MARK -UP
I
J
J$
230.25
$ 167.57
1
$
TOTALS 1
$ 1,765.25
$ 1.284.67
$
Option A
MATERIAL + 15% $1,765.25
LABOR + 15% $1,284.67
EQUIPMENT + 15% $0.00
PRIME CONTRACTOR TOTAL 1 $3,049.92
Sub Contractor Costs from Attached Cost Proposal(s)
SUBCONTRACTOR SUBTOTAL DIRECT COSTS 1 $0.00
PRIMARY 5% FEE ON SUBCONTRACTORS COST $0.00
SUBCONTRACTOR TOTAL FEE $0.00
PRIME TOTAL $3,049.92
SUBTOTAL COR $3,049.92
BOND ( not to exceed 2% of sub total) $ 61.00
TOTAL 1 $3,114.92
PREPARED & SUBMITTED BY: Jim Lyons
COMPANY: Calstate Construction, Inc. TITLE: PM
Cost Proposal
Project Name: San Ysidro Park Recreation Building
FIELD ORDER
City Of Gilroy
7387 Rosanna Street
Gilroy, CA 95020
FIELD ORDER NO. 19
Project Name: San Ysidro Park Recreation
Contract Date: 01/06/2012
To Contractor: Calstate Construction Inc
Address: 4165 Business Center Dr.
Fremont CA 94538
DESCRIPTION OF WORK:
Project No: 12 -PW -194
5/4/12/12
Calstate is directed to remove and reinstall the existing HVAC unit from the roof including the angle stand.
Remove and replace damaged plywood roof sheating. Install new sleepers as per Architect drawing.
Estimated Adjustment
of Contract Sum:
Ron Barri / PM
(Name of Construction Manager/Title - typed or printed)
By:
(Signature)
Date: 5/4/2012
Jared P / Project Manager
(Name of Contractor Representative/Title - typed or printed)
(Signature)
Date:
Estimated Adjustment
of Contract Time:
IsTote: This Field Order will be superseded by an allowance adjustment or a Change Order that will include the
scope of the change in the Work and any actual adjustments of the Contract Sum.
a I S t a t ..
CONSTRUCTION INC.
SUBJECTExisting HVAC Unit on Roof
DATE:
REQUEST FOR INFORMATION
No. 00041
Date: 05/02/12
Pape: 1 of i
PRIORITY: Normal
STATUS: Submitted
JOB: San Ysldro Park Recreation ( #12-001) C.O. #. N/A
Project No. 12 -PW -194 TRACK 0: N/A
7700 Murray Ave
Gilroy, CA 95020
TO: Judy Hemingway FROM: Jared Perry
Hemingway/Stock Inc Calstate Construction, Inc.
939 Reliez Station Rd P:510.857.1800 F:510.657.1810
Lafayette, CA 9454 -9 4165 Business Center Drive
Fremont, CA 94538
QUESTION-
The existing HVAC unit sits on top of a steel angle support frame which Is bolted directly on the composition roof
tiles. After the demo of the roof shingles dry rot was discovered under the unit. The roofer mentioned that their
manufacturer's rep will not warranty, the roof with the angle iron frame bolted directly ort to the roof system.
They suggest some sleepers be installed with a cricket and flashing on the uphill side of the roof. Please advise.
See attached picture of the existing unit
ANSWER.
USER FIELDS•
Schad. Impact
Cost Impact
COR e
T&tfe4 0 1 pt�
iY a re4� of � ck7 r4,
- - 14e, �zv(b e>16q� w�&Y- &'X14;W-A
PP-yt fr m re'r-
Note:
Provide backer flashing extending upslope under
shingles a minimum of 16" at top, and apron flashing
(w/ lower edge hemmed under) extending over
asphalt shingles at bottom. (Similar to skylight
flashing.)
Set bolts in sealant
Neoprene pad
c
1 1EI 1}
t 1
W .
4x PT sleeper —
Shingle roof assembly: A
Mechanical equipment
support frame
GSM cover
— High - domed, capped gasketed
fasteners at 16" o.c.
Flexible flashing over 4x and A35
Step flashing
Simpson A35 at 16" o.c. min.
(sleeper to deck Conn.)
0 Equipment Sleeper Curb (Typ. of 2)
Scale: 3" = V -0" 0 3 6
wof-"I
Pro)ecta San Ysidro Park Recreation Building
Hemingway/Stock, Inc. Remodel + Addition + Site Improvements
939 Reliez Station Road City of Gilroy, California
Lafayette, California 94549
(925) 944 -4745 Title: Equipment Sleeper Curb (Ref: RFI No.041)
Drawn, checked I Prood Ntnnbrr: GIi Q9
Drawing No_
S KA -OS
None
Date: 05-05-12
Project No. 12 -001
San Ysidro Park #12 -PW -194
San Ysidro Park Recreation Bldg Remodel # 12 -PW -194
DATE: 5/8/2012
CONTRACTOR: Calstate Construction, Inc.
CONTRACTOR COST PROPOSAL #: 21
POTENTIAL CHANGE ORDER (PCO) - COST PROPOSAL - PRIME CONTRACTOR
DESCRIPTION OF CHANGE: Remove and replace 4ea fx9k5/8- exterior AC plywood to southern end of building. Remove and replace 4 ea 2x6x10 resawn redwood
trims.
ITEM DESCRIPTION
MATERIAL sales tax included
OR (fully encumbered
QUANTITY
UNIT
UNIT COST
EXTENSION
QUANTITY
HOURS
RATE
EXTENSION
OUANTTY
UNIT COST
EXTENSION
SurveyA.ayoutfCoorclinate work/Subs
0
0
$
2
$82.00
$164.00
0
$0.00
$
Labor
4
$59.42
$237.68
Carpenter
8
$82.00
656.00
Trim
80.00
Plyvvood
$260
SUBTOTAL
$ 340.00
$ 1,057.68
$ -
,MARK-UP
$ 51.00
$ 158.65
$
TOTALS
$ 391.00
Is
1,216.331
$
Option A
MATERIAL + 15% $391.00
LABOR + 15% $1,216.33
EQUIPMENT + 15% $0.00
PRIME CONTRACTOR TOTAL i $1,607.33
Sub Contractor Costs from Attached Cost Proposal(s)
SUBCONTRACTOR SUBTOTAL DIRECT COSTS $0.00
PRIMARY 5% FEE ON SUBCONTRACTORS COST $0.00
SUBCONTRACTOR TOTAL FEE $0.00
PRIME TOTAL $1,607.33
SUBTOTAL COR $1,807.33
BOND ( not to exceed 2% of sub total) $ 32.15
TOTAL I $1,639.48
PREPARED & SUBMITTED BY: Jim Lyons
COMPANY: Celstate Construction, Inc. TITLE: PM
Cost Proposal
Project Name: San Ysidro Park Recreation Building Project No: 12 -PW -194
FIELD ORDER
City Of Gilroy 414/12
7387 Rosanna Street
Gilroy, CA 95020
FIELD ORDER NO. 14
Project Name: San Ysidro Park Recreation
Contract Date: 01/06/2012
To Contractor: Calstate Construction Inc
Address: 4165 Business Center Dr.
Fremont CA 94538
DESCRIPTION OF WORK:
Remove and replace 4ea 4'x9'x5 /8" exterior AC plywood to southern end of building. Remove and replace 4 ea
2x6xl0' resawn redwood trims.
Estimated Adjustment
of Contract Sum:
Ron Bard / PM
(Name of Construction Manager/Title - typed or printed)
By:
(Signature)
Date: 4/4/2012
Jared Perry / Proiect Manager
(Name of Contractor RepresentativwTitle - typed or printed)
(Signature)
Date:
Estimated Adjustment
of Contract Time:
Note: This Field Order will be superseded by an allowance adjustment or a Change Order that will include the
scope of the change in the Work and any actual adjustments of the Contract Sum.
San Ysidro Park Recreation Bldg Remodel # 12 -PW -194
Project No. 12 -001 DATE: 5/2!2012
San Ysidro Park #12.PW -194 CONTRACTOR: Calstate Construction, Inc.
CONTRACTOR COST PROPOSAL #: 20
POTENTIAL CHANGE ORDER (PCO) - COST PROPOSAL - PRIME CONTRACTOR
DESCRIPTION OF CHANGE: Fumish and Install Barbecue Grill per 170p15
ITEM DESCRIPTION
MATERIAL sales Max included
LABOR tffftWaly encumber
QUANTITY
UNIT
UNr r COST
EXTENSION
QUANTnY
HOURS
RATE
EXTENSION
QUANTITY
UNIT COST
I EXTENSION
Su A.a uNCoordinate wcrk/Subs
0
0
$
2
$6200
$164. 00
0
S0.00
Is
Labor
4
$59.42
$237.68
Barbecue
250
Concrete
100
SUBTOTAL
$ 350.00
$ 401.66
$ _
MARK-UP
$ 52.50
1
Is
60.25
$
TOTALS
$ 402.50
$ 461.93
$ _
Option A
MATERIAL + 15% $402,50
LABOR + 15% $461.93
EQUIPMENT + 15% $0.00
PRIME CONTRACTOR TOTAL ( 0"A3
Sub Contractor Costs from Attached Cost Proposal(s)
SUBCONTRACTOR SUBTOTAL DIRECT COSTS I $0,00
PRIMARY 5% FEE ON SUBCONTRACTORS COST $0,00
SUBCONTRACTOR TOTAL FEE $0.00
PRIME TOTAL $864.43
SUBTOTAL COR $864,48
BOND ( not to exceed 2% of sub total) $ 17.29
TOTAL 1 $881.72
PREPARED & SUBMITTED BY: Jim Lyons
COMPANY. Calstate Construction. Inc. TITLE: PM
Cost Proposal
Furniture Leisure Search result for'KPSF16'
<< Retum To Previous Page
Model KPSF16
CHARCOAL- WOOD BURNING PEDESTAL GRILL with flip grate.
CHARCOAL - WOOD BURNING PEDESTAL GRILL with
flip grate. Commercial heavy duty steel Pedestal Park
Grills are great for individual cook stations for Parks,
Apartments, Condominiums, and Resorts and
campground areas to enjoy outdoor Barbeque dining at
its best This four position non- removeable flip grill, 300
Square inches grilling surface 2 3/8 inch in ground post
wt 79lbsGrilis This grill is a part of outdoor park fumiture
environments for cook outs and outdoor parties. What
American has not had a charcoal cooked hotdog or
hamburger at a park on the 4th of July.
All cooking grates are 1/2 inch welded bars and non -
removeable with four postion adjustments. Swivels 360
degrees for wind control.
Specifications:
Type: Single Pedestal Park Grill
Construction: 3116 inch Welded Steel
Cooking Surface Size: 300 Square inches
In Ground Post: 2 3/8 inch Galvanized Post
360 Degree Swivel: Yes
Cooking Grates: % inch Welded Steel Bars
Weight: 79 pounds
Dimensions: 20 "w x 15 "d x 10 "h
Assembly Required: Yes, Assembly and Installation
Page 1 of 1
Print Page...
d2m 1 20051 ! ninon I Pci I G9 e�� I sbMw
CALL 1-9001-213-2401 salea4furniturreleisure.com
Se Habla Espanoli
http : / /Www.f umitureleisure.coml home -p. asp ?display= fufl&cid= O&itemid =KPSF 16&itemna... 5/2/2012
Project Name: San Ysidro Park Recreation Building
FIELD ORDER
City Of Gilroy
7387 Rosanna Street
Gilroy, CA 95020
FIELD ORDER NO. 15
Project Name: San Ysidro Park Recreation
Contract Date: 01/06/2012
To Contractor: Calstate Construction Inc
Address: 4165 Business Center Dr.
Fremont CA 94538
DESCRIPTION OF WORK:
Project No: 12 -PW -194
4/5/12
Install City Supplied ADA barbecue grill in accessible picnic area. Barbecue post to be imbedded in 12" concrete
cylinder hole, 3' deep. Location to be determined by City Representative.
Estimated Adjustment
of Contract Sum:
Ron Barri / PM
(Name of Construction Manager/Title - typed or printed)
By:
(Signature)
Date: 4/5/2012
Jared Perry / Project Manager
(Name of Contractor Representativelfitle - typed or printed)
(Signature)
Date:
Estimated Adjustment
of Contract Time:
Note: This Field Order will be superseded by an allowance adjustment or a Change Order that will include the
scope of the change in the Work and any actual adjustments of the Contract Sum.
San Ysidro Park Recreation Bldg Remodel # 12 -PW -194
Project No. 12-001 DATE: 4117/2012
San Ysidro Park #12 -PW -194 CONTRACTOR: Calstate Constriction, Inc.
CONTRACTOR COST PROPOSAL #: 18
POTENTIAL CHANGE ORDER (PCO) - COST PROPOSAL - PRIME CONTRACTOR
DESCRIPTION OF CHANGE: Fumish and Install approximately 150 LF of 8' 20 gauge galvanized flat strap flashing
ITEM DESCRIPTION
MATERIAL sales tax Intlud
LABOR (fullyenc umbered
QUANTITY
UNIT
UNIT COST
EXTENSION
QUANTITY
HOURS
BATE
EXTENSION
QUANTITY
UNIT COST
EXTENSION
Survey&aypuUCpprdInat9 work/Subs
0
0
$
4
$82.00
$328.00
0
$0.00
$
Labor
12
$59.42
$713.04
8
$86.47
1.78
Flat 6M Fieshl
$525
ChoW
$65
SUBTOTAL
;
$ 1,732.80
$ 590.00
MARK -UP
$
$ 259.92
$ 88.50
TOTALS
$
$ 1,992.72
IS
678.50
Option A
MATERIAL + 15% $0.00
LABOR+ 15% $1,992.72
EQUIPMENT + 15% $678.50
PRIME CONTRACTOR TOTAL 1 $2,671.22
Sub Contractor Costs from Attached Cost Proposal(s)
SUBCONTRACTOR SUBTOTAL DIRECT COSTS $0.00
PRIMARY 5% FEE ON SUBCONTRACTORS COST $0.00
SUBCONTRACTOR TOTAL FEE $0.00
PRIME TOTAL $2,671.22
SUBTOTAL COR $2,671.22
BOND ( not to exceed 2 % of sub total) $ 53.42
TOTAL �.-._ $2,724.64
PREPARED & SUBMITTED BY:
COMPANY: Calstate Construction, Inc. TITLE: PM
Project Name: San Ysidro Park Recreation Building
DESCRIPTION OF WORK:
Project No: 12 -PW -194
4/4/12
After removing portions of the perimeter siding it was discovered that the Activities room was built without a curb
(slab only). To properly water tight the structure we recommend:
• To remove and replace the bottom 2' perimeter sliding where it meets the mud sill at the Activities Room.
• Furnish & Install approximately 1001f of 8" 20 gauge galvanized flat strap flashing to the exterior
foundation slab at the mudsill (3" min below slab).
+ Overlap butt joints 4 ". Install sikaflex caulking between mudsill and slab. Fasteners to be galvanized.
Estimated Adjustment
of Contract Sum:
Ron Bard / PM
(Name of Construction Manager/Title - typed or printed)
By:
(Signature)
Date: 414/2012
Jared P / Project Manager
(Name of Contractor Representativc Title - typed or printed)
(Signature)
Date:
Estimated Adjustment
of Contract Time: 2 days
Note: This Field Order will be superseded by an allowance adjustment or a Change Order that will include the
scope of the change in the Work and any actual adjustments of the Contract Sum.
FIELD ORDER
City Of Gilroy
7387 Rosanna Street
Gilroy, CA 95020
FIELD ORDER NO. 12
Project Name:
San Ysidro Park Recreation
Contract Date:
01/06/2012
To Contractor:
Calstate Construction Inc
Address:
4165 Business Center Dr.
Fremont CA 94538
DESCRIPTION OF WORK:
Project No: 12 -PW -194
4/4/12
After removing portions of the perimeter siding it was discovered that the Activities room was built without a curb
(slab only). To properly water tight the structure we recommend:
• To remove and replace the bottom 2' perimeter sliding where it meets the mud sill at the Activities Room.
• Furnish & Install approximately 1001f of 8" 20 gauge galvanized flat strap flashing to the exterior
foundation slab at the mudsill (3" min below slab).
+ Overlap butt joints 4 ". Install sikaflex caulking between mudsill and slab. Fasteners to be galvanized.
Estimated Adjustment
of Contract Sum:
Ron Bard / PM
(Name of Construction Manager/Title - typed or printed)
By:
(Signature)
Date: 414/2012
Jared P / Project Manager
(Name of Contractor Representativc Title - typed or printed)
(Signature)
Date:
Estimated Adjustment
of Contract Time: 2 days
Note: This Field Order will be superseded by an allowance adjustment or a Change Order that will include the
scope of the change in the Work and any actual adjustments of the Contract Sum.
San Ysidro Park Recreation Bldg Remodel # 12 -PW -194
Project No. 12 -001 DATE: 416/2012
San Ysidro Park #12 -PW -194 CONTRACTOR: Calstate Construction, Inc.
CONTRACTOR COST PROPOSAL #: 17
POTENTIAL CHANGE ORDER (PCO) - COST PROPOSAL - PRIME CONTRACTOR
DESCRIPTION OF CHANGE: Fumish and Install 1 ea additional 8' xT widow to the existing rough opening on the east elevafion at the kitcheNvestibule area Match
existing new window criteria as Submitted In submittal #31.
ITEM DESCRIPTION
MATERIAL crates Wax Included
LABOR(fullvo ncumbered
$175.00
OUMnW
UNIT
UNIT COST
EXTENSION
QUANTITY
HOURS
RATE
EXTENSION)
OUANTi1Y
UNIT COST
EXTENSION
Su a irate work/Subs
0
0
$
1
$82.00
$82.00
0
$0.00
$
DemoArestallation
4
$82.00
$328.00
SUBTOTAL
$
$ 410.00
i
MARK-UP
S -
$ 81.50
$
TOTALS
Is
471.50
Is
Option A
MATERIAL + 15% $0,00
LABOR + 15% $471.60
EQUIPMENT + 15% $0.00
PRIME CONTRACTOR TOTAL ( $471.50
Sub Contractor Costs from Attached Cost Proposal(s)
SUBCONTRACTOR SUBTOTAL DIRECT COSTS
$175.00
PRIMARY 5% FEE ON SUBCONTRACTORS COST
$8. 75
SUBCONTRACTOR TOTAL FEE
$183.73
PRIME TOTAL
$471.50
SUBTOTAL COR
$655.25
BOND ( not to exceed 2% of sub total)
$ 13.11
TOTAL 1 $6W.3
PREPARED & SUBMITTED BY: Jim Lans
COMPANY: Calstate Construction, Inc. TITLE: PM
Cost Proposal
San Ysidro Park Recreation Bldg Remodel # 12 -PW -194
Project No. 12 -001 DATE: 4/6/2012
San Ysidro Park #12-PW -194 CONTRACTOR: Calstate Construction, Inc.
CONTRACTOR COST PROPOSAL #: 17
POTENTIAL CHANGE ORDER (PCO) - COST PROPOSAL - SUBCONTRACTOR CONTRACTOR
DESCRIPTION OF CHANGE: Fwtich and Install f as addWonai V X7 whlow to the existing rough openkV an the east elevation at the kkctwYvostlbule area Match
exJstina new window criteria as submitted In submittal #31.
MATERIAL
LABOR
EQUIPMENT
SUBTOTAL DIRECT COSTS
FEE ON DIRECT COSTS (15 %)
SUBCONTRACTOR SUBTOTAL
Third and Fourth Tier Sub Contractor Costs from Attached Cost Proposal
SUBCONTRACTOR SUBTOTAL
TOTAL
PREPARED $ SUBMITTED BY: Jim L - CSCI
COMPANY: TITLE:
Uption 6
$175.00
$0.00
$0.00
$175.00
$0.00
s17s.00
S17i.00
Proposed Cost Proposal
Subcontractor
Jared,
The cost for One 6' x 3' Milgard Model #1110H is $175.
Thanks,
Derick Yee
Wholesale Window Company
2200 Lafayette Street
Santa Clara, CA 95050
CA Contractor's License: 927443
EPA Lead Renovation: NAT - 34101 -1
AAMA/Installation Masters: 700006343
p: 408.654.9410
f. 408.654.9642
e: derick @wholesalewindowco.com
Project Name: San Ysidro Park Recreation Building
FIELD ORDER
City Of Gilroy
7387 Rosanna Street
Gilroy, CA 95020
FIELD ORDER NO. 11
Project Name: San Ysidro Park Recreation
Contract Date: 01/06/2012
To Contractor: Calstate Construction Inc
Address: 4165 Business Center Dr.
Fremont CA 94538
DESCRIPTION OF WORK:
Project No: 12 -PW -194
3/29/12
Furnish & Install 1 ea additional 3'x6' window to the existing rough opening on the east elevation at the kitchen /
vestibule area. Match existing new window criteria as submitted in submittal # 31.
Estimated Adjustment
of Contract Sum:
Ron Barri / PM
(Name of Construction Manager/Title - typed or printed)
By:
(Signature)
Date: 03/29/2012
Jared Perry / Project Manager
(Name of Contractor Representative/Titic - typed or printed)
(Signature)
Date:
Estimated Adjustment
of Contract Time: 0
Note: This Field Order will be superseded by an allowance adjustment or a Change Order that will include the
scope of the change in the Work and any actual adjustments of the Contract Sum.
1
Public Works Department
Project Budget Summary & Update
Updated: 5/15/2012
Proj. Name: San Ysidro Park Improvements Proj. Number: 12 -PW -194
Project Funding
Account Amount FY Notes
254
2621
4487
4340
$ 164,659
12
carry over to FY 12
254
2624
4487
4340
$ 170,000
12
carry over to FY 12
264
2624
4487
4340
$ 131,852
12
carry over to FY 12
400
2600
3370
4340
$ 416,481
12
carry over to FY 12
$297,642
CO 6
$3,475
$ 220,000
12
BA approve by Council 4/4/12
Total $ 1,102,992
Initial Total Project Budget
Grand Total Estimated Cost $ 771,744
all alternates included above
Change Orders
Amount
New Total Cost
Remaining
Budget
Comments
co 1
$10,350
$ 782,094
$320,898
CO 2
$1,329
$ 783,423
$319,569
CO 3
$4,122
$ 787,545
$315,447
C04
$7,951
$ 795,496
$307,496
CO 5
$9,854
$ 805,350
$297,642
CO 6
$3,475
$ 808,825
$294,167
CO 7
$42,276
$ 851,101
$251,891
already spent in FY 12 (Not inclding
constrt contract pmts ?)
$49,496
$ 900,597
$202,395
from Eileen's spreadsheet
CM & materials testing
$86,200
$ 986,797
$116,195
Nova contract
CO 8
$26,323
$ 1,013,120
$89,872
temp trailer hookup, misc. conc /AC
CO 9
$10,104
$ 1,023,224
$79,768
flashing, window, BBQ, ext. siding, HVAC
Note: italicised figures are estimated
Initials INA
Proj. Mngr. Finance PW Dir.