Wattis Construction - Traffic Signal Modification at Church & Tenth Streets - Change Order No. 3
City of Gilroy
Engineering Division
7351 Rosanna St., Gilroy, CA 95020
Phone (408) 846-0450; Fax (408) 846-0429
CHANGE ORDER NO.3
To contract for: Traffic Signal Modification at Church and Tenth Street, Project No 09-CDD-159
Contractor:
Wattis Construction
Contract Date:
6/25/2008
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Increase quantity for Bid Item 55 (Remove & Replace Pavement Along New Gutter
Pan) by 312 SF @ $15.75/SF
Increase quantity for Bid Item 56 (Asphalt Concrete Pavement Resurfacing) by 2436
SF @ $2.25/SF
$4,914.00
$5,481.00
TOTAL
$10,395.00
All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this
Change Order. The contract time shall not extend unless expressly provided for in this Change Order.
By signing this Change Order, Contractor acknowledges and agrees that the adjustments to cost and time contained herein
are in full satisfaction and accord, and are accepted as payment in full, for any and all costs and expenses associated with
this Change Order, (the "Extra Work"), including but not limited to labor, materials, overhead and profit, delay,
disruption, loss of efficiency and any and all other direct and/or indirect costs or expenses associated with the Extra Work
and hereby waives any right to claim any further cost and time impacts at any time during and after completion of the
Contract associated with the Extra Work.
I (We) agree to make the above change
subject to the terms of this Change Order
for the NET INCREASE of $10,395.00
Original Contract Price
Previous Change Orders
Total to Date
This Change Order
Total Change Orders to Date
Revised Contract Price
Cost
$457,590.90
$32,280.85
$489,871.75
$10,395.00
$42,675.85
$500,266.75
P.M.
Percentage Initial
7.05% ~
9.33% M
WATTIS CONSTRUCTION CO. INe
&~o~/cr
By. ';/Ai;~~ Date: /-/-77-d f
ACCEPTED BY:
RECEIVED
RECOMMENDED BY:
:::i: "
VAnlS CONSTRUCTION GO. lNG,