O'Grady Paving, Inc. - 2012 Agreement - Project No. 12-PW-196 - Change Order No. 1City of Oilrop Public Works Department - Engineering Division 7351 Rosanna St., Gilroy, CA 95020 Phone (408) 846 -0451; Fax (408) 846 -0429 CHANGE ORDER NO. 1 To contract for: Wren Avenu & Church St Resurfacing City Project No Contractor: O'Grady Construction Contract Date: 12 -PW -.196 This order shall become effective when it has been signed by the City Administrator, City Engineer, Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to the City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned to him as his authority to proceed with the work. Description of Work 1.Install temporary paint striping on Wren Ave, at Mantelli in lieu of thermoplastic for a Lump Sum of $1,115.00.(Includes a credit of $865.00 for Thermoplastic). 2.Re- layout for new crosswalks at Church St. and Lily Ave. for a Lump Sum of $685.00. 3.Refresh existing striping with paint at the intersection of Wren Ave. and 1st. for a Lump Sum of $2,480.00. All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this Change Order. The contract time shall not extend unless expressly provided for in this Change Order. By signing this Change Order, Contractor acknowledges and agrees that the adjustments to cost and time contained herein are in full satisfaction and accord, and are accepted as payment in full, for any and all costs and expenses associated with this Change Order, (the "Extra Work "), including but not limited to labor, materials, overhead and profit, delay, disruption, loss of efficiency and any and all other direct and /or indirect costs or expenses associated with the Extra Work and hereby waives any right to claim any further cost and time impacts at any time during and after completion of the Contract associated with the Extra Work. Change in working time granted by this change order: ► All Extra Work authorized under this Change Order must be billed separately from the original contract. All bills for work done under this Change Order shall reference this Change Order No. 1. I (We) agree to make the above change subject to the terms of this Change Order for a NET INCREASE not to exceed $24,727.44. X By: RECOMMENDED BY: ACCEPTED BY: I 0 Working Days Cost Percentage Initial Original Contract Price $1,144,020.00 Previous Change Orders $0.00 0.00% AW Total to Date $1,144,020.00 This Change Order $24,727.44 Total Change Orders to Date $24,727.44 2.16 %� Revised Contract Price $1,168,747.44 Date: l I Z99h Z W /9f /Z- Construction Manager Date City Administrator Date O'GRADY PAVING, INC. License #201696 Ar 2513 Wyandotte Street MOUNTAIN VIEW, CALIFORNIA 94043 (650) 966 -1926 FAX (650) 966 -1946 To City of Gilroy 7351 Rosanna Street Gilroy, CA 95020 -6197 Invoice # 12270 DATE ORDER NO 11/28/2012 12015 SHIP TO Wren Ave. & Church St. Resurf Project No. 12 -PW -196 Progress Billing FINAL SALESPERSON DATE SHtPP£D SHIPPED VIA F.O.B. POINT TERMS QUANTITY DESCRIPTION UNIT PRICE TOTAL Original Contract Amount $1,144,020.00 Change Order #1 24,727.44 Change Order #2 59,942.72 Revised Contract Amount $1,228,690.16 100% Complete Of Revised Contract Amount $1,228,690.16 Less 10% Retention -$122,869.02 Less Paid To Date $1,017,502.98 Net Amount Due This Estimate $88,3113.16 7fwj (ym