Harris & Associates, Inc.
or it!! of (1f) ilro!!
ORIGINAL
COMMUNITY DEVELOPMENT DEPARTMENT
Norman S. Allen, P.E., Director
Planning Division
Engineering Division
Building, Life & Environmental Safety Division
Housing & Community Development
(408) 846-0440
(408) 846-0450
(408) 846-0430
(408) 846-0290
FAX (408) 846-0429
FAX (408) 846-0429
FAX (408) 846-0429
FAX (408) 846-0429
December 31, 2001
CONTRACT ADDENDUM
(WORK ORDER 36)
Agreement for:
DESIGN PHASE ASSISTANCE ON THE GILROY POLICE FACILITY PROJECT
Consultant: HARRIS & ASSOCIATES, INC
Contract Agreement Date: November 10, 1998
This WORK ORDER shall become effective when the City Administrator, City Engineer, Project
Manager and Consultant have signed it. All copies forwarded to Consultant for signature shall be
returned to the City of Gilroy properly filled out. Upon acceptance by the City, the Consultant's
copy will be returned as authority to proceed with the work.
DESCRIPTION OF WORK:
Provide Project Management Services relating to the Gilroy Police Facility Project. Scope of
Services shall be as detailed in Attachment "A", consultant cost and work effort shall be as detailed
in Attachment "B". The Design Phase Services are expected to occur from October 1, 2001 through
June 30, 2002.
All requirements of the original Agreement Documents shall apply to the above work except as
specifically modified by this Addendum. The contract time shall not extend unless expressly
provided for in the Addendum.
Page 1 of2
City of Gilroy, Contract Addendum
Work Order No. 36
12/31/01
ORIGINAL
HARRIS hereby agrees to make the above
change subject to the terms of this Addendum
for the NET INCREASE OF $97,280
Original Agreement Price
i (Master Contract)
CONSULTANT:
By: ~~Cf-- ~ 1 ~J.s
Patrick Dobbins, Associate
Total Addendum to Date
Total Amendments to Date
CONTRACT TODATE
$2,774,768
$ 219,058
$2,993,826
This Addendum
$ 97 ,280
$3,091,106
Date: ~ 3 I z..oO z,.
.
REVISED AGREEMENT
ACCEPTED BY:
Date
Originals: (2) - City Clerk
Consultant
Copies: (2) - Purchasing
File
Page 2 of2
K:\ProgrmMt\Gilroy\WO 36 PoliceDept\Addendum 36.doc
ATTACHMENT "A"
ORIGINAL
SCOPE OF SERVICES
POLICE STATION PROJECT - PLANNING AND DESIGN MANAGEMENT
WORK ORDER No. 36
2.1 Design Phase Services (October 2001 through June 2002)
2.1.01 Project Design Meetings - HARRIS will attend progress meetings with CLIENT staff and the
design professional.
2.1.02 Architectural Coordination - HARRIS will exchange project information between the
CLIENT project management staff and design professional.
2.1.03 Review Design Documents - HARRIS will review design documents at 30% and 60% of
Design Development. HARRIS will make recommendations to the CLIENT and design
professional as to clarity and consistency with the CLIENT direction and needs of general
method of operation.
2.1.04 Scheduling - HARRIS will assist in the preparation of a CPM schedule highlighting known
milestone dates and specified sequence of work for the project delivery of two bid packages.
2.1.05 Construction Strategies - HARRIS will assist with the development of prequalification
requirements of contractors and alternate project delivery. HARRIS will review submitted
prequalification documents and participate in contractor interviews.
2.1.06 Cost Control & Review of Designer's Cost Estimates - HARRIS will review design
professional cost estimates. HARRIS will supply written comments to the CLIENT and
design professional on the acceptability of the cost data at end of Design Development, 30%
of Construction Documents, 60% of Construction Documents and 90% of Construction
Documents.
2.1.07 Biddability/Constructability Review - HARRIS shall review the Construction Documents at
60% and 90%. Make recommendations in writing to the CLIENT and design professional
as to biddability and constructability, cost, sequencing, scheduling and time of construction,
clarity, consistency, and coordination of documentation among the contractor, and as to the
separation of the project into construction contracts for various categories of the work.
In making reviews and recommendations as to design documentation or design matters,
HARRIS shall not be responsible for providing nor will HARRIS have control over the
project design, design requirements or the substance or contents of the design documents.
By performing the reviews and making recommendations described herein, HARRIS shall
not be acting in a manner so as to assume responsibility or liability, in whole or in part, for
any aspect of the project design, design requirements, design criteria or the substance or
contents of the design documents. HARRIS' actions in making such reviews and
recommendation as provided herein are to be advisory only to the CLIENT and to the design
professional.
Page 1 of 1
K:\ProgrmMt\Gilroy\WO 36 PoliceDept\Attachment A_36]olice Dept.doc
OR\G\NAL
ATTACHMENT "B"
CITY OF GILROY - CAPITAL IMPROVEMENT PROGRAM
WORK ORDER No. 36 - POLICE FACILITY PROJECT
k/prgrmmgmtlgilroy, wo34! Attachment B _ 36 _Police Dept.xls
Biddability &
Constructability Reviews
Project Manager
Administrative
300 hrs @
20 hrs @
$140
$70
TOTAL COST NOT TO EXCEED =
ASSUMPTIONS
The above estimate is prepared with the following assumptions:
Costs are based on current hourly rates. Rates may be adjusted only pursuant
to Article 4 of that Agreement for Professional Services by and between CITY
and CONSULTANTS dated November 10,1998.
2 The total project construction cost are estimated to be $19,600,000.
3 Work will be completed according to schedule provided by the Design Professional
assuming a 43 week duration commencing in the second half of 200 1.
ORiGiNAL
$42,000
$1 ,400
$97,280
4 The new building square footage is to be 47,600. The below grade parking is 130,500 sq. ft.
with 4,700 sq. ft. of detention facility space within the below grade garage.
5 Design Professional will prepare and distribute all meeting minutes.
k/prgrmmgmtlgilroY,wo34/ Attachment B _ 36 _Police Dept.xls
..
..
Harri s & Associ ates
January 3, 2002
Program Managers
Construction Managers
Civil Engineers
Bill Headley, Parks and Facility Manager
City of Gilroy
7351 Rosanna Street
Gilroy, CA 95020
Re: Work Order No. 36 for Design Phase Assistance on the Police Facility Project
Dear Bill,
Attached are an original and duplicate original of Work Order #36 for your consideration.
If the attached work order and backup is acceptable, please approve by executing both the
original and duplicate original and return one fully executed wet signature copy for our files.
Should you have any questions, please give me a call at 842-5777.
Sincerely,
HARRIS & ASSOCIATES
~~~Cf- ~)N<S
Patrick Dobbins
Project Manager
cc: Neil McCosker, Vice President
File: Admin. - Work Order binder
K:\ProgrmMt\Gilroy\ WorkOrderNo.31 \CoverLtr.doc
178 Second Street, Suite C Gilroy, California 95020 408.842.5777 FAX 408.842.5758 gilroy@harris-assoc.com
...; D 1
March 20, 2002
ORIGINAL
..
..
Mr. Bill Headley, Parks & Facility Manager
City of Gilroy
7351 Rosanna Street
Gilroy, CA 95020
Harri s & Associ ates
RE: POLICE FACILITY
Contract Amendment No.1 to Work Order No. 36
Program Managers
Construction Managers
Civil Engineers
Dear Bill:
As requested by the City, we prepared this amendment to Work Order No. 36 for additional management
services. The additional services are:
1. Preparation of a Master Schedule for the Civic Center Master Plan, Police Facility Design, and the
Community Library Design and Grant Application. This effort includes schedule updating and tracking.
2. Coordination with City Design Consultants to maintain the master schedule critical path obligations and
milestone deadlines for the Civic Center Master Plan Project.
As shown on the attached spreadsheet, this contract amendment totals $49,280. If this scope and fee is
acceptable, please authorize by signing below and the attached duplicate original. Please return one fully
executed wet signature original for our record, as our authorization to proceed.
Sincerely,
HARRIS & ASSOCIA lES
p-Iftlt C{L
.
~/1\I~
Patrick Dobbins, PE
Project Manager
Attachment: Spreadsheet
Copy of Original WO No. 36
- ..
ACCEPTED BY:
Date
UJ~
K:\ProgrmMt\Giiroy\Amendments\Revised Amend 1 to WO No. 36.doc
178 Second Street, Suite C Gilroy, California 95020 408.842.5777 FAX 408.842.5758 gilroy@harris-assoc.com
=
CI
.-
~
I:J
=
~
~ ~
~8
" ~
o ~
~~
~ =
E-o ~
Z 5
~t:
~ ell
~~
>-'""'
o ~
~=
~ CI
~~
'""'
~~
-< .
E-i CI
,"",Z
~ ~
< ~
u'E
,0
>~
o ~
~ CI
~~
~ CI
,,~
~'"':
o CI
~Z
E-i -=
~ ~
u 5
"0
=
~
5
<
N
o
o
N
0"
N
...c
u
...
ro
::E
~
=
'""'
~
~
E-o
'""'
~~
~~
~~
00
r:..u
~~
~Z
~<
~~
~E-o
='""'
u~
00,"",
~u
~<
E-or:..
oo~
<u
~::s
<0
r:..~
Oz
Z<
O~
'""'~
E-o~
~~
<E-o
~oo
~~
~~
~
E-o
Z
~
U
U
'""'
>-
'""'
u
I
g ~I~~!
NooNN
,....: an" N.... 0\"
- ('<) ~
{A {A {A {AI
II I
il
\O!
-I
1
I
><:i
01
~~l
N1
!
I
{AI
II
-
S
~
II II
000
~~t--
- - {A
{A (A
@)@)@)
~ ~I~
.E .Ei.E
ol\OIN
00 -,('<)
~
<':>
ell
-=
~
=
I~i
!~I
I a)'
I~I
,......,I~I,
s:: '-'I
o a) i
'_1 UI
~a
t+:: s::
,_ a)
"'01::
o .-
6~1t::
S::"'010
o s:: 0..
'.;:l cd g.
E ~ICI)
cd cdl Q)
0.. "'0 1 ;>
a) 0..1'-
~.....,~
p..."""'I~
a) a) I .....
"3 "31'a
"'0 "'0 I .....
Q) a)1 E
..c ..c I' "'0 I
~~<
.-
<':>
~
~
...
~
s::
.9
.....
0..
~
~
~
cd
OJ)
s::
.~
...s
;B
a)
..c
.....
..s
.~
"'0
a)
~
e-
a)
0..
.~
a)
~
.S
.....
~
a)
Q)
~
a)
;>
o
~
~
E--
~
s::
o
.....
~
~
~
o
~
~
~
tE
1::
a)
E
a)
a)
~
OJ)
<
a)
..s
<+-<
o
~
a)
.-
U
'-2
<
000
.....0'1
.....;:::
a
::s o~
~
!3 ~
0..]
.bE
s:: a)
o ;>
]z
tl"'O
::s Q)
:.a'~
cd "'0
a)CI)
.DE--
~z
E~
~....:l
~:::J
~z
<Ii 0
~u
cd "'0
~a
]>-
..8t
1::u
Q) s::
~ ~
U ~
s:: a)
0.D
"'0"'0
~ a
cd >.
.D.D
a) ~
~ a)
cd U
~ .....
tl c;
o a)
UCl)
..
00
z
o
'""'
E-o
~
~
00
00
<
N
o
o
N
o~
('<)
a)
s
.......
"'0
a
N
o
o
N
~
.-
-
~
::s
~
.D
a)
~
s::
a)
~
.....
a)
.D
a)
~
0..
~
.....
.-
.-
.~
OJ)
s::
.~
"'0
0..
::s
"'0
a
s::
o
'.g
~
0..
a)
~
0..
Q)
"3
"'0
~
U
~
a)
..c
E--
N
~
t::
l-8
4-<
a)
1)
::s
"'0
o
~
0..
~
~
~
"'0
a
~
t::
l-8
4-<
a)
~
1::
cd
.....
"3
~
s::
o
U
o
U
Q)
~
s::
~
~
o
o
u
:::::
.~
~
a)
~
'u
o
~
~
<
"'0
s::
cd
~
.~
::c
('<)
ORIGINAL
<Ii
OJ)
s::
.....
.....
a)
a)
:E
s::
o
'r;;
~
's
E
o
u
OJ)
s::
.~
ii:
"'0
a
U
.;;
U
a)
..c
.....
.....
U
~
4-<
a)
~
..s
~
~
.....
"3
~
s::
o
U
o
U
a)
..c
.....
>.
.D
"'0
Q)
~
0..
a)
~
0..
~
.....
U
::l
"'0
o
~
0..
~
~
~
a)
;>
o
~
0..
~
~
o
~
Q)
.;;
~
.....
2
'"
x
<0
(")
o
~
B
......
o
'0
c:
CIl
E
::;;
'"
c
CIl
E
'0
c:
CIl
E
~
~
o
<5
~
:2:
E
ro
01
o
~
~
.-
.-
U
s::
::l
o
U
o
U
<+-<
o
s::
o
'.g
~
0..
a)
~
0..
.5
~
t::
o
0..
a)
~
It::
cd
.....
CI)
o
U
~
~
0..
~
0..
.-
.-
.~
00
Q)
~
.....
U
o
~ .....
00 U
<,~
"'0 8
1a p...
~ ~
.~ ~
::cu
.-
.-
.~
It::
cd
.....
CI)
o
U
~o
V'\
Planning Division
Engineering Division
Building. Life & Environmental Safety Division
Housing & Community Development
arti!! of Q?;i!rl1!! ~~~TE~
COMMUNITY DEVELOPMENT DEPA~<<~--:J\\:>
Norman S. Allen, P.E., Director U /J
(408) 846..Q440 FAX (408) 846-0429
(408) 846~0450 FAX (408) 846-0429
(408) 846-0430 FAX (408) 846-0429
(408) 846-0290 FAX (408) 846-0429
CONTRACT ADDENDUM
December 31, 2001
(WORK ORDER 36)
Agnilement for:
DESIGN PHASE ASSISTANCE ON THE GILROY POLICE FACILITY PROJECT
Consultant: HARRIS & ASSOCIATES, INC
Contract Agreement Date: November 10, 1998
This WORK ORDER shall become effective when the City Administrator, City Engineer, Project
Manager and Consultant have signed it. All copies forwarded to Consultant for signature shall be
returned to the City of Gilroy prop'erly filled out. Upon acceptance by the City, the Consultant's
copy will be returned as authority to proceed with the work.
DESCRIPTION OF WORK:
Provide Project Management Services relating to the Gilroy Police Facility Project. Scope of
Services shall be as detailed in Attachment "A", consultant cost and work effort shall be as detailed
in Attachment "B". The Design Phase Services are expected to occur from October 1, 2001 through
June 30, 2002.
All requirements of the original Agreement Documents shall apply to the above work except as
specifically modified by this Addendum. The contract time shall not extend unless expressly
provided for in the Addendum.
Page 1 of2
City of Gilroy, Contract Addendum
Work Order No. 36
12/31/01
DUPl..JCA.11:
OIiIGI/ti..4i. '
"
\
HARRIS hereby agrees to make the above
change subject to the terms of this Addendum
for the NET INCREASE OF $97,280
Original Agreement Price
. .
i (Master Contract)
.......-'
Total Addendum to Date
Total Amendments to Date
CONTRACT TO DATE
$2,774,768
$ 219,058
$2,993,826
$ 97,280
$3,091,106
CONSULTANT:
l~...
By: ~~q~;~)~I'N..s
. Patrick Dobbins, Associate
This Addendum
Date: ~ ~ I 2..00 2-
REVISED AGREEMENT
ACCEPTED BY:
, ,--.I
Date
Originals: (2) - City Clerk
Consultant
Copies: (2) - Purchasing
File
Page 2 of2
K;\PrognnMt\Gilroy\WO 36 PoliccDept\Addendum 36.doc
ATTACHMENT "A"
. DUp.
'i..ICA:rj2
OIiIGIiVAJ..
SCOPE OF SERVICES
POLICE STATION PROJECT - PLANNING AND DESIGN MANAGEMENT
WORK ORDER No. 36 .
2.1 Design Phase Services (October 2001 through June 2002)
2.1.01 Project Design Meetings - HARRIS will attend progress meetings with CLIENT staff and the
design professional.
2.1.02 Architectural Coordination - HARRIS will exchange project information between the
CLIENT project management staff and design professional.
2.1.03 Review Design Documents - HARRIS will review design documents at 30% and 60% of
Design Development. HARRIS will make recommendations to the CLIENT and design
professional as to clarity and consistency with the CLIENT direction and needs of general
method of operation.
2.1.04 Scheduling - HARRIS will assist in the preparation of a CPM schedule highlighting known
milestone dates and specified sequence of work for the project delivery of two bid packages.
2.1.05 Construction Strategies - HARRIS will assist with the development of prequalification
requirements of contractors and alternate project delivery. HARRIS will review submitted
prequalification documents and participate in contractor interviews.
2.1.06 Cost Control & Review of Designer's Cost Estimates - HARRIS will review design
professional cost estimates. HARRIS will supply written comments to the CLIENT and
design professional on the acceptability of the cost data at end of Design Development, 30%
of Construction Documents, 60% of Construction Documents and 90% of Construction
Documents.
2.1.07 Biddability/Constructability Review - HARRIS shall review the Construction Documents at
60% and 90%. Make recommendations in writing to the CLIENT and design professional
as to biddability and constructability, cost, sequencing, scheduling and time of cOIlstruction,
clarity, consistency, and coordination of documentation among the contractor, and as to the
separation of the project into construction contracts for various categories of the work.
In making reviews and recommendations as to design documentation or design matters,
HARRIS shall not be responsible for providing nor will HARRIS have control over the
proj ect design, design requirements or the substance or contents of the design documents.
By performing the reviews and making recommendations described herein, HARRIS shall
not be acting in a manner so as to assume responsibility or liability, in whole or in part, for
any aspect of the project design, design requirements, design criteria or the substance or
contents of the design documents. HARRIS' actions in making such reviews and
recommendation as provided herein are to be advisory only to the CLIENT and to the design
professional.
Page 1 of 1
K:\PrognnMt\Gilroy\ WO 36 PoliceDept\Attachment A_36]olice Dept.doc
ATTACHMENT "B"
DUp
LIQ,q 1'/2
OAIG/,..
· lfA.l.
CITY OF GILROY - CAPITAL IMPROVEMENT PROGRAM
WORK ORDER No. 36 - POLICE FACILITY PROJECT
k/prgrmmgmt/gilroy,wo34!Attachment B_36_Police Deptxls
Biddability &
Constructability Reviews
Project Manager
Administrative
'']1 ,
....v,':.JJ I~
~ v~r€"O'
If:.t!("'; Ii!..
~"~4(
300 hrs @
20 hrs @
$140
$70
$42,000
$1,400
TOTAL COST NOT TO EXCEED =
$97,280
ASSUMPTIONS
The above estimate is prepared with the following assumptions:
1 Costs are based on current hourly rates. Rates may be adjusted only pursuant
to Article 4 of that Agreement for Professional Services by and between CITY
and CONSULTANTS dated November 10, 1998.
2 The total project construction cost are estimated to be $19,600,000.
3 Work will be completed according to schedule provided by the Design Professional
assuming a 43 week 'duration commencing in the second half of 2001.
4 The new building square footage is to be 47,600. The below grade parking is 130,500 sq. ft.
with 4,700 sq. ft. of detention facility space within the below grade garage.
5 Design Professional will pre:iare and distribute all meeting minutes.
klprgrmmgmtlgilroy.wo341Attachment B _36 _Police Dept.xls
ar it!! of Q?; ilro!!
COMMUNITY DEVELOPMENT DEPARTMENT
Norman S. Allen, P.E., Director
Planning Division
Engineering Division
Building, Life & Environmental Safety Division
Housing & Community Development
(408) 846-0440
(408) 846-0450
(408) 846-0430
(408) 846-0290
FAX (408) 846-0429
FAX (408) 846-0429
FAX (408) 846-0429
FAX (408) 846-0429
August 26, 2002
CONTRACT ADDENDUM
(WORK ORDER 46) - Revision 2
AGREEMENT FOR: PROFESSIONAL ENGINEERING SERVICES FOR CONSTRUCTION MANAGEMENT-
GILROY POLICE FACILITY SITE DEMOLITION
Consultant: HARRIS & ASSOCIATES. INC
Contract Agreement Date: November 10.1998
This WORK ORDER shall become effective when the City Administrator, City Engineer, Project
Manager and Consultant have signed it. All copies forwarded to Consultant for signature shall be
returned to the City of Gilroy properly filled out. Upon acceptance by the City, the Consultant's
copy will be returned to him as his authority to proceed with the work.
DESCRIPTION OF WORK:
Provide Construction Management and Inspection Services relating to Gilroy Police Facility Site
Demolition Project. The Scope of Services shall be as detailed in Attachment "A", consultant cost
and work effort shall be as detailed in Attachment "B".
All requirements of the original Agreement Documents shall apply to the above work except as
specifically modified by this Addendum. The contract time shall not extend unless expressly
provided for in the Addendum.
City of Gilroy, Contract Addendum
Work Order No. 46 - Revision 2
August 26, 2002
Original Agreement Price
.$. (Master Contract)
HARRIS hereby agrees to make the above
change subject to the terms of this Addendum
for the NET INCREASE OF $ 13,620.00
Total Addendum to Date
Total Amendments to Date
TOTAL TO DATE
This Addendum
By:
Date:
REVISED AGREEMENT
ACCEPTED BY
ItA
Parks & Facihties Manager
Originals: (2) - City Clerk
Consultant
Copies: (2) - Purchasing
File
Date
$4,974.721
$ 219,058
$5,193,779
$ 13,620
$5.207.399
Page 2 of2
August 26, 2002
ATTACHMENT" A"
SCOPE OF SERVICES
POLICE FACILITY SITE DEMOLITION
WORK ORDER No. 46 - Revision 2
2.2 PRE-CONSTRUCTION PHASE SERVICES
2.2.01 Bidding Assistance - Assist in the development of bidder interest and distribution of the
construction documents.
2.2.05 Bid Review - Prepare detailed bid tabulation, review all bids for conformance to contract
requirements, and report on low bidders acceptability.
2.2.09 Pre-Construction Conference - HARRIS shall organize, attend and record the pre-
construction conference.
2.3 CONSTRUCTION PHASE SERVICES
2.3.01 On-Site Management & Construction Phase Communication Procedures - HARRIS shall
provide and maintain a management team to provide contract administration as an agent of the
CITY. HARRIS shall establish and implement coordination and communication procedures
among CITY, HARRIS, Design Professional and Contractor.
2.3.03 Reports - Prepare correspondence and reports that may be required during the
construction phase. Prepare monthly reports to CITY.
2.3.07 Progress Pavment Preparation and Processing - HARRIS will prepare monthly progress
payment requests for submission to CITY based on Contractor's construction progress.
2.3.08 Change Order Preparation. Negotiation and Processing - Prepare independent statement
of probable construction cost for contract change orders. Negotiate contract change orders with
the contractor. Prepare contract change order document for execution by Contractor and CITY.
2.3.09 Minor Variations in the Work - HARRIS may authorize minor variations in the Work
from the requirements of the contract Documents that do not involve an adjustment in the
contract price or the contract time and which are consistent with the overall intent of the Contract
Documents. CITY shall provide to the Design Professional copies of such authorizations.
August 26, 2002
Attachment "A" - Work Order No. 46 - Revised
Police Facility Site Demolition
2.3.18 Ouality Review - Except for minor variations, HARRIS is not authorized to change,
revoke, alter, enlarge, relax or release any requirements of the Contract Documents or to approve
or accept any portion of the work not performed in accordance with the Contract Documents.
Communication between HARRIS and Contractor with regard to Quality Review shall not in any
way be construed as binding CITY or HARRIS as releasing the Contractor from the fulfillment
of any of the terms of his Contract Documents. HARRIS will not be responsible for, nor does
HARRIS control the means, methods, techniques, sequences and procedures of construction for
the Project. It is understood that HARRIS' action in providing Quality Review, as stated herein,
is a service to the CITY and by performing as provided herein, HARRIS is not acting in a
manner so as to assume responsibility or liability, in whole or in part, for all or any part of the
construction work for the Project. No action taken by HARRIS shall not relieve any or all ofthe
Contractors from their obligation to perform their work in strict conformity with the Contract
Documents and in strict conformity with all other applicable laws, rules and regulations. Not
withstanding the above, HARRIS is not relieved of any liability in the event it fails to properly
perform its duties, to manage construction activity for the project as permitted by the time
allotted by the CITY and the attached fee proposal, and to give notice to the CITY, of defects
and deficiencies in the work of the Contractors, all is set forth in this section.
2.3.19 Photographs and Videos - Provide videotape and photographic documentation of project
site prior to and during construction.
2.3.29 Field Inspection - Provide field inspection services to verify substantial compliance with
the contract documents.
2.5 FINAL ACCEPTANCE/CLOSEOUT SERVICES
2.5.04 Final Inspection and Punchlist - Provide final inspection and prepare list of deficiencies
for resolution by Contractor.
2.5.05 Construction Approval/Acceptance - Make recommendations to owner regarding final
project approval and acceptance.
2.5.11 Final Report - HARRIS will provide CITY with a final report for the project.
Page 2 of2
KIProgrmMtlGilroylWO 46 PD DemolAttachment A-46 Revision No. 2.doc
~
::::
Q
'\:l
.~
~
l:l::
I
'"
~
C.I
'E ~
~ = ~
00 0...
--= r.J
~ ~
S<M
~~8
~ '" M
.-= .C ~
oo;M
...=~
:.= .-.. ~
'c::l ,.Q =
~"l:l<
j;;J;, ~
~ t:
.~ .-
'0 S
=-~
00
...
=
= ~
~ S
Z~
~ ~
=
~ ~
=~
U =
< .S
~...
~ C.I
< e
...
'"
=
o
U
..
~
~
'"
o
Q.
o
..
=-
...
'"
o
U
0 0 0 0 0 0 0 0
0 0 , , , 0 0 0 0 0 0
= = = = = iii = =
N 0 QO '" 0 ..,. 1&1 1&1
..,. t- t- "l. 0 QO N N
III N
'" '" '" '" '" '" '" '" '" '" '"
. 0 '" '" a 0 a a a 0 0 0 0 0 0 0 0 '" or) 0 ~ 0 0 III III 0 ~I
..; '" c;:; c;:; iii or; c;:; c;:; = = = 'J:i ~ 0 ... S - or; 0; '" N 0 ~ ~ M
..,.
0 0 0 0 0 0 III '" a 0 I
= = = = = = M c;:; '" 0
0 0 0 0 0 0 0 0 I
0 = = = = 0 = =
0 0 0 0 0 0 0 0 I
= = = = = = = =
0 0 a 0 0 0 0 a III '" '" a '" a a III '" SI
= ... .....; = = = ... .....; ... '" .....; '" c;:; .....; '" = c;:;
...
III '" 0 a 0 0 0 0 a 0 a '" a '" a a 0 a 51
0 c;:; ... .....; = = = .. .....; = '" '" c;:; .....; '" M '"
... .....
III '" 0 a 0 0 0 0 a In a a 'F) 0 a I
= c;:; ... .....; = = = ... .....; M .....; .....; c;:; M '"
In 'F) 0 a 0 0 0 0 a 0 'F) 'F) a 'F) 'F) 0 0 I
= c;:; ... .....; = = = ... ..... Cl\ '" .....; '" c;:; '" ... ...
In 'F) 0 a 0 0 0 0 a In a 'F) a 'F) 'F) 0 0 I
= c;:; ... .....; = = = ... .....; iii .....; ..... .....; c;:; .....; ... ...
0 'F) 'F) 0 0 0 0 0 a 0 0 0 I
... c;:; c;:; = = = = ... .....; = 0 =
. 0 0
0 0
0 0
:! ::
<A <A
....
'"
"
==
"
].
0..-;
= '"
Q ..':l ~
~ ':l Cl..
'E s " 'ii 'E =
"
Q E 0() Q Q
~ ':l ~ .~
'" = ~ '" '" ~ ~
'B< i! Q .$ i! '" Q .$
1 '" '" ~ .... ol$ ... c C) ~ "Cl
tj;j '" ~ c '" '2 ~ .S1 ~ ~ '" ~ ..
c -= ;;: 2 "" -=
S Q ~ "" C) " c " = Q
~ " ;;; G- " ;;: Q
G- " t; " " Q ~ " " ~ ~ ~ Q
.. ~ C) ~ '0 ':l U C) e !:: c C) ..E; ~ U
~ '" '" ." '" c ~ '" ." r '" ;:) '0
i " ~ 6' S! 0() '" = ol$ i " 6' .. '" S! '" c is ~ ol$
0() ~ ~ '" l ~ 0() ~ (3 '" !:: l
~ c ... = } ~ ':l ~ ... = } '" " ~ ;e =
Cl.. S Cl.. ... == ~ '" ~
~ is c ; '" ~ ~ ~ is '" ; is ~ 6- '" c ~ '" ~ Q
U '" ... '" .~
.~ c ::E c c ;:< ':l .... .~ c ::E .~ c ;:< U c ~
.... " U ~ = ... U Cl.. U ;;: i
" ~ '" ~ Ii " ~ a '" '" " ~ Ii
.. ~ .;::; = " '" s " t; c '" .;::; ";l = "
..... '" .S1 S t; J5 ; ..... C) C) '" '" '" ; '"
E <J ;; :.::: " t; .. Q :.::: " ~ ~ t; == ] 'i:i .::
~ ':l .:: .. ~ ... ':l ~ 0() <J
... !:: ~ ~ '" !:: " '& ;:< ~ ... ~
~ '" c " 8 ." ..s ~ c i ~ ..s
~ '" ;} E '" 6' ~ ;} ~ " '" ~ <J C
~ C C ~ "'" c ... ... c " " c
... ~ .!:; .!:; .!:; "
.!:; u ~ u u Cl.. " ~ u u Cl.. Cl.. C) .. = u
'" := .... :=
.. S .~ ~ " Q = .~ ~
i> ~ i> " ..
0 U Eo< 0 U ~ Eo< '" ~
..
'" <=
OJ) '"
'" ~ 0
:€ '~'B ~
....< ::os o:l ~ ~
i:Q 'G .E <= ::os
'" ~ 0
'0' U
P::
E
~
;;;
N
C
N
N
oc
"0
~
;;
'"
i:>::
'D
'T
o
~
o:l
~
o
0-
2
"-
I/:;
o
I
..
0-
:;;;
""
::
~
.~
.~
~
~
I
'"
~
IJ
'E ~
~ = ~
rJ1 .s ..
.... IJ
:= ~
o '"
S-<M
~~g
M
~.C ~
OOl-<M
~ ....
....='"
:5 ~ ~
IJ'c:I
~"C:l-<
li<; ~
~ t:
... 's"
=:
~~
00
....
=
= ~
~ S
Z~
r-:l ~
~ ;
=~
U =
-< .S
~....
~ IJ
-< E
....
'"
=
o
U
l-<
~
-;
'"
o
Q.
o
l-<
~
....
'"
o
U
.
.
c:
~I
~I
I
I
31
~I
~I
~I
~I
~I
c:
-
o
o
or)
t'-
fA
s
;l
,;
:~
~
....
...
0=
...
-=
o
U
s::
c
~
g
.,
".,
~
~ "~
'" .,
0: OJ
'" <>
~ ~
s:: Cl,
~ ~
s:: "
c ~
t '"
" ~
E ;::
5 ~
~ ~
.~ ~
is' <>
~ ~
~ ~
:::S o:i .~ '5
oj ;>-, tl t;
.- 8'8 'c;j
.9 .:J .- <IJ
on CIl F: <r;
. !:I f3
:> ~
:5 0 <=
00<=
""0=
""'.0 M
NI.l:l
-('f~
....
fA~GI'l
~ g.,,;
u ~ 'S
6 :::s ~
~ 'if ~
-:l S ;
15 '" l-<
1-< .g,"
~
1
u
'"
"
]
"
<Ll
'0
<Ll
o
>-
~
....:l
G
~
o
~
U
~
.....
-=
~
Cl)
~
.0
]
.s
'"
Cl)
u
'E
Cl)
00
~
=
o
...
'"
'"
~
8
p..
I-<
c.9
t1
Cl)
S
Cl)
~
.s
<+-0
o
'1'
Cl)
-
~
.9
t1
~
:=
'"
8-
..Q
=
o
"t:l
Cl)
.....
'"
:=
€'.
~~
Cl)0\
.0 -
~o"
S::
~ Cl)
~1
<Ii 6
~z
I-< -g
..Q~
~"t:l
.,goo
t1~
Cl)<
1::-
:=U
uO
-=00
000
"t:l<
~I~H
S ~ ~
:I 0
",U"t:l
.<.....a
t::
~
Cl)
-=
o
';:1
e
Cl)
'"
.g
S
S
'S
's
"t:l
=
<I:l
=
o
...
~
I-<
.g
H
~
o
u
-=
o
.~
'"
=
o
u
=
o
"t:l
Cl)
'"
<I:l
.0
Cl)
~
'"
=
.S ~
uE-<
Cl) ......
'Q'U
6..s
~"t:l
o Cl)
-9 ~
a 6<
~ ~
N ~
~
'"
o
0..
8
0..
Cl)
~
'"
:g
-=
...
"t:l
Cl)
]
.s
=
Cl)
Cl)
.0
'"
<I:l
-=
Cl)
~
o
-
~
S
'€
Cl)
o
o
Z
r-)
-0
Cl)
]
g
...
.....
o
=
'"
...
N
o
o
N
I-<
Cl)
'S
Cl)
u
Cl)
o
<+-0
o
21
~
~
.....
"t:l
-=
o
~
.0
Cl)
~
=
.S
~
~
u
'"
~
.,t
~
o
-
'"
.E
0..
Cl)
~
~
"t:l
Cl)
u
...
o
6
...
'"
...
~
"2l
'"
=
o
U
~
u
'S
-=
u
Cl)
.....
o
~
tri
'1'
N
00
o.
\0
-
~
..Q
Cl)
~
s
.~
o
I-<
0..
~
'"
...
.....
'"
o
u
-=
o
...
.....
u
S
'"
=
o
u
.....
u
Cl)
'0'
I-<
0..
Cl)
-=
E-<
o
'"
~
"t:l
~
21
Cl)
~
u
o
0\
",.
~
S
M
i:i
o
...
~
I-<
:=
Ci
U
Cl)
'8'
p..
"t:l
Cl)
S
:=
'"
'"
<
r--:
N
o
o
N
0\
N
t;:;
J:
....,
.0
-g
~
0..
...
u
'E
<I:l
.~
I-<
o
.....
u
i::
t1
o
U
.9
"t:l
Cl)
Cl)
u
o
I-<
p..
o
.....
Cl)
.::l
c:
Z
'"
t>
Cl)
'8'
p..
00
ui
~
Cl)
~
.....
r:/J
"t:l
a
~
I-<
Cl)
"t:l
Cl)
~
-
~
-s
.~
Cl)
u
a
"t:l
I-<
o
U
U
<I:l
.S
=
o
...
~
~
Cl)
'"
.g
"t:l
=
<I:l
.s
.....
'"
Cl)
.....
~
~
Cl)
I-<
3
I-<
Cl)
~
s
("oJ
-0
Cl)
'"
'"
Cl)
u
o
I-<
0..
"t:l
a
"0
.~
.....
o
bJ)
Cl)
;:::
Cl)
.0
o
.....
.~
I-<
Cl)
"t:l
I-<
o
Cl)
bJ)
=
<I:l
-=
U
~
'"
'i<
N
o
N
N
oc
.",
~.
;;:
<Ll
~
'"
::1:
'-'
;s
OJ
~,
o
0-
o
....
0..
'"
::l
o
"t:l
I-<
<I:l
N
.a
-
~
Cl)
"t:l
.~
I-<
0..
.....
U
<I:l
I-<
.....
=
o
U
V-
i
....
0-
3;2
::::
.~
.c
U
Cl)
-=
E-<
0\
""'
-
'-'
Cl)
=
o
o
-
;::II
'-'U
-?biit~ of ~ilro~
COMMUNITY DEVELOPMENT DEPARTMENT
Norman S. Allen, P.E., Director
Planning Division
Engineering Division
Building, Life & Environmental Safety Division
Housing & Community Development
(408) 846-0440
(408) 846-0450
(408) 846-0430
(408) 846-0290
FAX (408) 846-0429
FAX (408) 846-0429
FAX (408) 846-0429
FAX (408) 846-0429
November 6,2002
CONTRACT ADDENDUM
(WORK ORDER 48) - Revised
AGREEMENT FOR: PROFESSIONAL ENGINEERING SERVICES FOR CONSTRUCTION MANAGEMENT-
SITE AND UTILITY IMPROVEMENTS FOR NEW GILROY POLICE STATION
Consultant: HARRIS & ASSOCIATES. INC
Contract Agreement Date: November 10. 1998
This WORK ORDER shall become effective when the City Administrator, City Engineer, Project
Manager, and Consultant have signed it. All copies forwarded to Consultant for signature shall be
returned to the City of Gilroy properly filled out. Upon acceptance by the City, the Consultant's
copy will be returned to him as his authority to proceed with the work.
DESCRIPTION OF WORK:
Provide Construction Management and Inspection Services relating to the Site & Utility
Improvements for the New Gilroy Police Station Project. The Scope of Services shall be as detailed
in Attachment "A", consultant cost and work effort shall be as detailed in Attachment "B" and "C".
Term of this WORK ORDER shall be from December 2002 through March 2003.
All requirements of the original Agreement Documents shall apply to the above work except as
specifically modified by this Addendum. The contract time shall not extend unless expressly
provided for in the Addendum.
City of Gilroy, Contract Addendum
Work Order No. 48 - Revised
November 6, 2002
HARRIS hereby agrees to make the above
change subject to the terms of this Addendum
for the NET INCREASE OF $ 124,180
Original Agreement Price
i (Master Contract)
$4,974,696
$ 328.043
$5,302,739
$ 124.180
$5.426.919
CONSUL T ANT:
BY:~' ~
Larry Ti er, Vice President
Total Addendum to Date
Total Amendments to Date
TOTAL TO DATE
This Addendum
Date: / /. ? 0 2.
REVISED AGREEMENT
ACCEPTE
Date
(U, i ~ ~
/I ~tI;L,
ate
Originals: (2) - City Clerk
Consultant
Copies: (2) - Purchasing
Pile
Page 2 of2
November 6, 2002
ATTACHMENT" A"
SCOPE OF SERVICES
WORK ORDER NO. 48 - Revised
SITE & UTILITY IMPROVEMENTS FOR NEW POLICE STATION
2.2 PRE-CONSTRUCTION PHASE SERVICES
2.2.09 Pre-Construction Conference - HARRIS shall prepare an agenda and attend the
preconstruction conference prior to the start of any field activities.
2.3 CONSTRUCTION PHASE SERVICES
2.3.01 On-Site Management & Construction Phase Communication Procedures - HARRIS
shall provide and maintain a management team to provide contract administration as an agent
of the CITY. HARRIS shall establish and implement coordination and communication
procedures among CITY, HARRIS, Design Professional and Contractor.
2.3.02 Progress Meetings - HARRIS will organize attend and record construction progress
meetings.
2.3.03 Reports - Prepare any correspondence and reports that may be required during the
construction phase. Prepare monthly reports to CITY.
2.3.04 Submittal Processing and Review - HARRIS will establish, implement and coordinate
system of submittal processing and review.
2.3.05 Schedule Review - HARRIS will review Contractor's initial schedule and monthly
schedule update and provide written comments.
2.3.06 Field and Laboratory Testing Services - HARRIS will provide, schedule, manage and
coordinate the field-testing of installed materials and laboratory testing, using laboratory
methods, test construction materials to monitor substantial compliance with the contract
documents.
2.3.07 Progress Payment Preparation and Processing - HARRIS will prepare monthly
progress payment requests for submission to CITY based on Contractor's construction
progress.
2.3.08 Change Order Preparation. Negotiation and Processing - Prepare independent
statement of probable construction cost for contract change orders. Negotiate contract change
orders with the contractor. Prepare contract change order document for execution by
Contractor and CITY.
November 6, 2002
Attachment "A" - Work Order No. 48 - Revised
Site & Utility Improvements for the New Gilroy Police Station
2.3.09 Minor Variations in the Work - HARRIS may authorize minor variations in the Work
from the requirements of the contract Documents that do not involve an adjustment in the
contract price or the contract time and which are consistent with the overall intent of the
Contract Documents. CITY shall provide to the Design Professional copies of such
authorizations.
2.3.18 Quality Review - Except for minor variations, HARRIS is not authorized to change,
revoke, alter, enlarge, relax or release any requirements of the Contract Documents or to
approve or accept any portion of the work not performed in accordance with the Contract
Documents. Communication between HARRIS and Contractor with regard to Quality
Review shall not in any way be construed as binding CITY or HARRIS as releasing the
Contractor from the fulfillment of any of the terms of his Contract Documents. HARRIS will
not be responsible for, nor does HARRIS control the means, methods, techniques, sequences
and procedures of construction for the Project. It is understood that HARRIS' action in
providing Quality Review, as stated herein, is a service to the CITY and by performing as
provided herein, HARRIS is not acting in a manner so as to assume responsibility or liability,
in whole or in part, for all or any part of the construction work for the Project. No action
taken by HARRIS shall not relieve any or all of the Contractors from their obligation to
perform their work in strict conformity with the Contract Documents and in strict conformity
with all other applicable laws, rules and regulations. Not withstanding the above, HARRIS is
not relieved of any liability in the event it fails to properly perform its duties, to manage
construction activity for the project as permitted by the time allotted by the CITY and the
attached fee proposal, and to give notice to the CITY, of defects and deficiencies in the work
of the Contractors, all is set forth in this section.
2.3.19 Photographs and Videos - Provide videotape and photographic documentation of
project site prior to and during construction.
2.3.29 Field Inspection - Will provide limited field inspection services to verify substantial
compliance with the contract documents.
2.3.13 Off-Site Inspection - Provide inspection as required at adjacent off-site locations
within 30 miles to verify substantial compliance with contract documents.
2.5 FINAL ACCEPTANCE/CLOSEOUT SERVICES
2.5.04 Final Inspection and Punchlist - Provide final inspection and prepare list of project
construction deficiencies for resolution by Contractor.
2.5.05 Construction Approval/Acceptance - Make recommendations to owner regarding final
project approval and acceptance.
2.5.11 Final Report - HARRIS will provide CITY with a final report for the project.
Page 2 of2
KIProgrmMt\Gilroy\WO 48 Util Reloc-HannalREVlSED Attachment A-48 001.doc
-
~
rIJ
C
Q.=
c 0
.. ....
~~
.....
00
QJ
C.I
....
-
o
=--
I
rIJ
Qj
c:J
....
>-
..
Qj
rJ:J.
.....
=
Qj
e
Qj
~
~
=
~
~ ....
=$
.s ;:J
't~
= QJ
.. ;'::
1;;00
=
c
U
..
cu
<;i
'u
o
=Ii
I
....QQ
~~
-e 0
~z
C-
.- QJ
U"C
-
o
~
-
o
~
000000
oooo~o
0000\1'\0
....,o~ooooo
~O\ON~oo
\0" C'l C'l N" ~" C'f
-
000000
ooo~oo
000\1'\00
Ooo....,r-ON
\00 ~O
...., r-" r-" 0," "0,"
\1'\
~
~~~~~~~~~~~
o
o
00000000000..t
00000000~00s::
NlCilCicxio\o..tlCi....,oo
V) C"l.......('t")NNl.O\OOO
o
o
o
\1'\
r-
o
o
o
o
0"
....,
o
o
o
o
....,
00 0
O~,O
0\1'\ 0
\l'\r- 0
r-~ ~
N" 00
~~~~~~~~~~~~
o
o
o
00
00
00
o 00
_ 00
o
~
\1'\
N
-
o
o
o
~
o
~
\1'\
-
o
o
..t
00
O~
0....,
- ....,
o
o
N
-
-
o
o
o
N
r-
..0
-
~~~~~~~~~~~
8088
0;;000
00
00
00
00
o 00
00 00
00"
00000000
00000000
00000000
ooN~O\OOOO
~_ 00 ~"~~~~
00
00
00
00 00
00 -
~"
00
~~
OO~
000
000
000
000
o,~
N" ~" -"
~~~~~~~~~~~
88888888~~8
~cxiICiO~~~~~~o
o
o
o
o
~
o
o
o'
o
"t
o
o
o'
o
00"
~~~~~~~~~~~
o
o
o
o
o
00
o
o
N
p.,
a(! ~
" Cl)
Z.;; I::
!= p.," 2 p., .5!
Cd I ~ ~
50 bIl...a(!a(!.b
e bIl'~ ~ I:: p., ~
p., I:: '" .l:< 0 , :5
OVi ~ U '.0 ..... s
~e~~5"O
gp.,~fr8<(
... 1::..<:: ... ~ I::
~.gu~~.~..eJ_
g ~ ..... ~ ~ (,,) tI)
.- I.l:: ~ .g Cl) E >'-
E .- .b Cl) 50 '"
.g~8iJe8~
rnUUrnp.,UVi
\I'\\Or-ooo,o-
00000 -
l"il"il"il"il"i....,....,
...., ...., ...., ...., ...., ...., ....,
0000000
~
Cl)
E
Cl)
~
~
::8
tI) ~
bIl....
I:: -
.- ;j
.... '"
I::
o
U
N
~
....,
....,
o
'"
'"
Cl)
I::
Cl)
a
~
'" <(
t:: u
o :..=
fr.g
~p.,
....,~
00
....,l"i
...., ....,
00
00000
0~000
0\1'\000
o,\ON~o,
~" ~ :::" ~ ~"
-
000008
0000~r...:
o\~N::iooN
000000
~o~ooo
\1'\0\1'\000
r-\I'\r-ooo
........ "l ("f') .......
~~~~~ ~
000808
~o~oocxi
N N..tN
00000
00000
00000
NNNNN
"'lNNN~"
~~~~ ~
00000
00000
NNNN~
00000
00000
00000
NNONN
\0 \1'\
" r. lr)'" _"' 0\
~~~~~
000808
oO~oocxi
..tcxioo~cxi\O
0000
0000
0000
0\1'\00
f"") ....... ("f') \0
~~~~~
0000
~~~~
....
.~
:a
u
I::
;j
p.,
o(j
I:: ;j
.g is ~
u Cl) '"
Cl) F= 0 t::
~~~u2
I::..sp.,....~
'';:: - - ~-
~ ~ ~ .0' ~
::8f.i:f.i:~f.i:
N....,~\I'\
00000
..t..t..t..t..t
...., ...., ...., ...., ....,
00000
'"
o
Cl)
~:g
~>
f..<o(j
~ '"
e3g.t;
V':l 50;.:::
~BiJ
~ 0 I::
..<:: ;j
p.,p.,
::-N
E:::O~
c..J~~
-"::00
000
000
000
\l'\NO
00 \1'\ 0,
N" 00"
N
~ ~ ~
o
o
o
r-
N
""
....,
~
000 0
~~~8:;;
N~~Og
00
00
00 '
\1'\ \1'\
r- -
o
o
o
o
0,
~~~~~
00 00
00 00
:2N ON
000 0
000 0
000'0
00,0 0,
o \0 r-"
" N" 00"
N ....,
~~~~ ~
00808
o~ooo\
00,\0000
N N
o 0
o 0
o 0
00 00
N N
~~~~ ~
o 0 0
o 0 0
NON
o 0
o 0
0'0
o 0
...., ....,
~ ~ ~ ~
000
000
NON
I::
.g
u
Cl)
I:: ~
.g ~
g~
~f.i:
..sf-
"00
Qi 0
f.i:z
....,~
~~
\1'\ \1'\
...., ....,
00
@)
g.
~
E
~
"5
'"
I::
o
u
.0
;j
rn
N
o
o
!.:::l
~
~
<=
<=
..e
~
0\
~
<=
<=
M
In
....
<=
~
0\
Q
In
~
<=
<=
~
\C
-.:r
<=
<=
N
0\
~
~
<=
<=
o
IX)
M
<=
In
....
vS
~
<=
<=!
....
-.:r
"0
Q)
"0
:J
o
c::
1'.1
~
~
~
~
=c:
~
~
1'.1
....
o
U
Q)
a.
U)
.~
"0
Q)
t;::
....
.E
U)
Q)
0)
co
~
0)
c::
'CO
>
~
a..
-Ie
November 6, 2002
ATTACHMENT "C"
CITY OF GILROY - CAPITAL IMPROVEMENT PROGRAM
WORK ORDER NO. 48
UTILITY RELOCATION AT NORTH HANNA STREET
CONSTRUCTION MANAGEMENT SERVICES COST
PreConstruction Phase
Project Manager
Construction Manger
Administrative
2 hrs @
6 hrs @
4 hrs @
Construction Phase
Project Manager
Construction Manager
Inspector
Administrative
Testing Sub consultant
30 hrs @
206 hrs @
441 hrs @
120 hrs @
$15,000 x
Proiect Close-out Phase
Project Manager
Construction Manager
Inspector
Administrative
9 hrs @
68 hrs @
22 hrs @
28 hrs @
$150 $
$140 $
$75 $
Subtotal $
$150
$140
$110
$75
1.10
Subtotal
$150 $
$140 $
$110 $
$75 $
Subtotal $
300
840
300
1,440
$ 4,500
$ 28,840
$ 48,510
$ 9,000
$ 16,500
$ 107,350
1,350
9,520
2,420
2,100
15,390
TOTAL COST NOT TO EXCEED $ 124,180
ASSUMPTIONS
The above fee estimate is prepared with the following assumptions:
1. Costs are based on current hourly rates. Rates may be adjusted only pursuant
to Article 4 of the Agreement for Professional Services by and between CITY
and CONSULTANTS dated November 10,1998.
2. The project construction cost is approximately $1,008,000.00
3. Assumed Project Duration is 5 months (107 working days.)
4. Project is assumed to begin in December 2002 and completed in March 2003.
[}L!:i-,.'lJC;/\'T"S O~;ClH\;/,~_
October 28, 2002
..
..
Harris & Associates
Bill Headley, Parks and Facility Manager
City of Gilroy
7351 Rosanna Street
Gilroy, CA 95020
Program Managers
Construction Managers
Civil Engineers
Re: Work Order No. 36 for Design Phase Assistance on the Police Facility Project
Amendment No.2
Dear Bill,
As requested, we have prepared this amendment to Work Order No. 36 for additional management
services. It is our understanding that the additional services are for project design and the duration is
from November 4 through November 8, 2002. We estimate our additional effort as follow.
I Project Management
I $140/ hr. I 8.0 hours I $1,120.00 I
If this amount is acceptable, please approve by executing both the original and duplicate original
and return one fully executed wet signature copy for our files.
Should you have any questions, please give me a call at 842-5777.
Sincerely,
HARRIS &
w-
ACCEPTED
K:\ProgrmMt\Gilroy\ WO 36 PoliceDept PreCon\Ammend 2 to WO No. 36.doc
178 Second Street, Suite C Gilroy, California 95020 408.842.5777 FAX 408.842.5758 gilroy@harris-assoc.com
301
January 31, 2003
..
..
Mr. Bill Headley
Facilities and Park Development Manager
City of Gilroy
7351 Rosanna Street
Gilroy, CA 95020
Harris & Associates
Re:
Police
Site Demolition Project
due to Effort Outside of Contract
Program Managers
Construction Managers
Civil Engineers
Dear Mr. Headley:
This letter is to request a budget amendment for the subject project. As you will recall, the City requested
a minimum effort on this project by Harris & Associates. The project was to be completed by December
8,2002; however, due to major design changes the project's deadline has been extended. These changes
have added substantial effort on our part to meet the City's requests. The delay and additional effort has
been caused by the addition of two parking lots, the delay of the house move at 7311 Church St., and the
demolition of 880 Sunrise Drive.
Although we have tried to stay within the original budget amount of $13,620, the budget balance as of
December 31,2002 will not be sufficient for Harris & Associates to bring this project to completion. We
have estimated the following effort and budget amendment to continue with the project.
Staff Hours Rate Total
Construction Manager 25 $140 $3,500.00
Administrative 30 $75 $2,250.00
Geotechnical Consultant $4,000.00
Total $9,750.00
If this fee is acceptable, please authorize by signing below, and on the attached duplicate original. Please
return one fully executed wet signature document, as our authorization to proceed. Should you have any
questions, please call me at (408) 842-5777.
Sincerely,
HAR~IS;' A~SO^C1TES
W~~
William Little III '
Project Manager
45tf- 2&QO - o<X:;o -43,-/0
C 1./3<<1 8103
6;)
ACCEPTED BY:
Date
178 Second Street, Suite C Gilroy, California 95020 408.842.5777 FAX 408.842.5758 gilroy@harris-assoc.com
.a:
t
ClS.
a
~
:E
o
....
<Xl
~
"
:3
""
Z
"
..
o
:E
o
....
<Xl
"
o
~
>:
~
::x:
OJ
~
:1.
III
120
~
III
o
n
....
OJ
....
ro
III
~
~
z
o
~
CD
::4-
s'
CD
e:..
-
o
~
CD
g-
'"
0'
CD
CD
:=
5'
C'l
~
c.
5'
So
"".
'"
~
CD
"d
.g
o
~
~ 0 (1
Il> '71 Gl
= C)&r
g P e:;
= i:C CD
""* 0 0'
~ -< ~
~. ~ 8-
g,c.g
o ::t C'l
; ~ ~
~a
0' en =:r
~ Rc g
6" ~q
:= en~
C'l 0....
I ~ ~
g. en ~
~ ~ ~
o CD'<
a c.0'
""* Z CD
~ 0 Il>
~ ~ &
g-g.~
R ~ 8-
g 0 g
Il> . q
'" - "d
(il ~ ~
.g 00 '"
CD S
~ a
c. 6'
~ ~
(') a.
~ ~
g,
....
g-
~
(il
CD
~
a
S'
""*
."
""*
o
~
'"
'"
o'
=
e:..
en
CD
~
"".
C'l
CD
'"
~
&
0'
~
CD
CD
:=
g
(1
~
I
~
~
a
:to
~ ~
~
<
1;;' --3
l'\l 0
Q. S'
(j ::;
o =-
= 0 ...
- ""l ~
~ Qq' >
~ S' 8
> e. l'\l
8 to a.
o s:: 8
= 0..
= ~ g
- ..... -
~ ~ ~
N......
=NOO
~ v~ =
~"""N
0000=
?O?
=0=
=0=
I
I~ g;
115 g;
I~ g;
I~ 1!l
I~ g;
I~ g;
I I
11; ~ I~
_0
~ g
"d (1
a e:;
g~
-
~
o
o~61
8 ~ a
i$.. ~ ~
S. ::t. 5-
~ ~ ==
c' ;s:
~ ~
-. ~
~ ~
~ a
~ 9
'::il ....
(":l
~
~
....
"t1
[
~
'G
~
;:
(\)
~
S"
'"
'Cl
~
n
....
"".
o
==
I
I
I~
I~
I~
I~
I~
.....~
<::::>=
(1......
~ 0 0
~ ~ s
~gato
CD ::l.
""* . C'l
g CD
o
<
~~
~e:.
~:;
~ '"
l;; ~.
..., ~ ~
l:: ~ -. ;s: -. ~
(\) (\) ~ ~
::tl ..., ~ ;s:
(\) ..". 0 ;,L~..~
"" ~ " \1Cl v'"' ==
ClO(l::S~~~
E"Cl~!:l'"
........~~..9~
c' 15' (":l ~ "0 a
::s:::>:o-a~~
~""~~a
"" S"
'"
'Cl
~
n
....
"".
o
==
~
-
~
o
o
o
=
=
=
.....~ ~
<::::>lHOo~O\O'I\.It(JI
.....~ ~
<::::> lH 00 ~ 0\ 0'1 \.It (JI
.....~ ~
<::::> lH 00 ~ 0\ 0'1 \.It (JI
.....~ ~
<::::> lH 00 ~ 0\ 0'1 \.It (JI
.....~ ~
<::::> lH 00 ~ 0\ 0'1 \.It (JI
=
=
-l-l:........v.,QC~N
(JI<::::><::::><::::>=\.It(JI
~ ~
~
~
=
u.
=
=
o
=
~
~
N
=
=
o
=
.
=
=
=
.
lH
U.
=
=
o
=
00
...
-
l'\l
~
~
=>
... 8
00 ~ l'\l
= ..... =
c:r 8 Q.
8 "0 8
... ., l'\l
- 0 =
;- < -
Q.8~(j
~ c:r _ 0 ...
:;;;:<< == :.... ~
1=-
~~:,S"~
c:r ., 0 ~ ,..
I ::3." < ::!.:
=~~o:;
~~l'\l"o
;; ~<<
~"'Co
~ a a
O. n' ~
~ l'\l
-oo~
l'\l _ 0
~ ~ .
e. ~
o 00
=
"'C
.,
o
....
l'\l
~
-
ar it!! of Q?; ilro!!
COMMUNITY DEVELOPMENT DEPARTMENT
Norman S. Allen, P.E., Director
Planning Division
Engineering Division
Building, Life & Environmental Safety Division
Housing & Community Development
(408) 846-0440
(408) 846-0450
(408) 846-0430
(408) 846-0290
FAX (408) 846-0429
FAX (408) 846-0429
FAX (408) 846-0429
FAX (408) 846-0429
March 5, 2003
CONTRACT ADDENDUM
(WORK ORDER 49)
AGREEMENT FOR: PROFESSIONAL ENGINEERING SERVICES FOR CONSTRUCTION MANAGEMENT -
NEW POLICE DEPARTMENT PRE-BID AND BID PHASE
Consultant: HARRIS & ASSOCIATES. INC
Contract Agreement Date: November 10. 1998
This WORK ORDER shall become effective when the City Administrator, City Engineer, Project
Manager, and Consultant have signed it. All copies forwarded to Consultant for signature shall be
returned to the City of Gilroy properly filled out. Upon acceptance by the City, the Consultant's
copy will be returned to him as his authority to proceed with the work.
DESCRIPTION OF WORK:
Provide Construction Management for pre-bid and bid phase services relating to the New Police
Department Facility Project. The Scope of Services shall be as detailed in Attachment "A",
consultant cost and work effort shall be as detailed on the attached worksheet.
All requirements of the original Agreement Documents shall apply to the above work except as
specifically modified by this Addendum. The contract time shall not extend unless expressly
provided for in the Addendum.
City of Gilroy, Contract Addendum
Work Order No. 49
March 5, 2003
HARRIS hereby agrees to make the above
change subject to the terms of this Addendum
for the NET INCREASE OF $38,685.00
Original Agreement Price
i (Master Contract)
This Addendum
$5,187,986
$ 458.543
$5,646,529
$ 38.685
Total Addendum to Date
Total Amendments to Date
TOTAL TO DATE
"7 - ".4
Date: :;;>.~:>,O./
REVISED AGREEMENT
$5,685.214
Date
c3/~~
Date
Originals: (2) - City Clerk
Consultant
Copies: (2) - Purchasing
File
Page 2 of2
March 5, 2003
ATTACHMENT "A"
SCOPE OF SERVICES
NEW POLICE FACILITY PRE-BID AND BID PHASE
WORK ORDER NO. 49
32. PRE-CONSTRUCTION PHASE SERVICES
32.021 - Bidding - Assist with consultant coordination and City review of pre-bid questions
and addenda preparation.
32.022 - Pre-Bid Conference - Organize, schedule, attend, and record the pre-bid conference.
32.023 - Bid Review - Prepare detailed bid tabulation, review apparent low bids for
conformance to requirements, review and report on bidders' acceptability.
1\.II11l I{Ilk
SLl \ III ( .ltq!()III..""
1.I,k
City Of Gilroy
Cost Proposal for Pre-Bid and Bid Phase Services
New Police Facility Project - Work Order No. 49
Submitted by Harris & Associates
3/5/2003
II
o
2
2
2
2
2
2
o
Bill Little
Project Manager
Overall Project Management
Interface with Agency Staff
Reporting on Project Status
$ 150.00
Scott Gilpatric
Construction
Manager
Overall Project Management
Interface with Agency Staff
Reporting on Project Status
Construction Management
Pre-bid services
Bidding phase services
Project Issue Resolution
Document Control
0 12 12 12 0 36 $ 5,760.00
10 10 10 30
2 2 2 6
$ 160.00 0 41 38 42 0 121 $ 19,360.00
15 6 6 27
15 20 20 55
6 6 6 18
5 6 10 21
Contract Administration
Administrative
Assistant Management Administration
Records Management & Processing
Total Labor Cost $
Geotechnical Sub-Consultant $
Biddability!Constructability Backcheck by Robert Ball $
32,095.00
2,750.00
3,840.00
Assumptions:
Overtime Allowance $
Grand Total $ 38,685.00
1. Costs are based on current hourly rates. Rates may be adjusted only pursuant to Article 4 of the Agreement for Professional
Services by and between the CITY OF GILROY and HARRIS & ASSOCIATES dated November 10,1998.
2. No Overtime allowance has been included in this fee proposal.
3. Escalation fee beyond the End of December 2003 is not included.
4. Geotechnical Consultant is invoiced at fee plus 10%.
5. The project construction cost is approximately $19,300,000.00.
6. Assumed Pre-bid and Bidding Phase Duration: 3 months, March 1, 2003 - May 31, 2003. Any additional time beyond what is
shown, may require a fee amendment.
klprgrmmtlgilroy/W049 Bid Phase Cost Proposal 2_l0_03/vm
1
\.
""""
''''""",,
..
..
Harris & Assoaates
Program Managers
Construction
Manaaers
May 29, 2003
William Headley, Parks and Facilities Manager
City of Gilroy
7351 Rosanna Street
Gilroy, CA 95020
Re: Gilroy Police Facility
Bid Review and Recommendations
Dear Bill,
We have completed our bid analysis of the New Police Facility bid on May 20, 2003. Attached you will
find a summary breakdown of the bids along with possible courses of action and our recommendations.
Per your request to find possible reasons why the bids came in so much higher than the engineer's
estimate, we offer the following possible causes:
A. General Contractor' s Work Percentage
A contributing factor to the increased cost may be due to the high 'minimum General
Contractor's work percentage' included in the original bid. Reducing the 'minimum' to 15% or
possibly less if feasible could help in lowering the bid amounts.
B. Drawing Ambiguities (Appendix A)
A quick comparison of Harris & Associates Biddability and Constructability Review (Dated Sept.
26, 2002) vs. Pre-Bid Clarification Questions from contractors vs. Addenda Issued, yielded the
following:
We found 45 B&C comments that paralleled Bidder's questions. This suggests that some of the
B&C comments were not incorporated into the bid documents prior to the bid date. In the interest
of time, only one contractor' s (West Coast Contractors) list of questions was compared to the
Addenda issued and we found only 13 of 139 questions were directly answered. There is a
possibility that some other comments and questions may have remained 'unanswered' therefore
necessitating the use of 'extra contingency money' in the bids.
C. Estimated Construction Costs
The summary findings of Appendix B-1 and B-2 yields to the conclusion that the estimated
construction costs relied upon by WLC were not realistic.
178 Second Street, Suite C Gilroy, California 94520 408.842.5777 FAX 408.842.5758 gilroy@harris-
assoc. com
",,",
........"
A list of possible actions can be found in Section 2 PROJECT OPTIONS. In considering your request
for ways to reduce the price we offer the following options:
A. Reduce the General Contractor work percentage to 15% or less.
B. Clean up the bid documents addressing all B&C comments and pre-bid inquiries.
C. Reject all bids, redesign project. Build or modify below-grade option, downsize above-grade
structure with potential for future expansion.
Further review and discussion is required to determine the best course of action. We would be pleased to
review this report with you, and are available for discussion with you and WLC.
Again, we appreciate this opportunity to provide services to the City of Gilroy.
Sincerely,
HARRIS & ASSOCIATES
W~~'T
William Little ill
Associate
Ene. Bid Review and Recommendations, Appendix A, B-1, B-2
cc:
178 Second Street, Suite C Gilroy, California 94520 408.842.5777 FAX 408.842.5758 gilroy@harris-
assoc. com
'.....,..
....,"'"
2. PROJECT OPTIONS:
A. Obtain additional funding required and build project as designed.
B. Reject all bids, repackage and build below grade portion now (Phase-1). Clean
up drawings and build remainder of project when funds available (Phase-2).
C. Reject all bids, cleanup drawings and re-bid project as designed.
D. Phase project with low bidder.
E. Reject all bids, redesign project. Build or modify below grade portion, downsize
above grade portion with capability for expansion.
F. Design-Build and lease (CHP).
G. Postpone project for 1-2 years.
H. Postpone project indefinitely.
3. RECOMMENDATIONS:
. Reduce GC work. percentage to a maximum of 15% (lower if feasible).
. Clean up drawings, address and/or incorporate B/C Review comments and all
pre-bid inquiries.
. A combination of Options B, C and E depending upon operational necessities of
the Police Department, and factors influencing time and money. Further review
and discussion will be required to determine the best course of action.
-,,-
'-'
New Gilroy Police Facility
Bid vs. Estimate Summary
Appendix B-1
GENERAL CONTRACTOR BIDS:
Subcontractor % Listed
Nibbi Brothers Construction
$26,137,000 (low bidder)
$26,700,000 (second)
$26,792,000 (third)
70%
S.J. Amoroso Construction
48.07%
K.H. Construction
71.55%
The average of the bids was $26,543,000. The cost variance between the low bidder and the
second bidder is 2.1 %, and between the third bidder is 2.5%. The cost variance between the
second and third bidder is less than one half of one percent (0.34%). This is a good indication
that the bidders all recognized the same cost factors, considerations, and/or allowances
necessary for construction of the project. It is also a good indicator that no major work element or
item was omitted or overlooked by the bidders as evidenced by the tight spread in bid cost.
PRE-BID ESTIMATES:
DLA Cost Estimate
$18,231,057 (100% design - 2/03)
$25,182,000* (90% design - 9/02)
WLC Architects
(* Total amount indicated excludes contingency cost for design development as added in DLA
cost estimate)
SUMMARY:
The low bid submitted was approximately 30% over the Architect's estimate of February 2003.
However, the low bid was only 3.6% over DLA's estimate at 90% design completion. It is
evident from the bids received, supported by the DLA cost estimate, that the construction cost
relied upon by WLC was not realistic.
~~
.....)i
~ 5"
~9:
-. 0
a:Q)
CD CD
~.... CI)
oS
.... Q)
Q) .....
g ~
:3 ~
~....
!as
o' CD
~ ~
g*
0:9:
::J S
o CI)'
;; o'
CD ::J
3 ~
Q) :::;:
~~
g~
~CI)
cti ::J
~ g,
~6:
-. CD
Q.::J
Q)Qo
::J:::!i
0. CD
~~
QoCl)
3" CD
Q)Q.
CD
~
3
~
~!\)
ijj()
~~
0......
~~
CiJ i:
~~
g.CI)
~5
o ~
....1::
~ ::J
*~
....
9:~
S .....
!!.!: ()
g Q)
CI) ::J
00.
01:)
~~
5'
CD ~
Q.~
5" cti
CD g
Q) 3
g.-o
CD ~
~Q.
3' ~
Q) 0
~3
~ =--'"
o I::
*!!!Q)
'ea:~
CD CD ~
a~....
CD CI) o'
::J 0 ::J
ijjO~
<o~
CD oc;:
:::;- Q)
"'i:
s-
o' '..
Q) CI)
CDQ)
0. 3.
Q) ~
~Q.
5- ~
~~
0-
ijj~
-C')
~I::
Q:ar
Q)g.
3<0
o CI)
55-
:"'000
o
::J
~
o
0-
....
",......:,.'\~.
~
I:)
CD
:if
II
~
~~
<0
I\)
~~
w
o
00
""'"
G)o"'U:;:om"'U'TIG)os::en"'U:;:OG)
-CD Q) 0--:;-,< Il) -=CD....
Il) _ -. 0 CD 3 CD ~ CII ~ 2 CD -. Il)
CIICII CD a:::!lgC""T'IC"CD 0 (1 CII ~9:
_ a -. ;:) ::J. <0 u 0 =e ;:) - 0;:)
G) -. cE co 0 - a Il) 0 .~ en .... <0
_o_:;:.ll)s::-a....'<- o_
Il) ;:) 'TI .c: - CD CD " CD 5' "'U
~- m 0" Il) g. g =0 ~ <0 Il)<
cE .0 0 (j) Il) O' iii' =n --
~ ::J. .... ;:);:) CII .... ;:)
;:)'0 -- - Il) <0
coa 0 ~ 3
o ~ -.
- ;:)
-- co
;:) -
<0 0
CD
o
"
-I
o
-
~
..
.. .. .. ..
.. .. .. .. ..
..
(fl
.....
w
~
0)
o
(J'I
(J'I
(J'I
{fl (fl
I\)W
0) <0
.....1\)
WO
...... (J'I
O(J'l
{fl {fl {fl {fl {fl {fl
(fl~.!"{fl~{fl{fl~~~{fl
0) woowoow...... (J'I 00"'" 0)
(J'I<O...... <01\) <0 00 0) 1\)""" (J'I
w......(J'II\)<OI\).JlO.OO<OO)w
~~OoOOo'O-.....No'-.....~
::;:::I\)...........(J'I<O(J'I.....I\)<OO)I\)
-(J'IOO(J'lO(J'lOO 0 (J'I(J'I
{fl {fl {fl {fl {fl
{fl {fl _w {fl _..... {fl {fl _..... ~ ~ {fl
.Jlo. (J'I O-llo-<O(,.)............I\).....-Ilo-
o 00 -Ilo-I\)...... 1\)""" 0 0...... (J'I
0...... w......(J'IO-llo-OO.....-Ilo-W
O'~~~~OoNOo~WOoO'Oo(O
g)ig)i)iggggggggg
{fl {fl {fl {fl
{fl {fl {fl {fl _w _-Ilo- (fl _I\) {fl {fl _.....
(J'I-Ilo-O)(J'II\)O-llo-.....I\)(J'I.....
wOOw..........O-llO-O)WI\)
(J'I.....I\)(J'I(J'IOO.....w......(J'I(J'I
OoOoOoOoOOoOoW(OOoN
-IlO-OOl\)-IlO--IlO-OOOO)I\)-IlO-O)
OOOOOOOOOO-llo-
(fl
.....
o
......
.....
~:s: <>> ~:s:
)i~)i
-I
o
-
!!.
..
.. .. .. ..
.. .. .. .. ..
..
.,.
00
en
w
cn
N
""
....
.,..,. .,.
.,..,..,.w.....~.,..,..,..,..,.~.,.
.....WOlcnN.........WWcncn....
000 OIN..... 00 N N.... 00""'''''
ooCDNoo.....NNCDoo.....O""
!2::...'"cn...,..en...,..~wen'"cnoo:...!2:
~oocncn.....O.....CDoocnooOW~
-....oo.....O.....cnOlCD"".....Ooo-
.,..,.
.,..,..,.~~.,..,..,..,..,. .,.
N""CDNooNooOl....CD CD
OIcncn....OI""ONOIOI N
oo.........oo..........cn""""w CD
!2:......:...coo~co'"cnco~......!2::...!2:
~NOIOoo.........OIWNN~O~
-01 00 00 ooCDOIOO "".....-CD-
'ffi
"11
en
C5
'<
~
:1E
o
....
"
o
<-
iii'
o'
;:)
-
;::;
CD
3
)>r
3 ~
o
....OJ
o __
ClIO.
o
ZI\)
-- ;:)
C"o.
Q:
OJ
a
CII
AW
Ia
o
o
;:)
!!L
~
r
o
m
en
-
c
~
m
en
-
)>"'UZ
'0 Il) CD
~2:=e
;:)~G)
9: OJ:;'
x -. 0
OJ a. '<
'O"'U
1\)<0
CD=
<! 0
__ CD
CD'TI
=e Il)
Il) 0
;:)=
a.;:;:
'<
o
o
3
~
Il)
....
iii'
o
;:)
.,;"-'""'
ff"
""'C
....,
.Q.
<D
(')
.....
. ....
. ....
iv.> ....... ~i~io>i~ .......ico
:0 01 CDi~i"""'iO v.>iCD
10 0>101 :0 I
j j j ,.--~--i~ j j j j
l~ ~ ~!~I~I~I~I~i~lglg ~I~I~ ~I~
'! 1_i i' i
.. . .
: I\.) : : :
i~i i i
. .
. .
. .
. .
.' .
.' .
~I~!~I~I~I~ ![li!~I~I~~I~I~I~ ~ I 1~1~1~1~!~I~I~I~I~!~I~I~I? .
~iml~i~:~!3:~:~i~ o'~,~ ~,~!~'~i~ ~i~i~;~i~'~i~
j~ v.>iv.>,3,3'~,~,~, 'CD'I\.),~,~j3j3 j~j3j3j3j3j3j3j3'3j3j3'3'3'3,3
I~ !1~1<n1~1;~~r~1 i I ~I~I.; ;l~I<Oitn!~IJ>i(+IW!.;!~I<OltnlJ>i"'w
i, ~ ::.':,. ~co ':,!" ~ i.,1 : ~ i ~ I
I~ I~ i~ i
i i v.>:
z
o
CO
CD
CD
~
o
v.>
~
I\.)
o
I\.)
o
v.>
9>
o
o
o
"'U
S>>
CC
CD
....
o
....
.c.
~'~!
~~i
~~I
0>0>:
O>O>i
Oi
. . . .
i ; ! i
.......__----.0.--............._
. . . .
. . . .
. . . .
. . . .
......._..-..~--_..--_.....-
. . . . .
. . . . .
. . . . .
. . . . .
.....--.......-..--...---.....
. . . . .
. . . . .
. . . - .
. . . . .
. . . . .
!....-L-.....L.......L_._.....L..........
OJ
go
o
<
tn 0
,,~
i 0
I """"
~Q......
c.::""
-,"tS
.DO"tS
c: '< CD
(I) "lJ ~
!Loe:
-. - ><
· 0 --
~ (") )>
tn (I)
< 'TI
tn Q)
. ~-
)>==
c.~
a.
CD
~
a.
Q)
--~
~
.~ I\) I\) ~.~;~
'(X) 01 0 <0:......(.0.);
,_ ...... (.0.) m:m11\):
I~ :!;
I\):~:O'I:~
......i~!......!<O
W!OOI~I<>>
I~!
;
;
,
! ; ;
;
! I
;
'"ti
'"1
..9.
C1l
g.
Z
9
1.0
,
,
;
; I
;
;
!
! !
j
j
;
i ;
i ; !
;
j
!
~
=
(JQ
"'
N
e
-..
~
1~1~1~1~1~1~1~1~1~1~1~111~1~ ~ll,~i~liIII'.
l~i~I~~~~~I~I~~~~I~I~~! l~iCD '00'1 '1
j'< j'< j'< i=':i=':i=': -< j'< i=':i=':i:J j'< j'< -< i .Sli~"..i~ :"'~;"'~ II
I.;~ I.i~ I.;~ I.J~ i.i_~ i.;_~ I.;_~ ~ I.-~ i.-~ i.;-~ I. ~ I.;~ 0 ~ l.:~" I. ~. !.! ~ ,~.,~.,~.
-.. -~!I\)!I\)
lililiiililiii ~'ili!i~l~ i i!~~~~I~I~ ~
. "O'I'm'I\)' o. i' 3:,1\) 1\)!)>!31!!
I ! i , i i ; ~! ~ j 8 8 !g. II\) 1 t .
; (.0.) ! _mo I,.' CD CD j I\) j
, 3 i-"l
; , (.o.)! 3 ,-
~.I\) ~!8i
~ i
JI '
,
)> )> )> )> )> )>I~)> )> )> )>
000000 0000
(.0.) (.0.) (.0.) (.0.) (.0.) (.0.) ,(.0.) (.0.) (.0.) (.0.)
m J:,. J:,. J:,. w w 0,: ~ I ~ J:,.
I\) m m 01 <0 (X) <0,01 Q) ~
OJ)> () i a. )>
:E
Q)
""'
CD
00
(')
:T
CD
a.
c
CD
:
;
! ,
j !
,
,
i
,
.._-1--1.._
m
go
o
<
en
.
"'0
CiJ
I
~~O
O-::~
~~O
CD,,~
ens>>Q
.... (") -.
o. -. :;-
::::J :: 0
en~'<
<
en
)>
0-
0-
CD
::::J
0-
S>>
"'I:;j
....
..9
~f
.....
z
9
\0
~
=
CJCl
~
~
=
"""l
...
m
QO
o
<
tn
.
'"U
ca
I
!!!'"UO
Q. 0 -.
O~~
c CD 0
CD on"
!!LmC)
-- n --
0::::;-
::J -. 0
tn~'<
~
.
)>
Q.
Q.
CD
::J
Q.
m
~
..9
CP'
~
Z
9
1,0
~
=
(JQ
~
".
o
~
".
m
go
o
<
tn
.
"'tJ
Cil
I
~"'tJO
a. 0 -.
D~~
c: CD 0
CD on""""
!!l.s>>C)
-. n --
0:::::;-
iJ~~
<
!I>>
)>
a.
a.
CD
:J
a.
S>>
dU/
DUPLICATE ORIGINAL
August 29, 2003
-
-
Harrls & Associates
Mr. Bill Headley
Facilities and Park Development Manager
City of Gilroy
7351 Rosanna Street
Gilroy, CA 95020
Re: New Police Department Project Re-Bid - Work Order No. 49-A
Request for Budget Amendment No.1
Dear Mr. Headley:
This letter is to request a budget amendment for the subject project in the amount of $159,655 for the re-
bid phase of the above-mentioned project. Our UfIderstanding of the scope of services is described on
Attachment "A". Our fee is detailed on the attached spreadsheet.
Ifthis fee is acceptable, please authorize by signing below, and on the attached duplicate original. Please
return one fully executed wet signature document, as our authorization to proceed. Should you have any
questions, please call me at (408) 842-5777.
Sincerely,
Vice President
UGiL, ~ ·
William Little III ~
Proj ect Manager
~L
ACCEPTE
C! Patrick Dobbins
Project file
K:\ProgrmMt\Gilroy\Amendments\Amend 1 to WO 49 PO Re-bid Cvr Ltr.doc
178 Second Street, Suite C Gilroy, California 95020-5100 408.842.5777 FAX 408.842.5758 gilroy@harris-assoc.com
August 28, 2003
JUPLlCATE OH1GIf'.AL
ATTACHMENT "A"
SCOPE OF SERVICES
NEW POLICE FACILITY OVERSIGHT COMMITTEE AND RE-DESIGN
WORK ORDER NO. 49-A
2.1 RE-DESIGN PHASE SERVICES
2.1.01 Meetings - Organize, schedule, notice, and attend design phase meetings. HARRIS shall
coordinate meetings with the City Staff, City Design Oversight Committee, City Council
members and Design Professional to address and coordinate project issues. Design Professional
will prepare and distribute meeting minutes.
2.1.02 Reports - Provide monthly status reports as directed by the CLIENT.
2.1.03 Project Administration - Establish and implement the procedures and documentation
process required to administer the project. Coordinate the review process with CLIENT staff,
and Design Consultant. Assemble and transmit comments to Design Professional. Review and
comment on the design schedule as prepared by the Design Professional. Oversight of the
Design Professional's activities to maintain the design phase schedule.
2.1.04 Statement of Probably Construction Cost Preparation, Review and Updating at
schematics, 60% and 90% of design and construction document - Prepare detailed statements of
probably construction cost based on the plans and specifications provided by the Design
Consultants. If statements are provided by the Design Consultants, Harris will review the cost
data supplied and advise the Client on the acceptability of the statements.
2.1.07 Review of Design Documents - HARRIS shall review design documents at schematic
design, design development, 30%, and 60% and make recommendations to the client and design
professional concerning the project as to clarity and consistency with the City direction and
needs of general method of operation. HARRIS will coordinate addressing the comments and
concerns with the CLIENT and Design Professional.
2.1.08 - Biddability and Constructability Review - HARRIS shall review the design documents
at 90% Plans and Specifications. Make recommendations to the CLIENT and Design
Professional as to biddability and constructability, cost, sequencing, scheduling and time of
construction, clarity, consistency, and coordination of documentation among the contractor, and
as to the separation of the project into construction contracts for various categories of the work.
The recommendations resulting from such review will be provided to the CLIENT and Design
Professional in writing.
In making reviews and recommendations as to design documentation or design matters, HARRIS
shall not be responsible for providing nor will HARRIS have control over the project design,
design requirements or the substance or contents of the design documents. By performing the
reviews and making recommendations described herein, HARRIS shall not be acting in a manner
so as to assume responsibility or liability, in whole or in part, for any aspect of the project
design, design requirements, design criteria or the substance or contents of the design documents.
HARRIS' actions in making such reviews and recommendation as provided herein are to be
advisory only to the client and to the design professional.
Work Order No. 49-A
Page 1 of 1
..
..
Ji!i'fIJ', ~~sociates
JUPLlCATE OR1GIN/\L
City Of Gilroy
Cost Proposal for Oversight and Re-Design Services
New Police Facility Project - Work Order No. 49-A
Submitted by Harris & Associates
August 28, 2003
Oversight Committee
Oversight Committee & Re-design
Phase I
Phase II
Team Meetings
Oversight Committee Mtg(s)
~..
Consultant Coordination
Administration @ $75/hr.
Total Hours
Total Amount
Project Manager Hrs.
$150Ihr.
4
4
6
5
19
$2,475
Office Engineer Hrs.
$1201hr.
2
o
2
----
o
4
$480
Team Meetings
Oversight Committee Mtg(s)
Consultant Coordination
Reviews & Report
Administration @ $75/hr.
Total Hours
Total Amount
Office
Project Manager Hrs. Engineer Hrs.
$1501hr. $1201hr.
12 4
10 0
40 10
16 6
-------------
20 20
98 20
$13,200 $2,400
Re-Design Phase III
Project Manager Hrs.
$1501hr.
20
80
8
24
64
Office Engineer Hrs.
$120Ihr.
4
20
o
--------
16
20
20
Team Meetings
----- ---_._--~
Consultant Coordination
Oversight Team Mtg.
30% Review
---_._..~~
60% Review
---._-----
90% Review (H/C Team)
(Lump Sum Not to Exceed) $ 47,000
Davis/Langdonl Adamson Cost Estimate Plus 10%
(Lump Sum Not to Exceed) $ 44,000
100% Review back-check 24
------_._-_._._-_._-_..~----_..
Admin. B/C @ $75/hr 100
Total Hours 320
Total Amount $ 131,500.00
o
.--
o
o
80
$ 9,600.00
GRAND TOTAL AMOUNT
$159,6551
ASSUMPTIONS: The above estimate is prepared with the following assumptions:
I. Costs are based on current hourly rates. Rates may be adjusted only pursuant to Article 4 of that Agreement for Professional Services
by and between CITY and CONSULTANTS dated November 10, 1998.
2. The total project cost are estimated to be $18,900,000.
3. Work will be completed according to schedule known as Exhibit "D" (Attached), assuming a 13 month duration of evaluation
analysis and design commencing August 4, 2003
-
-
Harris & Associates
07/01/03
07/11/03
08/04/03
*08/04/03
08105103
09/17/03
09/24/03
* 10106/03
10/29/03
11/05/03
* 11/17/03
12/01/03
01/05/04
01/14/04
01/21/04
*02/02/04
02103104
04/21/04
05/05/04
06/23/04
07/07/04
09/15/04
09/22/04
* 10/04/04
12/06/04
02/02/05
03/02/05
04/04/05
05/02/05
03/05/07
*Council Meeting
JUPLlCATE ORIGIN.,^ I
"I..
Exhibit "D"
Project Schedule
Gilroy Police Facility Redesign
Phase One - Scope of Work & Action Plan
Complete Phase One - Scope of Work.
Executive Oversight Committee Meeting.
Council Review and Approve Redesign Scope ofW ork.
Phase Two - Preliminary Redesign Phase.
Preliminary Redesign Options and Cause & Effect Matrix Submittal
Executive Oversight Committee Meeting.
Council Review Redesign Options and Cause & Effect Matrix
Redesign Documents and Draft Master Plan Update Submittal
Executive Oversight Committee Meeting
Council Review and Approve Redesign Documents and Draft Master Plan Update Altematives
First Outreach of Draft Civic Center Master Plan
Second Outreach of Draft Civic Center Master Plan
Final Preliminary Redesign and Civic Center Master Plan Update Submittal
Executive Oversight Committee Meeting
Council Review and Approve Preliminary Redesign and Civic Center Master Plan Update.
Phase Three - Construction Document Redesign
30% Complete CD Progress Review Submittal.
Executive Oversight Committee Meeting.
95% Complete CD and B&C Submittal.
Executive Oversight Committee Meeting.
Bid Package Submitted
Executive Oversight Committee Meeting.
Council Review and Approve Bid Package
Bid sets available; Bidding phase begins.
Pre-bid conference.
Bid Opening
Council A ward Contract for Construction
Begin Construction
Final Completion/Occupancy
1
Exhibit "D" - Redesign Project Schedule
Gilroy Police Facility
'-
..
..
Harri s & Associ ates
Program Managers
Construction Managers
Civil Engineers
GILROY CITY COUNCIL STUDY SESSION
New Police Facility Redesign Report
December 15, 2003
Schedule of Handouts
1. WLC Redesign Narrative
2A. Design Options Evaluation Matrix
2B. Conceptual Design Graphics for Options 1 - 3
3. Project Cost History to Date
4. Cost Estimate - Redesign Options
5. Gilroy Civic Center Master Plan - Supplemental Parking Assessment Report
6. Project Schedule
C:\Oata\City Of Gilroy Study Session for PO Redesign.doc
178 Second Street, Suite C Gilroy, California 95020 408.842.5777 FAX 408.842.5758 gilroy@harris-assoc.com
WLC
Architects
.....- Lorry WaIH, AlA . George M. Wiens, f1JA . Robert J. Hensley, AlA . James P. DiCamillo, AlA . Glenn Ueda, AlA
~ I /v1ox Medina, f1JA · Kelley Needham, f1JA
December 15, 2003
Redesign Project Narrative
Gilroy Police Facility
Redesign of the Gilroy Police Facility is necessary to reduce project costs to WLC's estimated
construction cost of $18,231,057.00. Bids received in February 2003 from three bidders ranged
from $26,137,000.00 to $26, 792,000.00. While significant changes in the overall project scope
are necessary to reduce cost, redesign objectives must fulfill Police Department space needs
based upon the City's projected population at build-out of the General Plan. To meet this
challenge, the redesign effort has been conceived to eliminate all non-essential Police
Department improvements from the project scope wherever possible. The primary approach to
the redesign of the Gilroy Police Facility consists of three primary components.
A. Eliminate lower B-2 below grade parking level.
B. Eliminate primary building upper floor.
C. Eliminate separate communications tower.
Schematic plans have been prepared to reflect these design modifications, and consist of Site
Plan, Main Level Building Floor Plan, Lower B-1 Parking Level Floor Plan, Building Section,
and Exterior Elevations. Changes to the design are anticipated to reduce costs as follows.
A. Eliminate Lower B-2 Below Grade Parking Level
I. Elimination of auger pile shoring system, and use of pier lagging excavation support
system along the north residential property and provide 1: 1 layback slope excavation at
three and three-quarters of the remainder of the site.
2. Reduced export fill material.
3. Elimination of 70,194 square feet of below grade, cast-in-place concrete Basement 2
parking structure.
4. Elimination of elevator at grid line K-1.
5. Reduced stairway and elevator flights.
6. Reduced mechanical and emergency exhaust systems.
7. Reduced fire/life safety and security systems.
8. Change from Type I-F.R. to Type II-F.R. construction throughout entire superstructure.
9. Reduced construction time.
B. Eliminate Primary Building Upper Floor
1. Relocate Communications Center from Upper Level to Main Level of building.
2. No change in overall building square footage; Main Level increases to 48,970 square feet.
3. Simplified roof design (Mansard roof mechanical screen) and decreased structural steel
costs.
4. Reduced tile roofing with 3:12 slopes eliminating Class "C" roofunderlayment.
5. Reduces complexity of mechanical duct distribution and roof enclosure.
6. Elimination of added utility rooms at roof level.
7. Reduced stairway and elevator flights with elimination of stair at grid lines F2.
8. Simplification of atrium which becomes a 2-story space-no smoke evacuation
requirement.
9. Reduced emergency power system.
10. Reduced fire/life safety and security systems.
11. Change from Type I-F.R. to Type II-F.R. construction throughout entire superstructure.
12. Reduced construction time.
A. Eliminate Separate Communications Tower
1. Police will use existing communications tower; conduit to site already in place. 590 lineal
feet of antenna cable and IT conductors still required for connectivity.
2. Elimination of tower clock and color kinetics lighting system.
.
~
~
~
<
8~
oz
C-:O
l(') """"
......~
~<
~~
E~
~<
g>
Q~
~
fI.l
~
.Cl
~
=
bIJ
...
fI.l
~
"Cl
~
~
I
.c-
...
-
...
C.l
~
~
~
C.l
...
-
o
~
>>
o
$..
-
~
<lJ <lJ <lJ <lJ (l) <lJ
~ ;> ;> ;> ;> .~ ;> = =
.~ .~ .~ .~ ..... .~ :3 :S
z .... -;; -;; ro
0 u <lJ S OJ) OJ) OJ) S OIl bI} OIl i ~
= = <lJ <lJ <lJ <lJ (l) <lJ
"""" Q. 0 :13 z z ~ :13 ~ z Z
E-< E Z I I I I 10 !"')
:::E .... .... .... :::E .... .... ....
~ .... 0 0 0 0 0 0 QO N
0 '<ir '<ir '<ir '<ir '<<i' '<ir !"'i M
:::E :::E :::E :::s :::E :::s ~ (I'l
M = =
Z .... '"0 "0 :5 :5
<lJ
0 U <lJ (l) <lJ <lJ <lJ (l) <lJ (l) ;> i ~
= = = = = = u = =
.g 0
"""" Q. 0 0 0 0 0 0 0 ....
E-< E Z Z Z Z Z (l) Z Z 0.. M r-
~ .... ~ S .., 0
0 ...... If) M
~ (I'l
...... = =
Z .... d -;; -;; -;; :S :S
0 u S S <lJ S <lJ S <lJ (l) <lJ i ~
= = = c = =
"""" Q. :13 :13 0 :13 0 :13 0 0 0
E-< E Z Z Z Z Z M ....
~ .... :::s :::E :::E :::E 0 ....
0 If) M
~ (I'l
~ ~ ';i
= .. .... =
Q 'i: Z
:c .... .~ := '" .... '6iJ
~ '" "0 u .... .... u 'i: 0
.... ~ .. '" .. .. ....
U Q I+'< ..... Q Eo-<
-; = b!I ... '" U .... Q
e. ~ oS b!I ~b!I := .... 0 U
00 u .5 = := '" = .ce. ....
~ 'j3 ~ ;e c E :g .- = ""0 '"0 ;:J
.... 0 .. "r::l .- .. ~
~ .c _"0 Q.'-
u "r::l = .... +: c .... 'S os :: =.c .... Eo-<
00 = p.. = O;i 0 '" =
.. >> .c := u_ e. 00
00 .... = <( Q. 0; ; '" .c '" = z
0 .c "0 = E
.... .. E 0"" b!I .... ....
.. '" 0' .. := = ~~ = .- 0 0
Z b!I '0 0 =.; = .. ell .!:,ll Co> U
~ ~ ~ Co> ;..,'" :E e S~ - ....
.... = U "0 .... c "0 0 = ~
.... ... ="0 .:; .... .... .- .9
...... 0 ... 0 ... .... '" o 0
00 .. Q 0 = .. .. '" ~
Q. 0 .c .~ ell =- 0..... ....
~ ._ 0 ell .c Co_ Q. e.= .c"O Co>"r::l Eo-<
0 .....c is: .... 0 c ~;:: .. .. = = .-
~ ... Co> .... ... .. .... .. "r::l.c <(
= 0 0 CoS = ~ ~ ~ .9 o ....
~ Q. .... .c =~ ...... ~Eo-<
.....c .. ;..,- ...... .c = .... Co>
.c 1;;.c .c .. .ce.
.... '0 ... .. Q. .!:! .~ f .......~ ....00
.... = b!I '" b!I ~ g, "r::l E .~ E
... = .~ '0 - .. '" 0 ~O
0 Q .- 0 .. Q Q e. .. 0 o ...
U ~ ~ 0
Z Z ~~ U Co> p.. ~ 0 Z Co> Ue. ~u
M !"'i ...; II'i ...c r..: 00 Qi 0 ,...;
...... - ....
!$
8
..J.
x
o
o
"'"
"'"
('l
o
\D
~
,z
U
i:J."
EB
'"
'"
o
I
'"
~
~ II
~JI
~~
~~
. ..... Cl::S
~~
.......,
~
.0
-t:
&
EB
...
...
o
I
...
,....-1
~ II
~JI
~~
~~
. ...... C\$
~~
~
~
.c
~
&
~
:>
..,
~~
#
.
.,
f
~
~
'(La
J
~!
it
WLC
Arch teets
..~ lorry Wolff, AlA. George M. Wiens, AlA. Robert J. Hensley, AlA . James P. DiCamillo, AlA . Glenn Ueda, AlA
~ I Max Medina, AlA · Kelley Needham, AlA
December 15, 2003
PROJECT COST HISTORY TO DATE
Gilroy Police Facility
Project 0024400.02
ITEM COST
Original Low Bid - May 2003 $ 26,137,000.00
Cost Estimate - Option 2 20,720,000.00 i
Reduction from Orie;inal Low Bid 5,417,000.00 i
Value Engineering/Items Applied to Option 2
Deletion of Auger Pile Shoring System
Deletion ofB2 Parking Level
10% area reduction ofB1 Parking Level
Raise B I Parking Level to grade
Deletion ofHV AC from B 1 Parking (provide natural ventilation)
Deletion of 2nd Floor Level, relocate Dispatch to main administrative level
Reduction of roof plaza area, omit plaza planters/ landscape/ fountain
Simplify roof design
Reduction of structural fireproofing
Deletion of clock/antenna tower at round-about
Deletion of Utility Building
Approved Project Construction Budget $ 19,354,644.00
Project Soft Costs Remaining 3,075,818.00
TOTAL BUDGET REMAINING TO DATE $ 22,430,462.00 ,
~ "
Total Costs- Option 2 $ 23,795,818.00
Potential VE Items 680,000.00
Total Option 2 Less VE Items $ 23,115,818.00
Difference between Remaining Budget and Option 2 $ I
685,356.QO I
Virginia Dare Tower. 1 0470 Foothill Boulevard. Rancho Cucamonga,Califomia 91730 . 3754 . ph: 909987 0909 fax: 909 9809980
1110 Iron Point Road. Suite 200. Folsom. California 95630.8301. ph: 916 3559922 fax: 9163559950
1250 4th Streelt Suite 150 . Emeryville, California 94608 . 2901 . ph: 510 450 1999 fax: 510 450 2525
Additional Potential Value Engineering Items
! Shell out various program spaces $ 170,000.00
! Simplify garage storage 80,000.00 I
! Downsize emergency generator 30,000.00
! Reduce street lighting 25,000.00 I
I
! Reduce landscaping 25,000.00
! Early Construction 350,000.00
TOT AL- VALUE ENGINEERING ITEMS $ 680,000.00
Major Potential Value Engineering Items
Split Police Department Programmed Facilities
NEW BUILDING EXISTING BUILDING !
- Administration - Neighborhood Services i
,
, -Property/Evidence - Dispatch
-Patrol - Custody
- Investigations/Detectives - Records
FC:fw
P0024400x5-ce
WLC
Architects
.....- Larry Wolff, AlA. George M. Wiens, AlA . Robert 1. Hensley, AlA. James P. DiCamillo, AlA . Glenn Veda, AlA
~ I .v1ax Medina, AlA · Kelley Needham, AlA
December 15, 2003
COST ESTIMATE - REDESIGN OPTIONS
Gilroy Police Facility
Project 0024400.02
ITEM AREA/SF. COST/SF. * AMOUNT
OPTION 1 - Raise Parking Structure to Grade
Main Building/Custodial Facility 49,920 $ 266.95 $ 13,326,144.00
Parking Structure on Grade Below 60,350 73.30 4,423,655.00
Building
Site/Staging/Emergency Generator 3,362,356.00
and Enclosure
Construction Costs Option 1 110,270 $ 191.46 $ 21,112,155.00
Remaining Soft Costs 3,075,818.00
TOTAL OPTION 1 11 0,270 $ 219.35 $ 24,187,973.00
Expenditures to Date $ 2,971,182.00
GRAND TOTAL OPTION 1 110,270 246.29 $ 27,159,155.00
$ 22,430,462.00 I
I AVAILABLE CITY FUNDS
* Includes Contractor overhead/profit and contingencies.
Virginia Dare Tower. 1 0470 Foothill Boulevard. Rancho Cucamonga,Califomia 91730 - 3754. ph: 909 987 0909 fox: 909 9809980
1110 Iron Point Rood. Suite 200. Folsom. California 95630 - 83010 ph: 9163559922 fox: 9163559950
1250 4th Street. Suite 150. Emeryville, California 94608 - 2901 . ph: 510 450]999 fox: 510 450 2525
ITEM AREA/SF. COST/SF.* AMOUNT
OPTION 2 - Raise Parking to Grade - Reduce Size by 10%
Main Building/Custodial Facility 49,920 $ 266.95 $ 13,326,144.00
Parking Structure on Grade Below 55,000 73.30 4,031,500.00
Building Reduced Size
Site/Staging/Emergency Generator 3,362,356.00
and Enclosure
Construction Costs Option 2 104,920 $ 197.48 $ 20,720,000.00
Remaining Soft Costs 3,075,818.00
TOTAL OPTION 2 104,920 $ 226.80 $ 23,795,818.00
Expenditures to Date $ 2,971,182.00
GRAND TOTAL OPTION 2 104,920 $255.12 $ 26,767,000.00
ITEM AREA/SF. COST/SF.* AMOUNT
OPTION 3 - Eliminate Parking from Building
Provide Parking Off-Site at 2-Level Parking Deck i
Main Building 46,270 $ 259.06 $ 11,986,706.00
Custodial Stmd Alone 3,650 650.00 2,372,500.00 I
t
Sally Port 800 200.00 160,000.00 I
Site/Staging/Emergency Generator 3,362,356.00
and Enclosure
Single Parking Structure, Rosanna and 80,000 55.00 4,400,000.00 ,
Seventh I
Construction Costs Option 3 130,720 $ 170.45 $ 22,281,562.00 I
I Remaining Soft Costs 3,075,818.00 i
TOTAL OPTION 3 130,720 $ 193.98 $ 25,357,380.00
Expenditures to Date $ 2,971,182.00
I GRAND TOTAL OPTION 3
130,720 I $
216.71 I $ 28,328,562.00 r
* Includes Contractor overhead/profit and contingencies.
GILROY CIVIC CJ1:NTER MASTER ,PLAN
Gilroy, California
Supplemental Parking Assessment Report
'~I'
'< L-,-
i ~
~
.
I ~ I
,i!
@
- - ~ - . - __ - c. .- _ - _.... ..-. .-.-:: "'" -
LmTll11111111111111111111111111 J
Wheeler
Community
Center
~,,-~,
. .@IJIlIIIIIIIIIIIIII
- II~~~
r' t~:,:~IC::ll::L~1 =,1
..'lIST SFIr.-fffi \nl!'Sl'
-.. .- ..~""-""'~.._'''.'''-"' ~_.
i
. . ---. :---'c::
, ,
"
"
Final Report
M
Prepared for
WLC Architects
Rancho Cucamonga, California
10 December 2003
HI(jGINS ,~SS()CI^TE)
TABLE OF CONTENTS
Page No
Executive Summary
CHAPTER 1 - Introduction 1
1.1 Proj ect Description................. .................. ................... .......... .................. .......................1
1.2 Scope of Work .................... .................. ................ ................................. .......................2
CHAPTER 2 - Parking Assessment
2.1 Background to Parking Assessment...... ............... .................... ............. ................... ......4
2.2 Existing Roadways for Gilroy Civic Center Precinct....................................................4
2.3 Phased Parking Assessment... ................. ............... ................ ........................................5
2.3 Parking during Construction............................ .......... ............................ ...7
CHAPTER 3 - Conclusions and Recommendations
3.1 Concluding Comments.......... .................. .............. .................... ....................................9
3.2 Recommendations.................. ................. ................ ....... ........ ............... ................... ......9
A03-13l Final Report.doc
LIST OF EXHIBITS
EXHIBIT 1 - 3 Minute Parking Walking Line
EXHIBIT 2 - Existing Parking 2003
EXHIBIT 3A - Phase 1A - New Police Facility Parking
EXHIBIT 3B - Phase 1A - Parking during Construction of New Police Facility
EXHIBIT 3C - Phase 1A&B - Parking for Simultaneous Construction of New Police Facility &
Library
EXHIBIT 4A - Phase 1B - New Library Parking
EXHIBIT 4B - Phase 1A - Parking During Construction of New Library
EXHIBIT 5 - Phase 2A - City Hall Annex Parking
EXHIBIT 6 - Phase 2B - Senior Center expansion Parking
EXHIBIT 7 A - Phase 2C - Wheeler Community Center Expansion Parking
EXHIBIT 7B - Phasing of Final Parking Construction
A03-l3l final Report.doc
Executive Summary
This supplemental parking assessment report evaluated the anticipated impact from the change or
redesign of the Police Facility and Basement Parking as part ofthe revised Gilroy Civic Center
Master Plan. Six Phases were assessed namely, existing 2003 conditions, Phases 1A & 1B and
Phases 2A to 2C. The detailed results have been discussed in the chapters of this report and the
conclusion is that the proposed parking implementation plan to support the Gilroy Civic Center
Master Plan would be adequate.
The location and proximity ofthe parking spaces available to the Civic Center users is such that
the principles of shared parking can be successfully applied to the analysis of the parking
requirements for the re-development ofthe Civic Center Precinct. The primary objective ofthe
parking assessment was to ensure that parking would be provided to the users ofthe facilities as
conveniently as possible, and ifnot located adjacent to the facility, within a 2 minute or 480 feet
walking distance from the different Civic Center Facilities at an average walking speed of 4 feet
per second. However, for seniors, a walking speed of2.8 feet per second or 336 feet distance was
used.
The parking assessment has shown that the existing parking supply exceeds the parking demand
by approximately 50% and that an average parking supply ratio of more than the 3.33 parking
spaces per 1000 square feet. of building is available for the existing situation. The ratio of3.33
parking spaces per 1000 square feet was used as the criteria to be achieved through all the
development phases of the Gilroy Civic Center Master Plan. The results from the parking
assessment show that the desired Civic Center Precinct parking supply ratio of 3.33 parking
spaces per 1000 square feet of building would be achieved for all Phases. However, the final
layout only provides a ratio of3.30 spaces/1000 square feet.
The following measures are necessary to facilitate the Gilroy Civic Center Master Plan:
1. The reconfiguration of the existing parking and construction of new parking lots planned
with each development phase ofthe Master Plan should be implementation as programmed.
This would provide a parking supply ratio of 3.33 parking spaces per 1000 square feet. of
building to serve the Civic Center Facilities for the duration ofthe period evaluated.
2. A formal parking policy should be developed and specific parking spaces assigned to staff
during each ofthe phases of the Gilroy Civic Center Master Plan.
A03-13l Final Report.doc
CHAPTER 1 - Introduction
1.1 Project Description
This supplemental parking assessment study report has been prepared in response to a change in
the design of and number of parking spaces that will be provided as part of the new Police
Facility in Gilroy. An initial Traffic Impact Study was prepared by Higgins Associates! to
address the traffic and parking implications ofthe expansion ofthe Gilroy Civic Center Facilities
to address growth into the year 2039.
The population of the City of Gilroy has more than tripled in size in the last 30 years from
12,641 people in 1970 to 41,464 in 2000. It is estimated that by the year 2020, the population of
the Gilroy area will be approxirnately 62,500 people.
Both the Police facility and the Library were previously expanded in 1986 and 1987. By their
respective accepted industry standards, both the Library and the Police Station currently lack the
square footage necessary to adapt to the growing needs ofthe City of Gilroy. The Civic Center
Master Plan=s phased improvement approach will accommodate the increasing number of City
residents and corresponding city staff.
The Gilroy Civic Center Master Plan includes five improvement phases to cater for the needs of
the Civic Center Facilities from 2003 through 2039 buildout conditions. The various phases can
be summarized as follows:
$ Phase 1A - The existing Police Facility located between Sixth Street to the north,
Seventh Street on the south and between Rosanna Street on the west and Church Street
on the east will be replaced with a new facility located on a site bounded by Dowdy
Street on the west, Seventh Street on the south and Hanna Street on the east.
$ Phase 1B - The existing Gilroy Public Library will be replaced by a new facility located
on the same site bounded by Sixth Street on the north, Hanna Street on the west and
Rosanna Street on the east.
$ Phase 2A - The Vacant Police Facility located between Sixth Street to the north, Seventh
Street on the south and between Rosanna Street on the west and Church Street on the east
will be remodeled and utilized as a City Hall Annex.
$ Phase 2B - The existing Senior Center located on the corner of Sixth Street and Hanna
Street will be expanded and a surface parking lot located on the corner of Sixth Street
and Dowdy Street will be provided adjacent to the Senior Center to serve the expanded
facility=s parking needs as well as provide overflow parking required by the Police
Facility.
1 Traffic Analysis and Parking Assessment Report, April 15, 2002, prepared by Higgins Associates.
A03-13l FINAL REPORT. DOC
1
$ Phase 2C - The Wheeler Community Center located adjacent to Sixth Street and
between Rosanna Street on the west and Church Street on the east will be expanded. The
land, adjacent to the County's Family Services Facility and on Rosanna Street between
Sixth and Seventh Street, will be developed into surface parking areas to serve the
expanded Civic Center=s parking needs as part ofthis phase.
As part of Phase 1 (approved projects), the City of Gilroy is proposing to demolish the existing
library facility by the year 2003/4, and build a new library facility at the existing site (contingent
on library state bond funding). The new two-story, 53,231 square-foot library building would be
constructed at its current location and would be designed to meet the long-range needs of the
community.
The new Police Department facility would consist of a two-level police station of approximately
48,970 square feet on the proposed 1.89-acre site bordered by Dowdy Street, Seventh Street,
Hanna Street, and the City=s existing Senior Center. Proposed with the new police facility is a
single-level, 114-vehicle below-grade parking structure. To accommodate the new police
facility, the seven city-owned residences on Dowdy and Hanna Streets, two of which are used for
City offic~s, were demolished. The projects described under Phase 2 ofthe Civic Center Master
Plan have not been scoped and scheduled for construction.
Detail of the existing and proposed Civic Center Facilities is shown in the table below.
Phase Estimated Description Existing Size Future Size in
Starting/Completion Time in SF. SF.
Phase lA 2004/5 to 2005/6 New Police Facility 17,665 48,970
Phase IB 2004/5 to 2005/6 New Library 12,700 53,231
Phase 2A 2007/8 to 2008/9 City Hall Annex added 30,215 47,165
Phase 2B 20010/11 Senior Center 10,515 15,515
Phase 2C 2013/14 Wheeler Community 15,890 19,890
Center
Total SF. of Buildings 86,985 SF. 184,771 SF.
Not included for upgrading in the Gilroy Civic Center Master Plan is the County's Family
Services Facility that is 4,795 square feet in size.
1.2 Scope of Work
< Parking Assessment
To determine the parking implications of the revised design of the Police Facility and the
A03-l3l FINAL REPORT.DOC
2
reduction of the number of parking spaces that would be provided in the basement parking
structure of the Police facility, a supplemental parking assessment was performed.
The same Phased development approach of the Gilroy Civic Center Master Plan was used in the
supplemental parking assessment. The following parking phases were evaluated:
o Existing (2003) conditions;
o Phase 1A - Police Facility;
o Construction of Phase 1A - Police Facility
o Simultaneous Construction of Phase lA&B - Police Facility & Library
o Phase 1B - New Library;
o Construction of Phase 1B - New Library
o Phase 2A - City Hall Annex;
o Phase 2B - Senior Center; and
o Phase 2C - Community Center and Full Parking Development.
A03-l3l FINAL REPORT. DOC
3
CHAPTER 2 - Parking Assessment
2.1 Background to Parking Assessment
The Gilroy Library, City Hall, Police Facility, Senior Center, Wheeler Community Center and
the County=s Children=s and Family Services make up the Civic Center Precinct. These
facilities are located in close proximity to each other on three City blocks bounded by Sixth
Street, Seventh Street, Dowdy Street and Church Street. Several off-street parking lots have
been constructed to provide parking for the Gilroy Civic Center Precinct. Hanna Street and
Rosanna Street are two local streets running in a north/south direction providing access to and
additional parking to the Civic Center facilities. It is planned to partially close and incorporate
Hanna Street and Rosanna Street into the Civic Center Precinct in future.
Due to the close proximity of the different facilities that make up the Civic Center Precinct, as
well as the different peak use characteristics, the principles of shared parking can be applied and
the parking spaces available in the Civic Center Precinct can be shared according to the different
facility=s demand for parking. However, care should be taken that the parking for handicapped
persons are located conveniently to all facilities and complies with Americans with Disabilities
Act (ADA).
This supplemental parking assessment is based on the comprehensive parking inventory and
utilization survey (of all on and off-street parking within a 720 feet radius - 3 minute walking
distance from the central point to the existing Gilroy Civic Center Precinct) that was undertaken
on 4 days between Thursday February 14th and Wednesday February 27th 2002. This was done to
get a clear and global understanding of the parking utilization patterns of the users for the
different facilities in the Civic Center Precinct, as well as to determine the extent of the
encroachment into the adjacent neighborhood streets.
This supplemental parking assessment should thus also be read in conjunction with the Initial
Project Report prepared by Higgins Associates, dated April 15, 2002.
Furthermore, it should be noted that two additional off-street parking lots on the corners of
Seventh Street with Rosanna Street and Church Street with 16 and 39 parking spaces
respectively have been implemented since the completion of the previous study.
2.2 Existing Roadway System for Gilroy Civic Center Precinct
Monterey Road, Church Street and Sixth Street provide primary access to the Civic Center
precinct. Other roadways in the area serving the Civic Center precinct include Seventh Street,
Dowdy Street, Hanna Street and Rosanna Street.
Church Street is a two-lane collector street providing north-south access in the east-central
portion ofthe city. On-street parking is provided in the vicinity of the Civic Center precinct and
access to some of the off-street parking lots is taken off Church Street.
A03-13l FINAL REPORT.DOC
4
Dowdy Street is a two-lane residential street running in a north-south direction on the western
side of the Civic Center precinct. On-street parking is provided in the vicinity of the Civic
Center precinct.
Hanna Street is a two-lane residential street running in a north-south direction through the
center of the Civic Center precinct. On-street parking is provided in the vicinity of the Civic
Center precinct and access to some of the off-street parking lots is taken off Hanna Street.
Monterey Road is a two-lane arterial traversing east-central Gilroy in a north-south alignment.
Rosanna Street is a two-lane residential street running in a north-south direction through the
center of the Civic Center precinct. On-street parking is provided in the vicinity of the Civic
Center precinct and access to some ofthe off-street parking lots is taken off Rosanna Street.
Seventh Street is a two-lane collector street running in an east-west direction through the center
of the Civic Center precinct. On-street parking is provided in the vicinity ofthe Civic Center
precinct and access to some of the off-street parking lots is taken off Seventh Street.
Sixth Street is a two-lane collector street providing east-west access to the Civic Center precinct
Limited on-street parking is provided in the vicinity of the Civic Center precinct and access to
some of the off-street parking lots is taken off Sixth Street.
2.3 Phased Parking Assessment
The parking assessment for the Gilroy Civic Center Master Plan was performed for seven stages
(existing situation plus six phased improvement project stages). The various phases are as
follows:
$ Existing (2003) Situation
$ Phase lA - Construction of the new Police Facility
$ Phase 1B - Construction of the new Gilroy Public Library
$ Phase 2A - Remodeling of the Vacant Police Facility as a City Hall Annex
$ Phase 2B - Expansion of the Senior Center
$ Phase 2C - Expansion of the Wheeler Community Center & Full Parking Development
The parking assessment is based on two main principles:
$ To endeavor to maintain a parking supply ratio of at least, (or as close to) 1 parking space
per 300 square feet of building throughout the redevelopment process (3.33 parking
spaces per 1000 square feet). There is no specific requirement for governmental
institutions, public library and public utility offices stipulated in the City of Gilroy
zoning ordinance. However, at the time of the initial parking assessment it was agreed by
the City of Gilroy Planning Department, that it would be the most appropriate ratio to
use. The City of Gilroy zoning ordinance should thus be updated to reflect this
A03-131 FINAL REPORT. DOC
5
requirement.
$ To provide parking to the users of the facilities as conveniently as possible and if not
located adjacent to the facility, within a 2 minute or 480 feet walking distance from the
different Civic Center Facilities at an average walking speed of 4 feet per second.
However, for seniors a walking speed of2.8 feet per second or 336 feet distance would
be used as the requirement (Refer to AASHTO Policy on Geometric Design a/Highways
and Streets 2001).
It should be noted that the parking assessment for the Civic Center Precinct as a whole, assessed
the parking within a 3 minute (720feet radius) from the center point of the Civic Center Precinct,
whilst the parking assessment of each individual facility in the Civic Center Precinct (City Hall,
Library, Police, Community Center, Senior Center and County Children=s & Family Services),
looked at parking spaces available within 2 minute walking distance from each facility.
The table below shows the parking analysis for the existing 2003 situation and Phase I of the
Civic center Master Plan. The number of spaces allocated to each facility (and used in the
calculations in the table) are shown in Exhibits 2, 3A & 4A and based on the parking spaces
available immediately adjacent or very close to the facility. It should also be remembered that the
parking spaces are not fully utilized at this point in time and that a spare capacity exists for the
existing to Phase 1 of the redevelopment program
This table should be read in conjunction with Exhibits 2, 3A & 4A which graphically show the
parking available for each phase and used in the calculations in the table.
Parking Analysis Summary for Phase 1 of the Redevelopment
Existing - 2003 Phase I A - 2004/05 to 2005/06 Phase IB - 2004/05 to 2005/06
Refer Exhibit 2 Refer Exhibit 3A Refer Exhibit 4A
Size Parking Ratio / Size Parking Ratio / Size Parking Ratio /
Description Spaces 1000 SF Spaces 1000 SF Spaces 1000 SF
Police Facility 17,665 82 4.84 48,970 163 3.33 48,970 163 3.33
Library 12,700 78 6.14 12,700 126 9.92 53,231 198 3.72
City Hall 30,215 107 3.54 30,215 175 5.79 30,215 134 4.43
Senior Center 10,515 42 3.99 10,515 44 4.18 10,515 35 3.33
Community Center 15,890 60 3.78 15,890 65 4.09 15,890 64 4.03
Children=s Services 4,795 19 3.96 4,795 29 6.05 4,795 29 6.05
Totals 91,780 3.88 4.26 123,085 602 4.89 164,985 623 3.81
From the table it can be seen that the average parking supply ratios for the existing situation,
Phase IA and Phase IB are 3.88, 4.89 and 3.81 respectively, which complies with the average
parking supply ratio of at least 3.33 parking spaces per 1000 SF. of building. The overall ratio of
3.33 parking spaces per 1000 square feet of building would thus be maintained through this
A03-l3l FINALREPORT.DOC
6
phase ofthe redevelopment.
The next table shows the parking analysis for Phase 2 of the re-development program. The
number of spaces allocated to each facility (and used in these calculations) are graphically shown
in Exhibits 5, 6, & 7 and based on the parking spaces available immediately adjacent or close-by
to the facilities. These tables should be read in conjunction with Exhibits 5, 6, & 7 which
graphically show the parking allocation for every civic facility during each phase.
Parking Analysis Summary for Phase 2 of the Redevelopment
Phase 2A - 2007/08 to 2008/09 Phase 2B - 20010/11 Phase 2C - 2013/14
Refer Exhibit 5 Refer Exhibit 6 Refer Exhibit 7
Size Parking Ratio! Size Parking Ratio! Size Parking Ratio!
Description Spaces 1000 SF Spaces 1000 SF Spaces 1000 SF
Police Facility 48,970 163 3.33 48,970 163 3.33 48,970 163 3.33
Library 53,231 184 3.46 53,231 182 3.42 53,231 166 3.12
City Hall 47,165 161 3.41 47,165 162 3.43 47,165 157 3.33
Senior Center 10,5]5 44 4.18 15,515 44 2.84 15,515 44 2.84
Community Center 15,890 57 3.59 15,890 58 3.65 19,890 67 3.37
Children=s Services 4,795 23 4.80 4,795 23 4.8 4,795 28 5.84
Totals 180,566 632 3.50 185,566 632 3.41 189,566 625 3.30
From the table it can be seen that the average parking supply ratios for Phase 2A to Phase 2C are
3.32, 3.54, and 3.43 respectively. This implies that almost all the future phases would comply
with the parking supply ratio of at least 3.33 parking spaces per 1000 SF. of building. The only
exception is for the final parking layout where a rate of3.30 spaces per 1,000 square feet would
be achieved.
The individual parking ratio for the Senior Center (Phase 2B) shown in the table is slightly less
than the 3.33 parking spaces per 1000 SF. However, this ratio only reflect the parking spaces
adjacent and close-by the facilities and do not take into consideration the shared parking
available within the 2-minute walking distance.
2.4 Parking During Construction
There are thirty parking spaces required to accommodate construction staff during each
construction phase. Three parking scenarios were assessed to evaluate the impact of the
construction of the new facilities on the provision of parking for other Civic Center Facilities.
The three scenarios are:
. Construction of Police facility on its own (30 spaces);
. Construction of New Library on its own(30 spaces); and
. Simultaneous construction ofthe Police Facility and the New Library (60 spaces).
A03-13l FINAL REPORT. DOC
7
The following table shows the detail ofthe parking evaluation during construction and should be
read with Exhibits 3B, 3C and 4B.
Construction Parking Analysis
Phase IA - 2004/05 to 2005/06 Phase IA&B - 2004/05 to Phase IB - 2004/05 to 2005/06
2005/06
Refer Exhibit 38 Refer Exhibit 3C Refer Exhibit 48
Size Parking Ratio! Size Parking Ratio I Size Parking Ratio!
Description Spaces 1000 SF Spaces 1000 SF Spaces 1000 SF
Police Facility 17,665 82 4.84 48,970 82 4.84 48,970 136 2.78
Library 53,231 62 4.88 0 0 0.00 0 0 0.00
City Hall 47,165 III 3.67 47,165 87 2.88 47,165 155 5.13
Senior Center 10,515 40 3.80 15,515 40 3.80 15,515 40 3.80
Community Center 15,890 49 3.08 15,890 53 3.34 19,890 89 5.60
Children=s Services 4,795 16 3.34 4.795 17 3.55 4.795 29 6.05
Totals 91,065 360 3.95 78,365 279 3.56 11 0,385 449 4.07
From the table It can be seen that the average parking supply ratios for the construction of
Phase 1A on its own, for simultaneous construction and Phase 1B on its own are 3.95, 3.56, and
4.07, respectively. This implies that with any permutation ofthe construction of Phase 1A and
Phase 1B, the parking supply ratio of at least 3.33 parking spaces per 1000 SF. of building would
be maintained.
A03-l3l FINAL REPORT.DOC
8
CHAPTER 3 - Conclusions and Recommendations
3.1 Concluding Comments
This supplemental parking assessment report evaluated the anticipated impact from the change or
redesign ofthe Police Facility and Basement Parking as part ofthe revised Gilroy Civic Center
Master Plan. Six Phases were assessed namely, existing 2003 conditions, Phases 1A & IB and
Phases 2A to 2C. The results have been discussed in the preceding chapters of this report and the
conclusion is that the proposed parking implementation plan to support the Gilroy Civic Center
Master Plan would be adequate.
The location and proximity ofthe parking spaces available to the Civic Center users is such that
the principles of shared parking can be successfully applied to the analysis of the parking
requirements for the re-development ofthe Civic Center Precinct. The parking assessment has
shown that the existing parking supply exceeds the parking demand by approximately 50% and
that an average parking supply ratio of more than the 3.33 parking spaces per 1000 square feet of
building is available for the existing situation.
The desired Civic Center Precinct parking supply ratio of 3.33 parking spaces per 1000 square
feet of building would be achieved for most of the Phases. The only exception is in the final
configuration where a parking ratio of 3.30 would be achieved.
3.2 Recommendations
The phasing of the parking lot improvements was carefully planned and an average parking
supply ratio of 3.33 parking spaces per 1000 square feet. of building could be maintained
throughout most of the Gilroy Civic Center Master Plan.
The following measures are necessary to facilitate the Gilroy Civic Center Master Plan:
1. The reconfiguration of the existing parking and construction of new parking lots planned
with each development phase of the Master Plan should be implementation as
programmed. This would provide a minimum parking supply ratio of3.30 parking spaces
per 1000 square feet of building to serve the Civic Center Facilities for the duration of
the period evaluated.
2. A formal parking policy should be developed and specific parking spaces assigned to
staff during each of the phases of the Gilroy Civic Center Master Plan.
A03-l3l FINAL REPORT. DOC
9
: :
r720ife,t
. 'ot'4ff/se'e
---------..
(;'J~I..~~',ii""""'.""""""""'.,
Library
,
"
,
"
to'
.,.'."i
\J";/ ,
DOWD'Imm
~
;.,.0.,...".
~:
~ ,,;
"~~,:r:
,I
~:
All~
"'~
'~
.~
,
t
,
\
,
,
,
,
,
.
.
I
I
.
.
,
., ..." '::'C'"
~ ,',
il
=
KA.NNA SlREn
ROWMSTRHT ,
CHURCH STREEt
~",
, ....
! '"
"
Legend
_ Future Parking Areas
_ 720 feet radius from center of
L' Civic Center Precinct and M
extent of Parking Survey HGG'Nl.A,SSOClAE>
3 Minute Walking Radius
For Shared Parking
Center Master Plan Parking
EXHIBIT 1
Legend
- Police Services Parking - 82
_ Library Parking - 78
I - City Hall Parking -107
II - Senior Center ParkinQ - 42
i" County Children Services Parkinp -19
II _ Wheeler Community Center Parkmg - 60
IL Handicapped Spaces -12
j
i
I
~ i
~ j
I
.............:::::............-:;.-:..-::......-...........-. , . :2==~__m~:__-.~:::_, I
I Existing Conditions (2003) : I
I Civic Center Master Plan Parking .
IJo.ec~,!!~~~10,2003) EXHIBIT 2 .
.. ..-.................................... .-.--...............................................................................................................:
DOWDY STREBT
....:;~
:,,,
.::o,~!
.'~
, .~
r
'1':
'"
~
Future
Police
~ Facility
~ Site ! 1 ;:d,~
~ : ,mmm mmm-IIIIIII-II~;~~r..m.""I,:I;="~~ II..~-I.!
Iii =@1. .........~ · I . : '11 !
[:; .. " :
ti,;.,..,:;::.:;c@:::.:::.::::0:dIlll~J.III~_=~~J{i~~"J
HANNA lmEJrr
.mm'TI
_:Q....~,,~ "" '<"- " ,,'\) ~\..\..\..\..~\..~),,'h',
'1..:.....................................,1f..m.........~~-.,.,."'.".,.""."".."':...,...."'.,.,.:y, ~l
'fr :. @;'
I "t '1)1111IJI-'_1 II n 1111I LII.r-ii
i'[
.
E-----------...jC=;--!--rE@.-
~@~ ~I~.
: ~ H=
~ !,t;
....._...__h_.._m...mm..........m......____..
.........-.-.........__........................................-...............
...............-.....,...-....-.......---
,
."j~
~...
i!;
: rl;;
1M!
HANNA STREET
'i
if
'[
ii!
'.1
,I
:1
'i
ROSANNA lmEJrr
HANNA 5'I1l.HfIT
DOWDY ST1lEET
"
(1
~
~
~
[1
....................--.-.....-...-......... ..............-.......-..........-
....-.................7......::....:....::::.::.::..:::.::..:::.:::.:.:::::::::...............................:"1
.~ lrmmmuiillll''']!!
~~ u"HII+~I+HHlllu '1
t= @ ~
1= 1111 mlD 11I11111111.n ~
i'i
::i
~
~
~. ..':, ,
(," : il
:,:," /: ~"....""""""<.._...,'. . .: ~
=:":;:::1\( ."
.t", ~
.:::;
. ,""'.
Library
I
Ploy
-
CHURCH STREET
Legend
.. Police Services Parking .163
_ Library Parking. 126
_ City Hall Parking. 175
_ Senior Center Parkin~ . 44
.. County Children Services Parkinp - 29
_ Wheeler Community Center Parkmg .65
Handicapped Spaces. 15
Phase 1 A (2004/5 to 2005/6)
New Police Facility
Civic Center Master Plan Parking
10, EXHIBIT 3A
'.~i'~0
.~
........... /
HANNA STIU!f,'f
IlANNA S'l'UlIT
@
DOWDY STREET
A
V
"'
',.!: ~
'"
~ ~
~ ~
~ ~
~
/P~::-il
'\GITTIl1lTlJTT1JTT~
r--j 'm ;111111111!nIIJII\II>I.,1
Library
i rrT'TTT"1 . i I'iJi'ITI fTTTT11'!'''-''' rr-ITTTlT~ '..m....m....
f -.J : " I i LJllo1Q.J f II " . f U i ! Ii II!. i! ID
i' @ ....... ... ........ ... m m mm mmm,X
i i.l.WlLH'! ,,_ I ! I I' 1",;7.////// ->>/////// ;1'
"o,~;"C.I},I~~III.I'~;'~:Xi;"::::::0:""::';~:;"
CHURCH STREET
Construction Parking. 30
.. Police Services Parking. 82
.. Library Parking. 62
.. City Hall Parking .111
I .. Senior Center ParkinQ . 40
11_ County Children ~ervlces Parkinp .16
Ii .. Wheeler Commumty Center Parking - 49
II Handicapped Spaces .11
Phase 1A (2004/05 to 2005/06)
Construction of New Police Facility
Civic Center Master Plan Parking
(December 10, 2003) EXHIBIT 3B
~I'~~
~
.~.....-
HANNA snEET
HANNA STREEJ'
DOWDY STREET
-s.
~
~
:.;: ~
~ :7
B
~
~ ~
~
~
Legend
1 Construction Parking - 60
I - Police Services Parking. 82
- Library Parking. 0
_ City Hall Parking. 87
_ Senior Center ParkinQ . 40
_ County Children Services Parkinp - 17
_ Wheeler Community Center Parkmg . 53
Handicapped Space~-10
CHURCH STREET
Phase 1 A&B (2004/05 to 2005/06)
Construction of New Police Facility & Library
Civic Center Master Plan Parking
(December 10,2003) EXHIBIT 3C
~
HANNA STREET
HANNA S1lUmT
ROSANNA STRBEr
OOWDY Sl'REJIT
.........................- .................................................... "::::::::::::::,"''<.' ;...,":::":":-;_: ;:-::::.-.:::::::::::--..:-:::":..:.-:-;,,,.-::,.,.-:::"":.,,..:::..:.::...::...:......:."'"
~
. --:.
i..rr'nTnm-,.r'l"'T"i;"rnrUiI.
n ii, I!~! q;" I;, 1] Iii!
UlrlrtTrllullTllTU . .>
@ =
I 1 I I IU.'fJlfl1Mll '.:.iI'.., I I I I I 1 I I 1 I I. .~ . '.....'.
Ul..l....W.EiI I.WJL.LU...l... : :.)
fu
~
~
//:1"-;' .: ~
'.f i. ;
1'.1. .m'...
<:~ . .
::l
"
~
"f~~Q~;frrrTTl1fiTTTrTF1"I"r'rl"F6L.'U
@=
; fllTTITUllfl.J'fllTITlTUTnmm
L" @ @
I UJJJl.l.lTI] \ "Dill i III : I~LLlLlJ.l- :
'-, '~II~.
/ 111 I iI'll : 1@J1111I : III:" 9 I. --
," -.... ....::.':..:.:::...:..,...;,>---.,,--:
......i
,; :"' ~]- ....
JL:", ~:
. .
~ ~.
II~@ l:-
'. . ""
i ~ ~~:-.-~.- ~
i ~ i...-- - ;-.......
: . .
. .
~_..._~ j'.......
:: l....._ ._____._.
::, 0 !
,i . ~l:;;; ~::J
--
...- i ~ --
: @ -- -- '
, --
-- ---
.... -- ---
l-::- Sm ==
L...'-------, : r"-"--
J 1 . J ,
~_...J
CHURCH STREET
Legend
.. Police Services Parking - 163
.. Library Parking -198
.. City Hall Parking - 134
_ Senior Center ParkinQ - 44
.. County Children Services Parkin9 . 29
_ Wheeler Community Center Parkmg - 64
Handicapped Spaces -16
Phase 1 B (2004/5 to 2005/6)
New Library
Civic Center Master Plan Parking
10, EXHIBIT 4A
~
c~
ALLEY
:f
:J
HANNA STBJ!Bf
OOWDY STREET
."
~
i ~
l.'i
~ ~
~
~,:
m
(111111 T 11I11 ~IIIII ! Ii" "W1J' .....~IIIIJlillli~1111111
,...............................................................+';,.;j"'C,.'.'
W ! .
~[; @~.i
@=-l~ ~
-'- t._.......
jnl~
=rLiiJ ~
! i i I i.l~
Legend
- Construction Parking - 30
liliiii Police Services Parking -136
liliiii Library Parking - 0
liliiii City Hall Parking -158
_ Senior Center ParkinQ - 40
I11III County Children ServIces Parkin9 - 29
_ Wheeler Community Center Parking - 89
Handicapped Spaces -14
CHURCH STREET
I~I
HANNA STREET
..___..___.__......__....__.___.___.__.__.___....__..___......_._._._____.........,'_',..,..,'__,._.,.,.". ,..'..--.--."..........'..'...---------.-.-..----.---.......--.-..__.____._n__.__."""'..,.
" .,.."..""....,.,.......,..."...
. :'.F=:.:::..~"=::;:"==:.:,=;:::"::,,::::.:.:J,.";l.....--.--""--,:.:==:.:,====,,:,,.:.:,:.:.:::,,::::::;:.:=:.:=:.:,"=:;,,;:.:,,"~
i Phase 1 B (2004/05 to 2005/06) ..
, Construction of New Library i
..! Civic Center Master Plan Parking i
.. i (De~ember 1o,2oo3l..........................EX..HIBI14B
I
'1
HAl'<"t\A sr~
---==--.- I
I
~A snBlJT
~:"::-::::~.;=::",..
" ,
J
. I
I.,
- .,' '.-,- - ----.- '--...+--.---.--" .....-------
n" __.".,-" _-"_,,_,,..,. 'O~_", -,-,,,,_o_r,-,.- _+"~_=-_....-=."_.,,,,, '.~"'- ~,--_, ,',' ,=,..-==~..,.,.,.-.-~
.,-,' c,-.-;""~~::O-';;"" ;';~>;"_';";~'~':-~::_~-::'-:::~~_~~'_;:;::::;';;_' i
DO":'iDY rn..BET
.t~
.:::":=--..:...~._---"1.,
Ii!
m
~
~
~
I'
L'=
t=.,,::!:,!!, ;'i": i ,: n
~: uttrtrti lttJ1ritthJ
i= G),
L_ I:?
=c:'CC~..'...-."_. ~~..':lCI." .:.
i: ;~,\ ~ i !
" 'II
::!~~]il"i"~; uLiJ U IIIL~I ~~O
r-
21..- U @ :; =
___I
~L_t
"",,,_"'0. "'"
OfURC!.i S1"RE1IT
J~j
..~-::;;;; -~
.- ----- -- -.. .. ------
- - -_._--~..._-,.__. "._-.-.,'-
. _____n_ _n...'___'- .' ___n,___ '0__
-- .--
-" :.~-_._=.~---
'"
j-
:=:>-1'
~' I
1 -"
'1.,
~ .'",--, - ''''',-
~
i
I
'In
ALLEY
u_ _._~__~_.____.._.n______ __ . ___
~-~-----_. - ----..' ---------
__ . ___ _ _. _~__,_"__,,,'_'U__"__'___~___
.:;:=,-,=~J
, .
-~""'..~.'=-<<=.;-~-"-
.~~~~:~r"~~-
~_._--, !
:_,::~'1
Phase 2C (2013/14 )
Phasing of Final Parking Construction
Civic Center Master Plan Parking
(December 10, 2003) EXHIBIT 7B
Denise Duffy & Associates, Inc.
PLANNING AND ENVIRONMENTAL CONSULTING
Monterey · Reno -San Jose
December 5, 2003
Larry Wolff/Frank Cuomo
WLC Architects
10470 Foothill Blvd.
Rancho Cucamonga, CA 91730
Re: Second Update to Initial Environmental Analysis Regarding Changes to the Gilroy Civic Center
Master Plan
Gentlemen:
As requested by Bill Little from Harris & Associates, I am submitting this letter to update and supplement
our letters dated September 19 and November 4, 2003 regarding the changes to the Gilroy Civic Center
Master Plan. I have reviewed the updated site plans, elevations, and renderings prepared for the
Architectural and Site Review.
It is my understanding that the most up-to-date redesign option currently under consideration for the
police facility eliminates subterranean parking entirely, moves the single parking level to the "first floor"
at grade, and moves the first floor of the building up to the second floor. In other words, it simply shifts
the overall structure (parking and building) up one level (approximately seven feet). However, the overall
height is still approximately four feet lower than the original design that was evaluated in the Initial Study
for the Civic Center project. In addition, I am informed that the ratio of 3.33 parking spaces per 1000
square feet of building space, which is the minimum criteria to be achieved through all of the
development phases of the Civic Center Master Plan, will still be achieved.
Given these facts, the current redesign will not result in any new significant environmental impacts that
would require preparation and circulation of an updated CEQA document. As before, all existing
mitigation measures remain relevant. Please call if you have any questions.
Sincerely,
Jeff Foster
Project Manager
DD&A
Monterey · Reno · San Jose
5310 Kietzke Lane, Suite 204B . Reno, NY 89511
Phone (775) 853-6090 · Fax (775) 853-6091' Email: ifoster@ddaplanning.com
www.ddaplanning.com
Exhibit "D"
Project Schedule
Gilroy Police Facility Redesign
Dece~ber15,2003
07/01/03 Phase One Scope on" ork & Action Plan
07/11/03 Complete Phase One Scope of Work.
08/0"1/03 Executiye Oversight Committee Meeting.
+()8/0"1/03 Council Review and Approve Redesign Scope of'Nork.
08/05/03 Phase Two - Preliminary Redesign Phase.
**09/15/03 PrelimirIary Redesign Options and Cause & Effect Matrix Submittal Received 9/22/03
**09/22/03 Ex€cutiye Oversight Committee Meeting.
+ 1 0/06/03 Council Re-v1e'N Redesign Options and Cause & Effect Matrix
+*10/0S/03 Parking Analysis (Submitted 10/15/()3)
**1012()/03 Preliminary Submittal to H&A(Submitted 1M2/(3)
**1fJ/28/03 @ 1:00 pm Redesign Documents and Draft Master Plan Update Submittal (Executive o.~sight
**11/05/03 Executive Oversight Committee Meeting (Date revised to ]O/2S/03 noted above)
11/13/03 Conference Call t-o Discuss Redesign Options
** 11/17/03 EOC Team Meeting conference call to Discuss new options and costs from WLC
**11/19/03 Submit and revievl Package viith Jay for transmission to Council at Retreat
12/08/03 Conference Call EOC to discuss new costs from DLA and Package for presentation to Jay
12/1 0/03 Presentation to Jay for approval of Package for COlUlcil
+**12/15/03 COlUlcil Review and Approve Redesign Documents and Draft Master Plan Update Altemaives
**01/08/04 First Outreach of Draft Civic Center Master Plan (Revisedfrom 12/1/03)
K:\Projects\Gilroy\PoliceStation'Scbedule 03'\WLC Redesign Project 8ch Updated 12-15-03_.rtf +Council Meeting
Gilroy Police Facility 1 ** Revision
-
-
Harris & Associak
,0
**02/16/04 Final Preliminary Redesign and Civic Center Master Plan Update Submittal
**02/26/04 Executive Oversight Committee Meeting
+03/01/04 Council Review and Approve Preliminary Redesign and Civic Center Master Plan Update.
**03/10/04 Phase Three - Construction Document Redesign
**04/27/04 30% Complete CD Progress Review Submittal.
**05/11/04 Executive Oversight Committee Meeting.
**05/18/04 Band C by Harris
**06/23/04 95% Complete CD and B&C Submittal.
**07/06/04 Executive Oversight Committee Meeting.
**07/07/04 Building and Planning Check for Permit Process
**09/01/04 Bid Package Submitted
**09/08/04 Executive Oversight Committee Meeting.
**09/13/04 Back Check for fmal Building Planning Check
+**10/04/04 Council Review and Approve Bid Package
**11/01/04 Bid sets available; Bidding phase begins.
** 12/01/04 Pre-bid conference.
**01/04/05 Bid Opening
**+02/07/05 Council Award Contract for Construction
**03/01/05 Begin Construction
**12/22/06 Final Completion/Occupancy
K:\Projects\Gilroy\PoliceStation'Schedule 03'\WLC Redesign Project Sch Updated 12-15-03_.rtf
Gilroy Police Facility 2
+Council Meeting
** Revision
-
-
Harris & Associak
\J-'
3Dl
I
--~.----~
-
-
ORIGINAL
Harrls & Associates
December 30, 2003
Mr. Bill Headley
Facilities and Park Development Manager
City of Gilroy
7351 Rosanna Street
Gilroy, CA 95020
Re: New Police Department Project Re-Bid - Work Order No. 49-A
Request for Budget Amendment No.2
Dear Mr. Headley:
This letter is to request a budget amendment for the subject project in the amount of $14.300 for the re-
bid phase, and additional cost estimate at a design development level of the revised construction
documents of the above-mentioned project.
If this fee is acceptable, please authorize by signing below, and on the attached duplicate original. Please
return one fully executed wet signature document, as our authorization to proceed. Should you have any
questions, please call me at (408) 842-5777.
Sincerely,
HARRIS & AS~OCIATE
Ii
J'\~//
Wi
William Little III
Project Manager
ACCEPTED BY:
C/ Mike Cooper
Project file
K:\ProgqnMt\Giiroy'\Amendments\Amend 2 to WO 49 PO Re-bid Headley.doc .,
178 Secon<1 Street, ~uite C Gilroy, California 95020-5100 408.842.5777 FAX 408.842.5758 gllroy@harns-assoc.com
3D!
City of Gilroy
ORIGINAL
.11
COMMUNITY DEVELOPMENT DEPARTMENT
Planning Divisiqn
Engineering Division
Building, Life & Environmental Safety
Housing & Community Development
(408) 846..0440; fax (408) 846..0429
(408) 846-0450; fax (408) 846..0419
(408) 846..0430; fax (408) 846-0429
(408) 846-0290; fax (408) 846-0429
March 12, 2004
CONTRACT ADDENDUM
(WORK ORDER NO. 63)
Agreement for: NEW POLICE DEPARTMENT PROJECT
Consultant: HARRIS & ASSOCIATES. INC
Contract Agreement Date: November 10.1998
This WORK ORDER shall become effective when The City Administrator, City Engineer,
Project Engineer, and Consultant have signed it. All documents forwarded to the Consultant for
signature shall be returned to the City of Gilroy properly filled out. Upon acceptance by the
City, the Consultant's duplicate original will be returned as authority to proceed with the work.
DESCRIPTION OF WORK:
Provide Construction Management Services relating to THE NEW POLICE DEPARTMENT
PROJECT. Specific tasks shall be as described in Attachment "A" - Scope of Services. The
term ofthis WORK ORDER shall be from July 1,2004 through February 28, 2006. The
Consultant fees shall be as described in Attachment "B".
All requirements of the original Agreement Documents shall apply to the above work except as
specifically modified by this Addendum. The contract time shall not extend unless expressly
provided for in the Addendum.
Page 1 of2
City of Gilroy, Contract Addendum
Work Order No. 63 - New Gilroy Police Department
March 12, 2004
ORIGINAL
HARRIS hereby agrees to make the above
change subject to the terms of this Addendum
for the NET INCREASE OF $ 1.891.500
Original Agreement Price
Total Addendum to Date
Total Amendments to Date
TOTAL TO DATE
CONSULTANT:
BY:~.~
G. Timmer
Date:J2~J2 ~~
-
This Addendum
REVISED AGREEMENT
(Master Contract)
$ 5.648.976
$ 1.020.233
$ 6.669.209
$ 1.891.500
$ 8.560.709
Date
Originals: (2) - City Clerk
Consultant
Copies: (2) - Purchasing
File
Page 2 of2
K:\ProgrmMt\Gilroy\WO 63 New PD eM 04\Addendum No.63 Police Dept.doc
March 12,2004
ORIGINAL
ATTACHMENT "A"
SCOPE OF SERVICES
NEW POLICE DEPARTMENT PROJECT
WORK ORDER NO. 63
33. CONSTRUCTION PHASE SERVICES
33.001 - Meetings - Organize, attend and record construction phase meetings.
33.010 - Consultant Management - Prepare reports that may be required during the construction
phase. Prepare monthly reports to Client.
33.030 - Submittal Review - Review submittals for compliance with contract documents
submittal requirements.
33.031 - Submittal Processing - Establish, implement and coordinate system of submittal
processmg.
33.032 - Clarification processing - Review and respond to contractor clarified requests. Track
all requests with architect.
33.033 - Change Order Preparation, Negotiation and Processing - Establish, implement and
coordinate systems for processing contract change orders. Prepare independent statement of
probable construction cost for contract change orders. Negotiate contract change orders with the
Contractor. Prepare contract change order document for execution by Contractor and Client.
33.034 - Schedule Review and Updating - Review Contractor's initial schedule submittal.
Review schedule monthly and provide written comments to the Contractor.
33.036 - Progress Payment Preparation and Processing - Prepare monthly progress payment
reports for submission to Client based on Contractor's construction progress.
33.039 - Construction Administration Services - Provide administrative and management
services during construction phase. Implement and monitor management procedures. Manage
project documentation, personnel, equipment, and facilities.
33.041 - Photographs and videos - Provide videotape and photographic documentation of
project site prior to and during construction.
33.042 - Maintain "Record" Drawings - Maintain one set contract documents with up-to-date
information regarding all addendum, substitutions, clarifications, and change orders.
R I Harris & Associates
Work Order No. 63 - New Police Department
Attachment "A" - Scope of Services
March 12,2004
ORIGINAL
33. CONSTRUCTION PHASE SERVICES (Continued)
33.134 - Field Observation Services - Schedule and coordinate field observation services. The
level of effort for continuous or periodic observations will be as required by the daily, weekly
and monthly scheduled work by the contractor. Provide daily observation reports on
construction activities as related to work performed in correlation to the contract plans and
specifications. Daily observation reports shall include work performed, onsite construction
equipment and observation of its use.
33.135 - Off-site Observation Services - Schedule and coordinate off-site observation services.
33.136 - Field Testing Services - Schedule and coordinate field-testing services.
33.137 - Laboratory Testing Services - Schedule and manage laboratory-testing services.
34. FINAL ACCEPTANCE/CLOSEOUT SERVICES
34.001 - Meetings - Organize, schedule, attend, and record final acceptance/close-out phase
meetings.
34.010 - Reports - Prepare reports that may be required during the final acceptance and project
closeout.
34.043 - Final Inspection and Punchlist - Provide final inspection and prepare a list ofproject
construction deficiencies for resolution by the Contractor.
34.044 - Construction Approval! Acceptance - Make recommendations to owner regarding final
proj ect approval and acceptance.
34.045 - Final Payment - Make recommendations to Client regarding Contractor's final progress
payment request. Prepare final progress payment report for submission to Client.
34.047 - Start-up Coordination - Assist Client during start-up and debugging of project.
34.049 - Project Closeout - Prepare all documentation needed for project closeout. Deliver all
project documentation to Client.
34.050 - Final Report - Provide Client with a project final report that includes the following:
A financial summary of the construction contracts, change orders, consultant services, project
management services, and direct purchase items. A summary of project change orders. A
construction summary and schedule review. A summary of final acceptance, A review and report
on the general constructor, subcontractors, and major equipment suppliers.
Page 2 00
K:\ProgrmMt\Gilroy\WO 63 New PD CM 04'\WO 63 PO CM Scope - Attach A.doc
III Harrls & Associates
Work Order No. 63 - New Police Department
Attachment "A" - Scope of Services
March 12,2004
ORIGINAL
35. FIELD OBSERVATION SERVICES
35.052 - Off-site Observation - Provide observation as required at any off-site location within
40 miles, to monitor compliance with contract documents.
35.053 - Field Testing - Test installed materials to monitor compliance with contract documents.
35.054 - Laboratory Testing - Utilizing laboratory methods, test construction materials to
monitor compliance with contract documents.
36. INSPECTOR OF RECORD (lOR)
36.001 - IOR Inspection and Reporting - Provide continuous inspection as required by the
essential facility act with all required reports and as indicated with in the Uniform Building Code
and Health and Safety Code.
Page 3 of3
K:\ProgrmMt\Gilroy\WO 63 New PO CM 04'\WO 63 PO CM Scope - Attach A.doc
III Harrls & Associates
....
=
f 6 ~
E-ist:o
Z "" ~ z
~ == as ""
~(J=~
== '5 ~ ""
u .....S::! 0 ~
<;<::=~~
E-i U =- 8 '0
E-i ~ ~ Q
< ~ ~
~
~
'C
""
=
==
"
;>
.~
~ 'iiJ
]8
-<
"
;>
.~
~ ~o
]~
<l:
~
~
e
...
1;l
~
....
~
Q
U
"Cl
~
Q
Q.
e
=-
5 ~
t$ ;:s
" 0
""'~
.E
5 ~
.- U
I ~
o ~
u::::;
5 ~
'il :iJ
i ~
o ~
u::::;
'iiJ
o
t$u
" ....
'0' ~
~ ~
::::;
t$ ~ ~
.g, ~ ::s
o ~ 0
~::::;~
'iiJ
o
U
~
f-<
~
~
~
f-<
'iiJ
o
U
....
o
t$
"
"'"
.E
'iiJ
o
U
~
g
~
5
~
~
g
t;I
"
>-
~
o
::::;
.,.
=
=
M
'<t ;g;
c:r ~
~ ~
o 0 0 0 000
'<t t"- \0 \0 0 '<t t"-
oo 00 M It') V) t'- 00
o~ 1./3' ~~ lr)" oct" 00 0
\0 \0 00 00 t"'-- t--- It')
fA '<t
fA
NOON 0 \0 \0 ~
..-I V) N M M t--- M
V) V) t--- I:'- \0 \0 00
","
000 0 0 0 0
o 0 0 0 0 0 0
\0 N \0 \0 0 N N
N" ~" ~" ~" ~" ~" ~"
fA fA
00 \0 00 00 0 \0 \0
~ ~ ~ ~ ~ ~ 8
o 0 0 0 0 0 0
fA '<t'<to\O'<t
\0 \0 \0 00 ~
~"~"~"~\O
fA
o 0 00 00 0 N 00
\O\ONMOO
----V)
o 0 V) V)
00 \0 ..-I ..-I
\0 t---" V) II')
N" M ",," v)"
01 01 01 01
fA
o 0 0 III
0\0"'=
M r--- V) =>
~ ('l")" iii" N
01 01 '<t
.....
fA
00 \0 0'. 0'. 0 \0 00
\Ot'-oooooor---r---
------5
o 0 V) V) 000
\0 ..-I 0 0 0 N 0
M r--- ~ ~ N V) \0
-.::t" 00" r---" r---" r""l" .,) v:J
N N N N N N II')
fA .....
fA
00 00 0\ 0\ 0 \0 0
~~OOOO~~~"
.....
o 0 000 0 0
o 0 0 0 0 0 0
(.t~,,~}~,,~,,~~
fA _
fA
00 00 00 \0 \0 \0 N
..-I ...... ..-I t"'--
'<t '<t
o 0
~ t;
<I.l 0
rJl
;g; ;g; ~
~ ~ +t
Z CI .g
<I.l
OR,GU\n~
g ~ ~ ~ ~ ~ g ~ ~ ~ g ~ ~
~ ~ ~ ~ ~ ~~"~,, ~~"~,, ~"~,,
r--- \0 00 00 00 00 00 0\ 00 r--- t"'-- \0 It')
fA ~
fA
..,.
=
=
M
N
...
.::
i::
"
~
\0 \0 \0 0\ 0 ~ \0 00 0\ 00 \0 0 00
..-I 00 0 0 M \0 0\ 0\ 0 00 V) N t"'--
\0 V) r--- r--- t'-- r--- \0 r--- r--- \0 \0 It') ......
00
o 0 0 0 0 0 0 0 0 0 0 0 0
o 0 0 0 0 0 0 0 0 0 0 0 0
o ~ 00 \0 \0 N 0 00 \0 \0 0 \0 ~
~:: ~~~~"~"~"~"~"~~V)
fA .....
fA
o N V 00 00 \0 0 ~ 00 00 0 00 \0
~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ 0
01"
o 0 0 0 0 0 0 0 0 0 0 0 0
o t"- ~ '<t '<t ~ 0 01 '<t '<t 0 01
\0 ~ ~ \0 \0 ~ 00 M \0 \0 00 q
~":::,;"s:"'~"'~~~"'~"'~"'~ 00
fA fA
~ ~ ~ ~ ~ !:
o '<t
~ ~
~ ~
\0 \0
..... .....
o 0 '<t
::8 ~"
.....
o 0 0 ~ ~ 0 0 ~ ~ 0 0 0 0
o N ~ - - M 0 ~ - ~ 0 ~ ~
~ ~ 00 ~ ~ ~ M ~ ~ ~ ~ ~ ~
- 0"' ~.,)~"'~"~"~"'~"' N"...... No\'
N N N N N N N N N N N N ~
fA 01
fA
01
"0
o 01 '<t ~ ~ ~ 0 t"- ~ ~ 0 ~ '<t
~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~
01"
o 000 ~ 0 0 ~ 0 0 0 0 0
~ ~ ~ ~ ~ ~ 8 0 ~ ~ ~ ~ ~
'" 01" \0" '<t" t"-" 00 vi 0" '<t" ..,f "," '<t" '<t"
N N N N N N N M N N N N 0
fA '"
fA
o N ~ ~ ~ ~ 0 ~ ~ ~ 0 ~ N
~ ~ 00 ~ 00 ~ 00 ~ ~ ~ ~ ~ ~
N
000 0 0 0 0 0 0 0 0 0 0
o 0 0 0 0 0 0 0 0 0 000
'<t '<t '<t '<t '<t '<t '<t '<t '<t '<t '<t '<t ~
N N" N" N"' N"' N" N N"' N"' N" N" NOO"
fA 01
fA
~ ~ ~ ~ ~
~ ~ ~
.,., .,.,
o 0
~ ~
~ ~ :g 6 ~ :g
~~~~~l
\0 \0 \0
..... ..... .....
~ ~
.....
.,., .,.,
o 0
fr t;
<I.l 0
'"
:g q ~
~ ~ :6
z CI ;:s
<I.l
....
=
f e ~
~ 1:: .
E-e=~
z_
~ ~ ~ ""
~....=~
== Q ~ 0"" '"
u ~.S:! ~
-<~Q~~
Eo-< u j:l.; ~ '0
Eo-< ~ ~ Q
-< ~ ~
~
'"
'C
""
=
==
'i.;l
o
U
~
E-<
~
g
::c:
~
E-<
<lJ
..
.~
-Ii! 'i.;l
]8
~
<lJ
..
.~
-Ii! ~
:~ 0
~::c:
~
~
~
.s
....
'"
~
'i.;l
o
U
....
o
t
<lJ
Q.,
Jj
....
'"
Q
U
"CI
~
'"
Q
:.
e
j:l.;
~ ~
" ::s
Q., 0
Jj::C:
'i.;l
o
U
p::
9
~
g
::c:
p::
9
c: 'i.;l
o 0
.- U
t !;
i i
U::E
c: ~
.9 g
t::C:
~ ~
o ii
U::E
'i.;l
o
'g~
.S ~
~ ~
::E
t !; ~
.~ ~;::S
E ii 0
""::E::C:
l;l
<lJ
><
~
o
::E
o 0
'<T '<T
o '"
N" .,)
v;; '<T
fA
o v;; v;;
'" 0\ -
'" '" 0\
o 0
o 0
~ ::"
;;;; -
00 '" 0
~ ~ ~
000
fA fA
000
'D 000
<= 00"'0
o \0 1II N
N N 0" ","
'" '" '<T
fA fA
00 '" 0
v;; on '"
- - '"
o 0 0
v;; '" 00
~~ ::~ ~
'" - '"
fA fA
00 v;; '<T
v;; t- '<T
- '"
000
000
'<T '<T 00
"," "," '<T"
fA fA
~ ~ ~
~ ~ ~
~ ~ "'t
...., ~ .g
CIl
~
o
.s
=
v
v
~
.r:J
"C
~
.s
'"
v
u
'E
v
rJ),
~
.9
'"
'"
~
8
A..
....
<S
1::
v
S
v
~
OIl
<r:
v
.d
.....
'0
"1'
V
-
~
.9
~
'" .
~~
Q..O\
~-
= .
o:=:
"C ....
B v
~-S
;o>~
ell 0
vZ
.r:J"C
1;> v
s~
~rJ),
~~
'" .......
vu
~o
....rJ),
~rJ),
~<r:
,gOd
n
8"C
"C d
v ell
"'>-0
~o
"'~~
.~~ ~ C>
....o~
6 U 0
i
'"
-< .....i
;,.;
E-<
U
:>-.
or-
."
~
<lJ
50
~
~
t::
~
<lJ
5
.~
~
<Il
-8
~
:1
]
c:
o
.~
....
.g
t
"
~
o
"
5
''3
~
o
"
5
."
<lJ
~
or-
~
~
o
''3
.g,
8
Q.,
8
..c::
~
::E
N
~
o
2-
Q.,
<lJ
~
<Il
:.s
.5
."
.s
::s
'0
.5
Ii
<lJ
or-
]
<lJ
<.>
ii
~
..Si
-;
"
e
'-2
~
o
o
Z
M
-0
o
'5
Q.,
-g
o
<lJ
<Il
o
'0
t
.g,
8
Q.,
."
<lJ
1;j
<.>
'6
.5
.s
$l
Q.,
::s
."
.s
::s
'0
.5
.~
"
~
5
.~
-;
<.>
<Il
~
~
]
]
t-
o
'"
fA
..Q
"
1;j
.~
8
Q.,
~
.~
'i.;l
o
<.>
5
''3
~
o
<.>
t
.g,
[
<lJ
~
.n
~
o
v
'"
o
'U
t)
v
'5'
....
Q..
....
<S
~
~
-
"C
~
v.
'"
~
Q..
OIl
d
~
"C
.....
.r:J
v
oS
OIl
d
'J::
.g
....
v
~
~
t)
v
'8'
A..
..0
o
OIl
.S
.g
'"
'"
ell
'0
.d
1::
~
-
'"
;::l
"i5..
~
"C
~
"C
d
v
~
u
o
"1'
'"
....
o
.....
u
~
o
U
o
.....
"C
v
v
u
8
A..
.9
t) v
v .~
'8' .....
Q.. 0
"C Z
S
;::l
'"
'"
<r:
d
o
'.;::l
ell
.g
o r...:
ORIGINAL
~
<=
<=
N
M
....
'5
..
01
~
~
o
o
N
~
~
.s
"C
~
Q..
'0
.....
1::
ell
.~
vi
~
v
~
.....
rJ),
]
ell
]
v
"C
v
~
:a
~ ~
.....
8 e
~ ]
.... u
o ell
U t::
g <r:
d d
.~ ''1'''"4
d "C
o v
.~ IS
c '"
v ~
'" 0
.g ~
] '0
ell V
OIl g.
.Ej ~
~ d
~ :s
.. .~
~
~ ~
.d
'"
'"
ell
'"
V
'.;:1
.g
E
.g
v
Q..
'"
......
o
'"
~
'J::
~
'"
;::l
-E
ell
N
ell
.d
'"
....
u
v
'0'
....
A..
-
ca ==
v .~
"C
.~ ]
.... u
Q.. ~
.....
o
....
o
.....
u
v
Q..
CIl
d
.......
-
-
.~
..0
o
~
Eo-<
00 0\
ORIGINAL
City of Gilroy
COMMUNITY DEVELOPMENT DEPARTMENT
Planning Division
Engineering Division
Building, Life & Environmental Safety
Housing & Community Development
(408) 846-0440; fax (408) 846-0429
(408) 846..Q450;fdX (408) 846-0429
(408) 846-0430; fax (408) 846-0429
(408) 846"()290; f-ax (408) 846"()429
June 3, 2004
CONTRACT ADDENDUM
(WORK ORDER NO. 67)
Agreement for: NEW POLICE FACILITY STAGING AREA AND
BROWN HOUSE DEMOLITION PROJECT
Consultant: HARRIS & ASSOCIATES. INC
Contract Agreement Date: November 10, 1998
This WORK ORDER shall become effective when The City Administrator, City Engineer,
Project Engineer, and Consultant have signed it. All documents forwarded to the Consultant for
signature shall be returned to the City of Gilroy properly filled out. Upon acceptance by the
City, the Consultant's duplicate original will be returned as authority to proceed with the work.
DESCRIPTION OF WORK:
Provide Construction Management Services relating to the New Police Facility Staging Area,
and Brown House Demolition Project. The Scope of Services shall be as detailed in Attachment
"A", consultant cost and work effort shall be as detailed in Attachment "B".
All requirements of the original Agreement Documents shall apply to the above work except as
specifically modified by this Addendum. The contract time shall not extend unless expressly
provided for in the Addendum.
Page 1 of2
City of Gilroy, Contract Addendum
Work Order No. 67 - PD Staging Area & Brown House Demolition
June 3, 2004
HARRIS hereby agrees to make the above
change subject to the terms of this Addendum
for the NET INCREASE OF $ 14.020.00
Original Agreement Price
Contract)
Total Addendum to Date
Total Amendments to Date
TOTAL TO DATE
By: _
This Addendum
Date:
b' 3' v1
REVISED AGREEMENT
ACCEPTED BY:--"",
tty E
~A'~<h
City Project Manager.
Originals: (2) - City Clerk
Consultant
Copies: (2) - Purchasing
File
Page 2 of2
K:\ProgrmMl\GilroyIWO 67 New PD Staging Area_Brown HouselAddendum No.67 Brown House Demo.doc
ORIGINAL
(Master
$ 8.406.994
$ 1.020.233
$ 9.427.227
$ 14.020
$ 9.441.247
/
,b -7-o~
Date
1R11/ or-(-
ate
ORIGINAL
June 3, 2004
ATTACHMENT" A"
SCOPE OF SERVICES
New Police Facility Sta2in2 Area & Brown House Demolition
WORK ORDER NO. 67
2.2 PRE-CONSTRUCTION PHASE SERVICES
2.2.01 Bidding Assistance - Assist in the development of bidder interest and distribution of the
construction documents.
2.2.05 Bid Review - Prepare detailed bid tabulation, review all bids for conformance to contract
requirements, and report on low bidders acceptability.
2.2.09 Pre -Construction Conference - HARRIS shall organize, attend and record the pre-
construction conference.
2.3 CONSTRUCTION PHASE SERVICES
2.3.01 On -Site Management & Construction Phase Communication Procedures - HARRIS shall
provide and maintain a management team to provide contract administration as an agent of the
CITY. HARRIS shall establish and implement coordination and communication procedures
among CITY, HARRIS, Design Professional and Contractor.
2.3.03 Reports - Prepare correspondence and reports that may be required during the
construction phase. Prepare monthly reports to CITY.
2.3.07 Progr ess Payment Preparation and Processing - HARRIS will prepare montWy progress
payment requests for submission to CITY based on Contractor's construction progress.
2.3.08 Change Order Preparation, Negotiation and Processing - Prepare independent statement
of probable construction cost for contract change orders. Negotiate contract change orders with
the contractor. Prepare contract change order document for execution by Contractor and CITY.
2.3.09 Minor Variations in the Work - HARRIS may authorize minor variations in the Work
from the requirements of the contract Documents that do not involve an adjustment in the
contract price or the contract time and which are consistent with the overall intent of the Contract
Documents. CITY shall provide to the Design Professional copies of such authorizations.
June 3, 2004
Attachment "A" - Work Order No. 67
New Police Facility Staging Area & Brown House Demolition
ORIGINAL
2.3.18 Oualit y Review - Except for minor variations, HARRIS is not authorized to charIge,
revoke, alter, enlarge, relax or release any requirements of the Contract Documents or to approve
or accept any portion of the work not performed in accordance with the Contract Documents.
Communication between HARRIS and Contractor with regard to Quality Review shall not in any
way be construed as binding CITY or HARRIS as releasing the Contractor from the fulfillment
of any of the terms of his Contract Documents. HARRIS will not be responsible for, nor does
HARRIS control the means, methods, techniques, sequences and procedures of construction for
the Project. It is understood that HARRIS' action in providing Quality Review, as stated herein,
is a service to the CITY arId by performing as provided herein, HARRIS is not acting in a
manner so as to assume responsibility or liability, in whole or in part, for all or any part of the
construction work for the Project. No action taken by HARRIS shall not relieve any or all of the
Contractors from their obligation to perform their work in strict conformity with the Contract
Documents and in strict conformity with all other applicable laws, rules and regulations. Not
withstanding the above, HARRIS is not relieved of any liability in the event it fails to properly
perform its duties, to manage construction activity for the project as permitted by the time
allotted by the CITY and the attached fee proposal, and to give notice to the CITY, of defects
and deficiencies in the work of the Contractors, all is set forth in this section.
2.3.19 Photographs and Videos - Provide videotape and photographic documentation ofproject
site prior to and during construction.
2.3.29 Field Inspection - Provide field inspection services to verify substantial compliance with
the contract documents.
2.5 FINAL ACCEPTANCE/CLOSEOUT SERVICES
2.5.04 Final Inspection and Punchlist - Provide final inspection and prepare list of deficiencies
for resolution by Contractor.
2.5.05 Construction Aporoval/Acceptan ce - Make recommendations to owner regarding final
project approval and acceptance.
2.5.11 Final Report - HARRIS will provide CITY with a final report for the project.
Page 2 of2
K:\ProgrmMtlGilroyIWO 67 New PD Staging Area_Brown HouselAttachment A WO 67 Scope.doc
ATTACHMENT "B"
ORIGINAL
.
COST PROPOSAL FOR ONSTRUCTION MANAGEMENT SERVICES
City of Gilroy
New Police Facility StaIDne: Area & Brown House Demolition
Work Order No. 67
Submitted by: Harris & Associates
3-Jun-04
'\ l!lIc f,:, dc'
.......L] ],--,- ( (1IL....2.\ 'IlL'"
11,[
II
l'iI'll'cle"! "ldllill~ ['I! Ie'lIl (I,
\1",--
"llllllllILI\-'I~ .I lit ,-' , [ 1.t1_,,-+ 11..>"-+
,"II
II
6 8 8
2 2 2
2 2 4
Ryan Fair
Construction $130.00 2 4 2
Manager 0 0 0
----
5 4 0
1 1
1 1
1 1
2 1
450
2
2 2
2 1
-..
31 $ 4,030.00
8
10
2
11
9 $ 1,170.00
2
4
3
2 2
2 2 4
Construction $110.00 2 2
Inspector 28 28 56
1 1 2
2 2
2 2 4
Assumptions:
1. Costs are based on current hourly rates. Rates may be adjusted only pursuant to Article 4 of the Agreement for Professional Services by and
between the CITY OF GILROY and HARRIS & ASSOCIATES dated November 10, 1998.
Total Labor Cost $ 14,020.00
2. Man-hour projections are based on construction contract duration and minimum observation effort as requested by CITY.
3. No Overtime allowance has been included in this fee proposal.
4. Escalation fee beyond the end of December 2004 is not included.
5. The project construction cost is approximately $155,532.00.
6. Assumed Project Duration: 1-112 months, 45 calendar days.
7. Project's Notice to Proceed to Contractor is anticipated by July 2004.
8. The City will provide all hazardous material removal testing and observation in accordance with all Federal and State laws.
9. One (1) Contract Change Order is to be negotiated and processed.
-
-
ORIGINAL
Harrls & Associates
-,0 I
"'0'
'- ~
July 20, 2004
Mr. Bill Headley
Facilities and Park Development Manager
City of Gilroy
7351 Rosanna Street
Gilroy, CA 95020
Subject: New Police Department Project Re-Bid - Work Order No. 49-A
Request for Budget Amendment No.3
Dear Mr. Headley:
This letter is to request a budget amendment for the subject project in the amount of$25.658.28.
The redesign effort is now complete. Harris & Associates, as requested, managed this effort
under the accelerated schedule, to meet City Council's request that the project be out to bid to
meet the 2004 construction season window.
As we indicated on our previous proposal dated August 29,2003, arid as we discussed directly
after the December 15,2003 City Council meeting, we have monitored our fee expenditures and
have made every effort to work under the accelerated schedule at the same fee; however, during
March 16 and 22,2004, a decision to add $10,000 for additional cost estimating that was
supported by the City, Harris, WLC Architects, and cost estimators Davis Landon Adamson
(DLA.)
In addition, during the May 14,2004 Executive Oversight Committee meeting, it was determined
that Harris' responsibilities would include:
./ Receipt of completed set of bid documents
./ Route bid documents for signature
./ Prepare documents for reproduction
./ Mail bid documents to plan rooms
Elite Reprographics estimated the cost for reproduction at $15,000. The Harris' staff time was to
be billed at time and material.
178 Second Street, Suite C Gilroy, California 95020-5100 408.842.5777 FAX 408.842.5758 gilroy@harris-assoc.com
City of Gilroy, Contract Amendment No.3
Work Order No 49 - Police Department Re-bid
July 20, 2004
Page 2 of2
ORIGINAL
With the sequence of events above and with our payment to Elite Reprographics, the following is
the allocation of funds for the requested amendment:
Harris staff $3,230.00
Printing and mailings $13,504.30
DLA cost estimate $10,000.00
Sub Total $26,734.30
Fee Remaining as of July 1, 2004 $1,076.02
Total Amendment $25,658.28
If this fee is acceptable, please authorize by signing below, and on the attached duplicate
original. Please return one fully executed wet signature document. Should you have any
questions, please call me at (408) 842-5777.
Sincerely,
HARRIS & ASSOCIA lES
[):~ k
William Little III '
Project Manager
C/ Mike Cooper, Harris & Associates
Larry W olt: WLC
Project file
Y.\PrnfT1"T'nl\A"t\r,.;lrnv QR_l()11')\Wn AO"1PT1rtnHmh~\ATTlP....u-t ~ to WI) d,Q Pf) "RP_h1r1 'J.lpnrllp" ,.lop
II I Harrls & Associates
.,
/"/ !'') f
""" ....
~'--' (
DUPLICATE ORIGINAL
"
October 14, 2005
-
-
Program Managers
Construction Managers
Civil Engineers
Harris & Associates
Mr. Rick Smelser, City Engineer
City of Gilroy
7351 Rosanna Street
Gilroy, CA 95020
Re: New Police Department Project - Work Order No. 63
Request for Budget Amendment No. 1- Construction Management
Dear Mr. Smelser:
This letter is to request a budget amendment for the subject project in the amount of $52,800. As
outlined on the attached document, this additional effort will be for an additional construction
manager to document necessary information and work through the items that are of potential
claim and resolve them at the lowest level with the General Contractor.
I John Spingarn, AIA I 44 days x 8 hrs. per day = 352 hrs. X $150 per hr. I $52,800
If this fee is acceptable, please authorize by signing below, and on the attached duplicate
original. Please return one fully executed wet signature document, as our authorization to
proceed. Should you have any questions, please call me at (408) 842-5777.
Sincerely,
2jJ1~~
William Little III, CCM, A VS
Project Manager
Date
Date
IO/p/f))-
I Date
C/ Project file
K:\ProgrmMt\Gilroy 98-l03l2\WO 63 New PO CM 04'\Amend 1 to WO 63 Additional CM.doc
178 Second Street, Suite C Gilroy, California 95020 408.842.5777 FAX 408.842.5758 www.harris-assoc.com
.J'
October 12, 2005
City of Gilroy Police Facility
Claims Monitoring and Mitigation
The information below will outline Harris & Associates recommendations to
increase the staffing for claims mitigation. As the Team is aware we have
encountered several issues with respect to the design team's responses to RFls.
The result may be impacting, in certain areas, what was originally bid by the
contractor. The impacts will need to be reviewed for entitlement, quantified with
respect to pofential costs and/or time and finally negotiated with the contactor.
There is never a perfect set of contract documents. However, there are
expectations that the General Contractor (GC) provide what is in those
documents. If there are revisions/changes to those documents they get paid at
fair and equitable price and any time associated with the revisions/changes be
evaluated.
The observed pattern from the GC is to continually submit claims and/or change
order requests for contract work. In addition there has been distinct
revisions/changes to the contract documents that may be significant and impact
the cost and time to complete the project. To the extent that the contractor has
attempted to create the appearance of delay from what should have been clear
to him through the documents, we will try to assess, as well.
The revisions/changes that were initiated by the RFI process not only have a
monetary impact due to additional labor, equipment and material but the lack of
clarity, coordination and/or timeliness of the response. The additional equipment
and labor are fairly straightforward in what the GC is due. The time impact due
to GC coordination issues and design team RFI response issues requires much
more detailed review and analysis.
With the information outlined above it is Harris's recommendation to add an
additional construction manager (CM) to the project team. The intent is to '.
continue to assemble all the documentation necessary to work through the items
that are of potential claim and resolve them at the lowest level with the GC.
THE ISSUES:
~ Contract work vs. Contractor Request for Change Order
~ Time Impact Analysis Related to:
o Contractor Created Delay
o RFI Timeliness Response Potential Delay
o RFI Revision/Change or Response Coordination Potential Delay
~ Labor, Equipment and Materials Required to Perform the Changed Work
. Harris & Associates..
-
-
Harrls & Associates
Program Managers
Construction Managers.
Civil Engineers
January 7, 2006
LTR No. 01S
Bill Headley
City of Gilroy
73S1 Rosanna St.
Gilroy, CA 9S020
Re: City of Gilroy
New Police Facility
Project No. 03-CDD-114
Construction Management Status Report
Dear Bill:
This report is provided to inform you of the status on the above project as of the end of December
200S. The following report is an overview of SJ. Amoroso Construction's actual progress from
December 1, 200S through December 31, 200S.
CONTRACT WORK COMPLETED:
Finish grading for new sidewalks and placement of baserock for site work is 6S% complete, and
the south end of Hanna has been paved. First floor ceiling electrical rough-in is 9S% complete,
and wire pulling is completed. Second floor wall rough-in for electrical is 40% complete.
Mechanical ductwork installation at the second floor is 9S% complete, and 80% complete at the
roof level. Mechanical piping and insulation at the second floor is 90% complete, and SO%
complete at the roof level. HV AC control work is 90% complete at the first floor, and equipment
installation at the boiler room is underway. Cast iron piping rough-in at the second floor is
substantially complete, and copper pipe rough-in is 91 % complete. Fire protection piping rough-
in at the second floor is 75% complete. Elevator equipment is on site and ready for installation to
begin. Roofing insulation is 65% complete, and spray-on fireproofing is substantially complete.
Formwork for equipment and locker bases is complete. Metal stud framing is 85% complete, and
installation of window frames/glazing is 7S% complete. Installation of exterior metal lath is 70%
complete, and exterior plaster is 40% complete. Light fixtures, firecycle materials, detention
equipment and special police equipment have been procured and are ready for installation.
File: 9810312.02.063 - 00015
Issue:
178 Second Street, Suite C Gilroy, California 95020 408.842.5777 FAX 408.842.5758 www.harris-assoc.com
City of Gilroy
January 7, 2006
Page Two
CONTRACT TIME:
As of the end of December approximately 90% of the contract time has elapsed (see attached
Contract Calendar Day.Status Report). We have advised the Contractor that a 25-calendar day
non-compensable time extension will be issued for delay to completion of the roof pads. This will .
revise the completion date to March 18, 2006. This time extension will likely be issued
unilaterally as the Contractor believes it is entitled to compensable time. Once the Contractor
revises the August update, we can resume the review process of subsequent updates. The October
update indicated extended completion to April 20, 2006, and we anticipate further overrun (as of
the end of December) that will push out the completion into May 2006. Delay factors contributing
to the completion overrun are addressed below.
V ALUE OF WORK COMPLETED:
The value of work completed as of the end of December was $18,043,818. This represents
approximately 78% of the total contract sum. The variance between time and cost expenditure
remains at 12%.
EXECUTED CHANGE ORDERS:
Change Order Nos. 1 through 36 has been issued (see Contract Change Order Log attached for
status). The total cost of these change orders is $672,717 and represents 3% of the contract
amount.
PENDING CHANGE ORDERS:
Submitted and estimated costs for change issues/items through December total $854,433 (see
attached Potential Cost Items/Issues for specific status). Adding this cost to the executed change
order cost from above, the total cost through December is approximately $1,527,150 or 6.8% of
the contract amount. We are evaluating the merit of these issues and changes, and negotiating
these costs with the Contractor. This change order value equates to a negative ($637,150) from
the budget amount of $890,000, and does not reflect potential change order cost for the remaining
$5 million of construction. This budget overrun has been discussed with the City, and is pending
action as appropriate.
File: 9810312.02.063 - 00015
Issue:
== I Harris & Associates
City of Gilroy .
January 7, 2006
Page Three
POTENTIAL CLAIMS/DELAYS:
1. Roof Pad/Curb Construction
2. Repair of Fractured Pilasters
3. Roof Deck Inserts/Hangers
4. Completion of Built-up Roofing
5. Testing of Mechanical Duct
6. Garage Fire Sprinkler Installation
7. Removal/Replacement of Damaged Materials
Roof Pad/Curb Construction:
As reported last month, a time extension will be recognized for the change/delay to construction
of the roof pads/curbs. In our evaluation the delay to concrete placement of the roof pads was 25
calendar days. The Contractor's position is that the delay equates to 29 calendar days, and that
SJA is entitled to compensable time. Since we disagree with the Contractor's position, a unilateral
time extension will be issued to the Contractor in order for us to move forward with schedule
updates. The matter of compensation may be revisited with the Contractor at a later date, or will
be left to resolution through claim procedures established by the contract.
Repair of Fractured Pilasters:
The Contractor has submitted a TIA (time impact analysis) for the repair of the fractured masonry
at beam pockets, requesting a compensable time extension of 27 calendar days. The Contractor
has asserted that the time to determine/provide for a corrective method, and time to effect repairs,
delayed completion of overhead MlEIP installations at the first floor. We are evaluating the
Contractor's delay assessment associated with repair of the pilasters, however it is our initial
position that completing mechanical installations where affected by pilaster repair was not
controlling critical path work.
Roof Deck Inserts/Hangers:
We are completing our review of this issue to determine responsibility of the costs submitted and
subsequent delay in placement of the roof deck. Through December, the Contractor has submitted
direct costs totaling approximately $286,921. As a result of the changed installations, placement
of the insulating concrete roof deck was delayed. We are finalizing our review of the contract
documents and shop drawing submittals to determine responsibility of the Contractor. However,
based on our initial review we have advised the Contractor that the costs submitted and any delay
to placement of the roof deck concrete is the responsibility of SJA and its subcontractors. The
outcome of this issue will likely require resolution through claim procedures of the contract.
File: 9810312.02.063 - 00015
Issue:
=; I Harris & Associates
\ .
City ()f Gilroy
January 7,2006
Page four
Completion of Built-up Roofing:
The roofing issues have been resolved and direction has been given to the Contractor to complete
the installation, however weather conditions have further delayed completion of the roof. As a
result of the incomplete roofing, and the Contractor's lack of protective measures, other building
components/materials below the roof have sustained damage from rain. The damaged materials
consist of fireproofing monocoat, batt insulation, and exterior gypboard sheathing. We have
advised the Contractor of these damaged materials and issued Non-Compliance Notices for
action. We have also marked the locations of these materials on a floor plan and will be issuing
this to the Contractor for removal and replacement of the damaged materials. The Contractor does
not believe that protecting the roof is his responsibility, because he would have had the roofing
complete if not for the design issues and installation problems encountered. We have repeatedly
advised the Contractor that he is responsible to protect the work, regardless of any non-execution
status. The removal and replacement costs will no doubt be submitted for payment to the
Contractor by change order, or for resolution under claim procedures of the contract. The issue of
damaged gypboard sheathing will be addressed below.
Testing of Mechanical Duct:
The issue of pressure testing of ductwork in accordance with specification 15990 continues to be
refuted by the Contractor. The costs to perform the testing will no doubt be submitted for
payment to the Contractor. Our position is that the testing specified is part of the contract work
and no additional costs will be recognized. The Contractor is having difficulty achieving system
leakage percentages at the jail area, and a meeting (conference call) has been scheduled for
Monday morning (1/9/06) to discuss the results and test criteria with the Contractor and
Designers. This may be another item that the Contractor will seek compensation for under the
claim procedures of the contract. Potential costs in dispute over the testing could be as much as
$50,000.
Garage Fire Sprinkler Installation:
The Contractor's fire protection subcontractor (Superior) has taken exception to the conclusions
reached by RJA in its report of 12/20/05 to the City. The outcome of this issue may hinge upon
interpretation of Code (NFPA-13), and will require further discussion between the City, Fire
Marshal, and Harris. A copy of the letter from Superior in response to the RSA report has been
provided to the City/Fire Marshal for review. This issue also has potential cost implications and
delay consequences.
Removal/Replacement of Damaged Materials:
Due to a lack of, or ineffective work protection measures by the Contractor, the exterior gypboard
sheathing has sustained damage. Rainwater has saturated various areas around the building
perimeter, which will require removal and replacement. At various locations, mold is evident, and
File: 9810312.02.063 - 00015
Issue:
=: I Harris & Associates
CitY of Gilroy
January 7, 2006
Page Five
exterior plasterwill also have to be removed with the sheathing. Upon visual evidence of mold
conditions, a specialist was brought in to inspect and examine the building. A report and
remediation procedures is expected on Monday 1/9/06. Once received, we will issue direction to
the Contractor and brief the City. The Contractor has the same opinion of responsibility for this
issue as he does for the roof issue. The costs for removal and replacement of gypboard sheathing
and plaster could amount to $100,000 and more depending upon extent of removal where mold is
evident and/or growing.
CM BUDGET:
CM costs to date are approximately $1,581,403, or 81 % of the budget amount. Through
December, management costs are within budget with a total balance of $362,897. Management
costs to projected completion are being finalized for submission to the City.
COMMENTARY:
We continue to work closely with the Architect to expedite responses to RFI submissions, and in
resolving field issues associated with design. As discussed at the last Executive Team meeting,
we expect that there will be unresolved issues with SJA that will require resolution through claim
procedures (mediation, etc.) of the contract. If negotiation of cost issues and delays reach an
impasse, we will direct the Contractor in accordance with the provisions of the contract. We are
working to finalize projected costs to anticipated completion of the project, and will be provided
to the City shortly.
We continue to assist the Contractor in matters of design, inspection, and quality assurance. The
Building Department authorizing Tony Perez (Project lOR) to inspect work on behalf of the City,
has had a positive affect on the Contractor and subcontractors, and is helping to maintain
continuity and sequencing of work.
Very truly yours,
HARRIS & ASSOCIATES
~~~
Scott Gilpatric, CCM
Associate
Cc: Lanny Brown, GPD
File: 9810312.02.063 - 00015
Issue:
= I Harris & Associates
CONTRACT-CALENDAR DAY STATUS REPORT
Gilroy Police Facility
City of Gilroy
R~pOrt No.:
Contractor:
. Date:
16
S. J. Amoroso
January 4, 2006
Date of Notice to Proceed:
Original Contract Calendar Days:
Original Contract Completion Date:
September 7, 2004
480
December 30, 2005
Time Extensions Issued:
CCO No. 10 No. Calendar Days 13
CCO No. 11 No. Calendar Days 6
CCO No. 13 No. Calendar Days 7
CCO No. 14 No. Calendar Days 11
CCO No. 16 No. Calendar Days 6
CCO No. 19 No. Calendar Days 3
CCO No. 23 No. Calendar Days 7
TOTAL TIME EXTENSIONS
53
Total Contract Calendar Days Allowed:
(Original Calendar Days + Time Extensions)
533
Revised Contract Completion Date:
Feb. 21. 2006
Calendar Days Elapsed Thru Report No. ~
450
Calendar Days Elapsed From 12/1 thru 12/31/05:
31
Total Calendar Days Elapsed to Date:
(
481
)
Calendar Days Remaining To Complete Project: 52
Recognized Holidays/Non-work Days:
11/25/04 02/21/05 11/11/05 01/02/06
12/24/04 05/30/05 11/24/05
01/03/05 07/04/05 11/25/05
01/17/05 09/05/05 12/26/05
= I Harris & Associates
Contract Calendar Day Status Report
January 4,2006
Page Two .
20 Day Weather Allowance/Days Recognized:
10/17/04 10/22/04 12/07/04
10/18/04 10/25/04 12/08/04
10/19/04 10/26/04 12/09/04
10/20/04 11 /1 0/04 12/10/04
10/21/04 11/11/04 12/28/04
12/30/04
12/31/04
01/02/05
01/07/05
01/08/05
The foregoing is a report of the status of contract calendar days through Dec. 31. 2005.
Any disagreements regarding this report shall be directed to the Construction Manager
within five (5) working days of the date received. This report does not reflect pending or
future requests for extensions of time as provided for in the contract documents.
sco~triC, CCM
Cc: File
= I Harris & Associates
NEW GILROY .POLlCEFACILlTY
CITY OF GILROY
12/31/05
- I......... ......qQN...RAPj"qH.A~~gQRP~RLQG.......
................. .
.............. .
............ .
......... .
..... . . .
................. .
. . . . . . . . . . . . . . . . . .
................ .
.................. .
. . . . . . . . . . ... . .
........... .
............. .
............. .
............. .
............. .
... ..........
....,......... .
............. .
.... ..........
......... .
. . . . . . . l .
. '. . . .'. . .
........ .
........ .
........ .
........ .
........ .
........ .
. . . . . . . . . . . . . . . . . . .!
..,..... -.........
.... -. -........ -'.
.."....... '.'........
........ .........
~i~~~\~~~~: :~ji~:~\:: :\~\: [:::::~] [j: ~: .
CCO SJA H&A RFQ RFI CCO
NO. DESCRIPTION' PROPOSAL ESTIMATE STATUS No. No. AMOUNT
1 Extend Substitution Request Period $0.00 $0.00 Executed $0.00
2 Door Veneer Substitution ($6,502.00) ($11,000.00) Executed 1 ($8,751.00)
3 Added ExcvNault Lid/BOC Changes $14,490.00 $9,590.00 Executed 3,5,6 45 $9,991.00
4 Add Beams/Pit Grates/Thresholds $7,873.00 $6,454.00 Executed 8R,16,27 133,147 $6,843.00
5 Add Floor Drains and Piping $21,340.00 $18,051.00 Executed 128,120 $18,432.00
6 Add Fir Drains/Pipe/Revise Faucets $17,925.00 $15,263.00 Executed 15 183,157 $15,263.00
7 Add FD's/Range/Steel Changes $24,154.00 $16,405.00 Executed 4,9,24,29 1,213 $16,646.00
8 Hanna Street Design Revisions $35,442.00 $15,000.00 Executed 2 107 $30,269.00
9 Add Block Course/Splice Box at P107 $18,159.00 $13,894.00 Executed 11,18,34 284,126 $13,660.00
10 13 Calendar Day Time Extension $26,080.00 $15,844.00 Executed $15,836.00
11 Revise Jail FixUDeepen Ftg Const. $17,159.00 $13,189.00 Executed 23,31 105,195 $13,444.00
12 Revise Jail Core Area Fndtn/Slab $25,910.00 $20,633.00 Executed 13 $20,633.00
13 Jail Ceil Light Rev/Explosion Motors $25,871.00 $16,840.00 Executed 12,31,43 55,140 $17,765.00
14 Lower VaulULight & Fire Alarm Revs $18,523.00 $13,972.00 Executed 21,26 232,32.1 $13,972.00
15 Sleeve Conc/BCM Upgrade/Redetail $18,439.00 $17,106.00 Executed 28.38,44 363 $17,106.00
16 J-Ftg & Steel Revs/Cable Increase $20,147.00 $13,905.00 Executed 7,33,37 63,301 $13,905.00
17 Dowl Epoxy @ Jail Core/Skylight Glas $24,847.00 $17,028.00 Executed 13,47 173,443 $16,899.00
18 Add Card Readers/Elevr Hoist Beams $25,225.00 $19,361.00 Executed 42,57 257,474 $19,361.00
19 Add LCP/Drain Relo/Door Changes $27,364.00 $25,193.00 Executed 40,46 357,464 $24,347.00
20 Foundation Changes at Elevr S107 $40,412.00 $24,874.00 Executed 17 161,162R $24,874.00
21 S103/S101 & Generator Ftg Changes $31,687.00 $22,162.00 Executed 17,36 161,162R $22,162.00
22 Pad Repairs/Remob CosUGate Adds $47,060.00 $17,213.00 Executed 230,447 $17,213.00
23 7 CD Time Extension/Deck Shoring $32,615.00 $32,615.00 Executed 521R $32,615.00
24 PAC Closets/Create Storage at CMU $41,602.00 $24,352.00 Executed 30,43,60 26,353 $24,352.00
25 Pneumatic Tube/Clips in lieu of Track $32,065.00 $22,014.00 Executed 62 484.5 $22,014.00
26 Grind Mill Scale/Revise Lobby Framin $30,819.00 $25,071.00 Executed 253,498 $25,071.00
27 CLSM Fndtn Backfill/Steel Revisions $19,240.00 $17,843.00 Executed 271,347 $17,843.00
28 Route Conduits from Rm 1019 to 114E $47,058.00 $25,211.00 City to sign 45 385 $25,211.00
29 Steel Changes/Sandblast Slab Joints $16,594.00 $15,280.00 City to sign 63 348,490 $15,280.00
30 Fire Treated Ply/Revise Steel at Gen $25,788.00 $24,044.00 Executed 70,75,80 550,529 $24,044.00
CCO' .... SJA H&A RFQ RFI CCO
NO. DESCRIPTION PROPOSAL ESTIMATE STATUS No. No. AMOUNT
31 Revise Steel Dwgs/Relo Air Compo $26,205.00 $24,369.00 Executed 64,73,81 358,474 $24,369.00
32 Operational Changes by PO $29,998.00 $24,129.00 Executed 65 $24,129.00
33 Excess Excv/Reviseq Lighting at Gar $27,010:00 $24,489.00 Executed 25 $24,489.00
34 Grind Conc Cap/Casework Revisions $58,715:00 $2~, 196.00 Executed 59 $24,458:00
35 Remove' AC/Meter By-Pass/Doors $25,240.00 $24,024.00 Executed. 79 253,413 $24,024.00
36 Soffit Attachment/Modify SDMH $71,805.00 $24,948.00 Executed 63 484,491 $24,948.00
. .
$966,359.00 $652,562.00 $672,717.00
TOTAL CHANGE ORDER COST:
PERCENT CHANGE ORDERS:
$672,717.00
3.0% *
* Percentage based on original contract value.
Contingency @ 4%:
Change Order Cost:
Balance:
$890,000.00
$672,717.00
$217,283.00
(Change Order No. 12 executed unilaterally)
NEW GIL~OYPOLlCE FACILITY
CITY OF.GILROY
12/31/05
. l/p()T~N"'~A(..PQ$tl"l"~M$n.$$Q~$'.
..,..... .
......... .
........ .
.. ..........
.. .....
......... .
. . . . . . . , . . . . . . . . . .
........ .
......... .
. . . . ~ . . . .
...................:.:........:..........:...:..:...........
::; ::;:;:::;:;:;; ;:;=:: :~:~:~ ~~:::: ::~: ::: l~:: :::::: ::;:;:::::: :'." .
................... ..........
. . . . . . . . . . . . . . . . .. .,... - . . .
.............. .
....... ....... ","
H I.
. . ........,... ,", ,"................
. . . . . . . . . . . . . . . . . .. ..".......
........................ .
............. .
ITEM SJA H&A RFQ RFI CCO
TYPE DESCRIPTION PROPOSAL ESTIMATE STATUS No. No. AMOUNT
A FWS Claim CosUJail Core Area $20,960.00 $8,603.00 Pending 13B
A Explosn Proof Sewage Motors/Elect $5,000.00 SJA to submit 12B 55
B Hanna Streetscape Redesign $58,206.00 $58,206.00 In Review 74 107
A Cost for Multiple Colors at Lockers $1,907.00 $0.00 Denied
A Add Mechanical Platform $2,500.00 SJA to submit 327
A Grind Ext Block for Card Readers $1,000.00 SJA to submit
A Elec for Sewage Ejector Remote Pnl $4,684.00 $3,303.00 Approved 32 260.1 $3,303.00
A Add Power/Phone Line at Entry Telep. $6,000.00 SJA to submit 35 135.1
A Added Flashing at Wall Base $11,083.00 $11,083.00 T&M FD-48 349
A Mansaard Roof Braces not Shown $5,000.00 SJA to submit 319
FWS Claim/Extra Excv/OT Cost $7,628.00 $0.00 Denied
A Jail Core Fndtn - 8 CD Delay $31,672.00 $0.00 Denied 13
A Relo Verizon VaulUExtnd Conduits $10,000.00 T&M FD-11 398.1
A Delete Deep Tone Colors/Extra Coat $0.00 $0.00 In Review 50
A Changes to Railing/CMU at Balcony $4,000.00 SJA to submit 391.1
A Relo Help Buttons/IC Devices $2,500.00 SJA to submit 51
A Reroute Conduits From 1157 to 1148 $8,416.00 $10,000.00 Incomplete 52 446.2
A Excv/Extnd Antenna Conduits to Bldg $26,607.00 $21,150.00 Approved FD-8 $25,253.00
A Light Cove Detail/Delete Strip Lights $8,582.00 $380.00 Approved 55 415.1 $380.00
A Gypboard Soffits at Room 1109 $1,656.00 $0.00 Denied 417
A Column Condition at F & 7 Line $1,500.00 SJA to submit
A Route 2" Conduits inside P111 to "PA" $1,500.00 T&M
B Storage at CMU Areas-Elect & FireP $10,000.00 Incomplete 60
A Slab Depression at Line 9 Costs $4,000.00 SJA to submit 496
B Changes to Signage Submtl #152 $9,567.00 $7,946.00 SJA to advise
A AN Elec Provisions at Room 1075 $1,500.00 T&M FD-20 519
A L3x3 Angle for Stud Attachment $5,459.00 $2,402.00 SJA to advise FD-23 538
A Cost for Island Lockers at Rm P123 $7,715.00 $0.00 Denied 389
A Repair/Cover Conduits at Hanna $2,000.00 T&M FD-34
A Extend 6" 00 thru Stair wall to Grade $2,417.00 $1,660.00 T&M FD-39 483
A Lower Beams at 2/F and 2/G $1,000.00 T&M 517
A Add Card Reader at Elevr S101 $2,500.00 SJA to submit 66 515.1
A Add 10ga Clip/For Stud to C-channel $26,223.00 $5,812.00 Approved FD-24 537 $5,812.00
A Provide Roof Deck Closure Angle $20,398.00 $8,159.00 Approved 542 $8,159.00
A Soffit Connects - 9 CD Delay $35,631.00 $0.00 Closed 63 491,523 $0.00
A Deck Extension at 7.5 and J Line $5,000.00 SJA to submit 78 547.1
A Bridge (E) Cone at Main Stair Entry $27,947.00 $8,000.00 In Review FD-28
ITEM' SJA H&A RFQ RFI CCO
.TYPE DESCRIPTION PROPOSAL ESTIMATE STATUS No. No. AMOUNT
A Added Details/Mech Pads & Curbs $58,201.00 $20,000.00 In Review' FD-25 555
B Relo/Revise Elec-Doors-Wndws $0.00 $0.00 Approved . 68 . '$0.00
A .Ext Framing Arch Higher than. Steel $4,123.00 $1,000.00 . Approved FD-26 570 $1,122.00
A Lower Arch/Hide Steel - 2 CD Delay $7,918.00 $0.00 Closed '$0.00
A Add Clips/ExtAIiQ.nmnt -12 CD Del. . $47,508.00 $0.00 Closed $0.00
A 4" Water Meter Type Cost Difference $3,660.00 $0.00 Denied
A Repairs for Fractured Masonry $7,000.00 T&M FD-29 502
A Nailable Insul/Mansard Roof Valley $29,703.00 $18,000.00 T&M FD-40 552.1
A Add Framing Clips at J & 1 Lines $7,230.00 $1,143.00 Approved 522 $1,143.00
A Extend 5" OD at Line A & 10 $1,506.00 $939.00 T&M FD-39 590
A Revise Boiler Room Floor $18,445.00 $18,445.00 In Review 72 577
A Conduit Routing into Existing Bldgs $10,000.00 T&M
A Add Presets to close off Walker Duct $7,000.00 SJA to submit 86
A Roof Pad/Curb Const - 41 CD Delay $162,319.00 $114,811.00 In Review FD-25 555
A Cut Wall Header at P111 for Switchgr $3,500.00 T&M FD-35 608
A Extend Top of Parapet at Lines 2 & 11 $6,782.00 $5,496.00 Approved FD-36 605.1 $5,496.00
A Adhesive for Parapro 123 Flashing $29,957.00 $20,000.00 T&M FD-41 399.1
A Add Soffit End Cap Closures $4,000.00 SJA to submit 82 579
A Relo Door at East Tower/Duct Conflict $1,500.00 T&M FD-37 253.7
A Fire Treated Ply for Shtmetal Curbs $2,500.00 SJA to submit 83
A Walker Duct Transition at Deck Slab $3,000.00 T&M FD-42 612
A Enlarge Col Furring/Relo Piping $5,000.00 T&M FD-43 536.1
A Elec for Heat Trace/2nd Flr/Syst 3 $4,000.00 SJA to submit 84 589.1
A Extd Waterproof membrane to Sheath $1,212.00 $1,212.00 In Review 4.1
A Provide Wall to Parapet Saddles $1,713.00 $1,713.00 In Review 582
A Place Roof Deck w/side Lap Conn. $4,255.00 $4,255.00 In Review FD-27 557
A Main Stair Dry Well/Relo "NN" Fixt $9,681.00 $7,098.00 Approved 85 $7,098.00
B Add Pistol Locker/Jail Door Speakers $10,000.00 SJA to submit 86
A Add Sprinklers at N. & E. Roof Attic $15,789.00 $14,775.00 T&M 87 599.1
A Change 8 Type "I" Fixt to "F" $1,000.00 SJA to submit 88 626
A Add TS for Guiderail Supports $10,000.00 T&M FD-46 593.2
A Roof Deck Inserts/Hangers/Supports $234,614.00 $234,614.00 In Review FD-32 600
A Roofing Detail Issues/Changes $8,000.00 T&M FD-47 624
A Grab Bar Mod/Sink Chase Wall $1,500.00 SJA to submit 89 630
A Form Bulkhead for Walker Duct Pour $2,500.00 SJA to submit 90
A Roof Deck Inserts/Hangers/Supports $52,307.00 $52,307.00 In Review FD-32 600
A Cement Plaster Ceiling/South Entry $6,021.00 $0.00 Denied
A Revise Size ofVAV-2 & 3/Submt1192 $1,152.00 T&M FD-57
B Added Fire Sprinklers/Storage Area $3,862.00 T&M FD-58
A Providellnstl Flashg at Panel Joints $907.00 T&M FD-59 592.1
A Siplast Roofing IssueslWLC Changes $10,000.00 T&M FD-62 638
A Added Curf/Flashg at Pilaster $5,000.00 T&M FD-63 637R
A Revise Wall Finish above Drs J127/128 $3,000.00 SJA to submit 91 657
A Mansard Roof End Termination $3,000.00 SJA to submit 92 649
A Added CMU at Cells/Revise PSH-1 $3,000.00 T&M FD-64
A Roof AddsllnsullFlashg/Deck Pieces $10,000.00 SJA to submit 93
A Change Ceilings at J146 & J147 $5,000.00 SJA to submit 94
ITEM SJA H&A RFQ RFI. ceo
TYPE DESCRIPTION . PROPOSAL ESTIMATE ST A TUSH No. No. AMOUNT
A Replace Wet Soil at Hanna. $8,042.00 $0.00' Denied
A Revise Fountain Alcove per ADA $1,500.00 T&M FD-65 661
.
$1,027,744.00 $854,433.00 $57,766.00
CONTINGENCY AMOUNT:
TOTALS TO DATE:
(includes estimated & CCQ-1 thru 36)
$890,000.00 (4% of contract sum)
$1,527,150.00 (78% construction)
CONTINGENCY BALANCE:
PERCENT CHANGE ORDERS:
-$637,150.00
6.8% (percent of contract sum)
A = Design Change (conflict,omission)
B = Owner Requested Change
(Values in Italics are Best Guess)
ORIGINAL
{,o,\ ~ .""''''
A~' ".1.\ r;; 1/ ".
'_"~.. ....<J"i .
,>' .'rO"
.' . .' - .'
; ',-' . '...,
. .. II ~, ..L."
'. ",,';r"~\ '
~ .". . . u') "i! . _ 1~ .
. v.' ,*,
". ~",.., .' .
". ....~..'-.,<
.~" <, ......,. ...,~ .~ ..
City of Gilroy
COMMUNITY DEVELOPMENT DEPARTMENT
Planning Division
Engineering Division
Building, Life & Environmental Safety
Housing & Community Dcvclopmcnt
(408) 846-0440; fax (408) 846-0429
(408) 846-0450; fax (408) 846-0429
(408) 846..0430; fax (408) 846-0429
(408) 846-0290; fax (408) 846-0429
May 22, 2006
CONTRACT ADDENDUM
(WORK ORDER NO. 63)
Amendment No.2
Agreement for: NEW POLICE DEPARTMENT PROJECT
Consultant: HARRIS & ASSOCIATES. INC
Contract Agreement Date: November 10.1998
This WORK ORDER shall become effective when The City Administrator, City Engineer,
Project Engineer, and Consultant have signed it. All documents forwarded to the Consultant for
signature shall be returned to the City of Gilroy properly filled out. Upon acceptance by the
City, the Consultant's duplicate original will be returned as authority to proceed with the work.
DESCRIPTION OF WORK:
This budget amendment request is for the subject project in the amount of $759.320. As outlined
on Attached "A", this additional effort will be for continued management services from May
2006 through January 2007, for the subject project.
The original project completion date was in February 2006. We have been successful in
managing our original fee estimate to extend our effort through April 2006. The general
contractor (GC) is anticipating an October 2006 completion date according to the latest project
schedule update. Due to the project closeout activities and the historic work activity progress by
the GC we have extended our fee estimate through January 2007.
If this fee is acceptable, please authorize by signing below and on the attached duplicate original.
Please return one fully executed wet signature document, as our authorization to proceed. Should
you have any questions, please call me at (408) 842-5777.
Page 1 of2
City of Gilroy, Contract Addendum
Work Order No. 63, Amendment No.2 - New Gilroy Police Department
May 22, 2006
HARRIS hereby agrees to make the above
change subject to the terms of this Addendum
for the NET INCREASE OF $ 759.320
Original Agreement Price
Total Addendum to Date
Total Amendments to Date
TOTAL TO DATE
CONSULTANT:
By:
REVISED AGREEMENT
This Addendum
Date:
. chael K. Cooper, Vice
131/0' .
ACCEP
.6 C
lty nginee
~~7J
Date
Originals: (2) - City Clerk
Consultant
Copies: (2) - Purchasing
File
Page 2 of2
K:\ProgIInMtlGiIroy98-I0312\WO63 New PO eM 04'1Addendwn NO.63 Police Dept_Amend2.doc
(Master Contract)
$ 9.830.777
$ 1.073.033
$ 10.903.810
$ 759.320
$ 1 1.663.130
III
....
0::
~~
z~
........
-= ~ ~
~ III e u
>>.5]"0
E-<O"IlI~
z.::O::e~
~';q:s III < 0
::E....Ql"')..
=:O~\C~
U~=d:;
< .- 0 z ~
E-<U~..Cj
~ ~ ~ ~
..... Z" '"
0<
~~
o '"
~ E
0::
=:
-
'"
o
U
-.;
'0
f-;
'"
....
::s
o
::c:
-.;
'0
f-;
"
'E
'"
~ '"
'28
's
-0
-<
"
~
.~
:: ~
"2 5
s ::c:
-0
-<
....
~ ti
" 0
~U
.5
....
o ~
t) ::s
" 0
~::c:
.5
-
'"
o
U
~
Q
~
::s
o
::c:
~
Q
-
= '"
.g 8
u ....
.5 ~
'" '"
s a
u~
~
= ::s
.9 0
t)::C:
::s ....
~ ~
= '"
o =
U::E
-
'"
o
t)U
" ....
.~ ~
.... '"
P-o =
'"
~
....
'0 ~ ~
.~ ~ 5
~::E::C:
....
'"
"
>-
-..
..c
;:
o
~
o 0 0 0 0 0 0 0 0 0
~ ~ ~ ~ N g ~ ~ ~ ~
C"'.f ..q: IoCr. 00 N" 00" ('..I" rrl a::
~ ~ 00 ~ 00 00 ~ ~ ~ ~
V1'7~EA-~(;,q.~~~~\c
""
~
....,
0-,"
0-,
'"
""
N 0
N
,.... ,....
'" N
if) if)
'" ,....
O"d"M\O\OOO =
~~~~~~~.~
1.11" VI" ~
C.
'"
.s
o 0 0 0 0 0 0 0 0
o 0 0 0 0 0 0 0 0
N N 0 00 0 N 0 0 00
t""'j" ~ N" rr1 N" M" ('I" \0" "<!:f'''
"" ""
~~~~~V'7E17
\0 \0 0 "d" 0 \0 0 0 "d"
~ ~ \0 00 \0 ~ \0 00 \0
o 0 0 0 0
\0\0 0 "d" 0
t""""lM\ON\O
0\"a::~6r--:
N
~ (;"oft (;A EI7 EI7
00000
o 0 EI7 EI7 \0
:... :... ['"
"" "" -
""
\O\OO"d"OOO
[-,1:--\000\.00000
'.Q
=
=
M
o 0 0 0 0 0 0 0 0 0
00 00 0 N N 00 0 0 \0 "d"
N N 00 V) 1.11 NOON 0\ \0
1'-" r---" ..; 01:)" 00 r--: ..; \0" "d"" a::
N N N N N N N ~ EI7 0\
EI7 EI7 {;A {;A {;A {;A (;A
""
'" '" 0 -.j- -.j- '" 0
r-r---\Ooooot--\O
-------
o N 00
-.j- ...., 00
N"
-
o 0 0 0 0 0 0 0 0 0
~~~~...~~~~~":"
0-," 0-," r-" ['." 0:: r-" r--: ~
N N N M N N N N M \0
GAGA{A(A.(;A(;A.(,A(;AGAN
""
\0 \0 0 "d" 0 \0 0 0 "d" \0
t-- J:-. \0 00 \0 J:-. \0 \0 00 M
-- -"1,
o 0 0 0 0 0 0 0 0 0
o 0 0 0 0 0 0 0 0 0
~ 00 00 00 00 00 \0 00 00 \0
v;ddddd~dd~'"
00 ~ ~ ~ ~ ~ ~ ~ ~ ~
;g \0 \0
b 6 C?
w ::s "3
~ -. -.
'"
;g ;g 8 ~
~ U 6 B
o CJ ~ J:;
ZCl-.::s
C/J
~ '" '"
~~~
-< C/J 0
o
o ..
N Q
0" ~
o ..:!
"" t:
...
..
is
'"
.;:
..
'" '"
q ::
]
Q
Eo<
'"
0"
-
~" ~" ~"~~
-.j- "" '"
"" "" r-
""
....
'" r-
Oc g
~]
-; =: .:
.0 -; g
G.l oc M
c..... ...
rJi '" "
-0 = =
: "0 ;
CJ) ..9 .s
~: 3
... =
Eo< ...
!l
'"
=
:c
<
t-
..
-;
rJi
-
'"
Q
U
'"
.;:
..
..
==
]
Q
Eo<
....
<E
1::
<l)
E
<l)
<l)
....
bI)
<
<l)
..J::
......
......
o
"<t
<l)
u
'-2
<::
o
......
......
l::
'"
= .
~~
5.0\
>>..-
"2 0"
o ..-
-0 ....
<l) <l)
~s
:o'~
'" 0
<l) Z
.0-0
~2
E~
2gs
"'r-
~<::
~o
~o
.... r/)
>>r/)
'i:<::
50"(3
..J::
......r/)
l:: ......
~~
g ~
l::
0"0
-0 l::
<l) '"
2~
'i"'~ ~ g
....0....
e U 0
=
'"
'"
<
>-
E-<
o
<l)
..J::
......
l::
<l)
<l)
z
<l)
.0
-0
l::
'"
>>
.0
'"
<l)
u
.:;
....
<l)
r/)
c;
l::
o
'[ji
CIl
~
o
....
0..
~
E-<
o
>>
.0
-0
<l)
......
CIl
<l)
::l
c:r
<l)
....
'"
'"
t::
@
<l)
l::
o
.~
>
....
<l)
CIl
.0
o
E
::l
E
'c
's
-0
l::
'"
l::
o
.~
....
::l
"0
....
U
'"
....
......
l::
o
u
l::
.S
......
u
::l
....
......
CIl
l::
o
u
l::
o
-0
<l)
CIl
'"
.0
<l)
....
'"
CIl
l::
.S
......
u
<l)
'0'
....
c..
....
::l
o
..J::
I
l::
'"
;;S
N
c;
CIl
o
c..
o
....
c..
<l)
~
CIl
:a
......
.8
-0
<l)
-0
::l
U
.8
l::
<l)
<l)
.0
CIl
'"
..J::
<l)
U
l::
'"
~
..9
c;
<l)
E
'-2
<l)
>
o
o
Z
M
-ci
o
.;::
<l)
c..
......
=
o
<l)
'"
o
U
......
u
<l)
'0'
....
c..
-0
<l)
rtj
u
:0
.8
<l)
..J::
......
o
......
c..
::l
-0
<l)
-0
::l
U
.8
.~
<l)
~
l::
.S
......
'"
c;
u
CIl
~
.,;.
rJi
]
<l)
~
......
r/)
"0
l::
'"
c;
....
<l)
-0
<l)
....
c;
;S
.~
<l)
u
~
-0
....
o
u
u
'"
.8
l::
o
.~
>
....
<l)
CIl
.0
o
"0
l::
'"
bI)
.8
......
CIl
<l)
......
c;
>
o
E
<l)
....
c;
.;::
<l)
~
E
'"
::l
o
-0
....
'"
N
'"
..J::
c;
<l)
-0
.:;
o
....
c..
.~
o
U
<l)
..J::
E-<
v)
'.Q
=
=
M
M
M
,..,
..
~
)l
~
d
o
.~
....
......
:.0
....
'"
'i::
o
.~
.~
::=
>
Q)
0::
"!
o
Z
C
Q)
E
"0
c:
Q)
E
<(
m
C
Q)
E
.s::
o
Cll
~
....
o
......
()
'"
....
......
l::
o
U
c;
....
<l)
l::
<l)
o
<l)
..J::
......
bI)
l::
.;::
=
-0
'"
<l)
u
.:;
....
<l)
CIl
<l)
-0
::l
U
.8
E
o
<t::
"0
<l)
....
<l)
>
o
u
<l)
....
<l)
.0
CIl
......
CIl
o
u
<l)
CIl
<l)
..J::
......
~
..J::
......
-0
l::
<l)
E
E
o
u
<l)
~
Ui
o
()
o
c..
C")
CD
o
~
M
CD
o
~
N
~
C")
o
~
cO
0>
>-
g
g
~
E
Cl
o
a:
:>2
......
o
l::
CIl
<l)
o
-0
c;
CIl
o
c..
o
....
c..
<l)
~
CIl
:a
E-<
...0
*
*
--
-
Harris & Associates
Program Managers
Construction Managers
Civil Engineers
September 19,2006
LTR No. 023
Bill Headley
City of Gilroy
7351 Rosanna St.
Gilroy, CA 95020
Re: City of Gilroy
New Police Facility
Project No. 03-CDD-114
Construction Management Status Report
Dear Bill:
This report is provided to inform you of the status on the above project as of the end of August
2006. The following report is an overview of SJ. Amoroso Construction's actual progress from
August 1, 2006 through August 31, 2006.
CONTRACT WORK COMPLETED:
Exterior building stair pours are complete. Parking lot grading and vertical curbs are complete.
Street excavation/demolition at north Hanna is underway, and traffic circle construction has
resumed. Exterior CMU (block at deck gates) has been completed. Piping insulation at the second
floor has been completed, and HV AC control work at the roof level is substantially complete.
Second floor ceiling electrical rough-in, and wire pulling is substantially complete. Second floor
lighting installation is 75% complete. Installation of F AlP AlData provisions at the second floor is
80% complete. Plumbing trim at the first floor is substantially complete, and 90% complete at the
second floor. Fuel system for the emergency generator is substantially complete. Second floor
trim of fire protection systems is 80% complete. Preformed wall panels are 7S% installed, roof
flashings/parapet coping is complete, and sheet metal roofing is 80% complete. Installation of
wood doors and hardware is 8S% complete. Drywall hanging and taping has been completed, and
exterior plaster is substantially complete. Acoustic ceiling work is 50% complete, and interior
painting is 75% complete. Ceramic tile is SO% installed, carpet and resilient flooring 2S%
installed, and athletic flooring is 60% complete. Casework and countertop installation is SO%
complete, and toilet partitions are 7S% installed. The mechanical shelving system and pre-fab
freezer have been delivered and are being installed.
File: 9810312.02.063 - 00023
Issue:
178 Second Street, Suite C Gilroy, California 95020 408.842.5777 FAX 408.842.5758 www.harris-assoc.com
City of Gilroy
September 19, 2006
Page Two
CONTRACT TIME:
As of the end of August, the project is 191 calendar days beyond the recognized contract
completion date of February 21, 2006 (see attached Contract Calendar Day Status Report). As
previously reported, it is our position that the Contractor is due some amount of additional time,
but until all cost information is submitted by the Contractor associated with the delay issues, time
extension change orders to the contract cannot be issued. No delay cost information has been
submitted by the Contractor since our last report.
The August update of the Contractor's completion schedule forecast completion of the project by
November 13, 2006 (265 calendar days beyond 2/21/06). Of the 265 days of overrun, the
Contractor has quantified 85 days of delay (roof pad/curb construction and roof deck
inserts/hangers). The remaining 180 days of overrun has not been quantified and/or justified by
the Contractor to be considered compensable delay and/or excusable time. Once our review of the
Contractor's August update is completed, our review letter will advise the Contractor that the
non-quantified overrun may be subject to assessment of liquidated damages.
V ALUE OF WORK COMPLETED:
The value of work completed as of the end of August was $22,496,347. This represents
approximately 95% of the total contract sum.
EXECUTED CHANGE ORDERS:
Change Order Nos. 1 through 60 has been issued to the Contractor. The total cost of these change
orders is $1,240,998 and represents 5.5% of the contract amount (see attached Contract Change
Order Log).
PENDING CHANGE ORDERS:
Submitted and estimated costs for change issues/items through August total $829,491 (see
attached Potential Cost Items/Issues for specific status). Adding this cost to the issued change
order cost from above, the total potential change order cost through August is approximately
$2,070,489 or 9.3% of the contract amount. We are evaluating the merit of these costs and
changes, and negotiating with the Contractor. This total change order cost does not reflect any
potential change order cost for the remaining $1 million of construction.
File: 9810312.02.063 - 00023
Issue:
III Harris & Associates
City of Gilroy
September 19,2006
Page Three
POTENTIAL CLAIMS/DELA YS:
Attached is a new listing (Dispute Issues/Costs) of potential claim issues and costs currently
under dispute with the Contractor. We have removed these issues/costs from pending change
order cost, as it is our belief that the Contractor will pursue dispute resolution of the items
identified and/or submit a claim at completion.
. Roof Pad/Curb Construction
. Roof Deck Inserts/Hangers
. Removal/Replacement of Insulation and Fireproofing
. Removal/Replacement of Exterior SheathingIPlaster
. Delay Associated with Roofing Issues
Roof Pad/Curb Construction:
Resolution of this issue is pending SJA submission of subcontractor delay cost, and acceptance of
settlement language to be incorporated into the change order. (No change/rom last month)
Roof Deck Inserts/Hangers:
The Contractor has submitted costs (direct and indirect) totaling approximately $555,855
associated with this issue. As previously conveyed, it is our recommendation to pay the direct
costs of the subcontractors and reduced costs of SJA. The Contractor has revised its initial TIA
delay impact analysis of 36 calendar days to 56 calendar days. Regardless of the delay
quantification, it is our recommendation (as a bargaining position) that the City grant the
Contractor a non-compensable time extension and waive assessment of liquidated damages for
the delay period. Resolution of this issue is pending submission of subcontractor delay cost by
SJA. (No change/rom last month)
Removal/Replacement of Insulation and Fireproofing:
Repair/replacement of water damaged insulation and fireproofing has been substantially
completed. It is the Contractor's position that replacement of these materials is due to delay in
completion of the roofing not the fault or responsibility of SJA despite provisions of General
Conditions for protection of work and materials. We have denied reimbursement for removal and
replacement costs associated with the damaged materials, and the Contractor is recording and
submitting cost documentation in accordance with General Conditions 00700-7.3 .2.2.
Removal/Replacement of Exterior Sheathing:
Removal and replacement of water damaged and/or mold impacted sheathing has been
completed, and re-plastering is ongoing. Of the total direct cost of $795,838 submitted by SJA,
only $4,831 has been recognized as additional cost. It is our position that these costs are not the
Owner's responsibility, and all issue information has been provided to the City's legal council for
review. The Contractor will undoubtedly pursue recovery of all costs incurred associated with this
Issue.
File: 9810312.02.063 - 00023
Issue:
;; I Harris & Associates
City of Gilroy
September 19,2006
Page Four
Delay Associated with Roofing Issues:
On 7/11/06 the Contractor submitted a TIA for a 100-calendar day compensable time extension
asserting delay to completion of built-up roofing. We have responded to the Contractor denying
the request citing non-compliance with time submission requirements, and concurrency of time
quantification with SJA's CPE #217 (roof deck inserts/hangers). The Contractor may elect to
revise and resubmit this TIA. (No changefrom last month)
CM BUDGET:
CM costs billed through August total approximately $2,232,252. The balance to the current
budget is approximately $212,048.
COMMENTARY:
The prosecution and rate of progress being achieved by the Contractor is minimal, yet the
Contractor has made no effort to recover lost time or improve upon prosecution of the work. The
August schedule update indicates that the Contractor will require two and one half (2.5) more
months to complete approximately 5% of the remaining contract work. In our estimation, this
amount of time is overstated to complete the work remaining, and affirms that the Contractor
does not recognize any sense of urgency or need to complete the work as timely as possible.
Design changes/issues continue to occur resulting in increased costs to the project. We have
received finalized costs for the Hanna Street changes in excess of $400,000 and are negotiating
these costs with the Contractor. We are diligently reviewing the open change items/issues to
determine responsibility and provide timely response and direction to the Contractor. We
continue to assist the Contractor in matters of design, construction issues, and quality assurance.
Very truly yours,
HARRIS & ASSOCIATES
~~~
Scott Gilpatric, CCM
Associate
Cc: Lanny Brown, GPD
File: 9810312.02.063 - 00023
Issue:
I Harris & Associates
CONTRACT CALENDAR DAY STATUS REPORT
Gilroy Police Facility
City of Gilroy
Report No.:
Contractor:
Date:
24
S.1. Amoroso
September 1, 2006
Date of Notice to Proceed:
Original Contract Calendar Days:
Original Contract Completion Date:
September 7,2004
480
December 30, 2005
Time Extensions Issued:
CCO No. 10 No. Calendar Days 13
CCO No. 11 No. Calendar Days 6
CCO No. 13 No. Calendar Days 7
CCO No. 14 No. Calendar Days 11
CCO No. 16 No. Calendar Days 6
CCO No. 19 No. Calendar Days 3
CCO No. 23 No. Calendar Days 7
TOTAL TIME EXTENSIONS
53
Total Contract Calendar Days Allowed:
(Original Calendar Days + Time Extensions)
533
Revised Contract Completion Date:
Feb. 21. 2006
Calendar Days Elapsed Thru Report No. 23:
693
Calendar Days Elapsed From ~ thru 8/31/06:
31
Total Calendar Days Elapsed to Date:
(
724
)
Calendar Days Remaining To Complete Project: -191
Recognized Holidays/Non-work Days:
11/25/04 02/21/05 11/11/05 01/02/06
12/24/04 05/30/05 11/24/05
01/03/05 07/04/05 11/25/05
01/17/05 09/05/05 12/26/05
I Harris & Associates
Contract Calendar Day Status Report
September 1, 2006
Page Two
20 Day Weather Allowance/Days Recognized:
10/17/04 10/22/04 12/07/04
10/18/04 10/25/04 12/08/04
10/19/04 10/26/04 12/09/04
10/20/04 11/10/04 12/10/04
10/21/04 11/11/04 12/28/04
12/30/04
12/31/04
01/02/05
01/07/05
01/08/05
The foregoing is a report of the status of contract calendar days through Aug. 31. 2006.
Any disagreements regarding this report shall be directed to the Construction Manager
within five (5) working days of the date received. This report does not reflect pending or
future requests for extensions of time as provided for in the contract documents.
~~~
Scott Gilpatric, CCM
Cc: File
I Harris & Associates
NEW GILROY POLICE FACILITY
CITY OF GILROY
8/31/06
. .
. .
...,..... .
. . . . . . . . . .
. . . . . . . . .
...,.... .
........ '.1
........ .
........ .
........ .
........ .
........ .
........ .
........ .
........ .
........ .
........ .
I' '.' . . .... ..... . . . . . '. . . . ......... .
. ..:.:..C.ONTRAqT:.qH.AN~i$Q~P.~R:.ilQ@.:....:......:......;..;.
. .
.. .
CCO SJA H&A RFQ RFI CCO
NO. DESCRIPTION PROPOSAL ESTIMATE STATUS No. No. AMOUNT
1 Extend Substitution Request Period $0.00 $0.00 Executed $0.00
2 Door Veneer Substitution ($6,502.00) ($11,000.00) Executed 1 ($8,751.00)
3 Added ExcvNault Lid/BOC Changes $14,490.00 $9,590.00 Executed 3,5,6 45 $9,991.00
4 Add Beams/Pit Grates/Thresholds $7,873.00 $6,454.00 Executed 8R,16,27 133,147 $6,843.00
5 Add Floor Drains and Piping $21,340.00 $18,051.00 Executed 128,120 $18,432.00
6 Add Fir Drains/Pipe/Revise Faucets $17,925.00 $15,263.00 Executed 15 183,157 $15,263.00
7 Add FD's/Range/Steel Changes $24,154.00 $16,405.00 Executed 4,9,24,29 1,213 $16,646.00
8 Hanna Street Design Revisions $35,442.00 $15,000.00 Executed 2 107 $30,269.00
9 Add Block Course/Splice Box at P107 $18,159.00 $13,894.00 Executed 11,18,34 284,126 $13,660.00
10 13 Calendar Day Time Extension $26,080.00 $15,844.00 Executed $15,836.00
11 Revise Jail Fixt/Deepen Ftg Const. $17,159.00 $13,189.00 Executed 23,31 105,195 $13,444.00
12 Revise Jail Core Area Fndtn/Slab $25,910.00 $20,633.00 Executed 13 $20,633.00
13 Jail Ceil Light Rev/Explosion Motors $25,871.00 $16,840.00 Executed 12,31,43 55,140 $17,765.00
14 Lower Vault/Light & Fire Alarm Revs $18,523.00 $13,972.00 Executed 21,26 232,32.1 $13,972.00
15 Sleeve Conc/BCM Upgrade/Redetail $18,439.00 $17,106.00 Executed 28,38,44 363 $17,106.00
16 J-Ftg & Steel Revs/Cable Increase $20,147.00 $13,905.00 Executed 7,33,37 63,301 $13,905.00
17 Dowl Epoxy @ Jail Core/Skylight Glas $24,847.00 $17,028.00 Executed 13,47 173,443 $16,899.00
18 Add Card Readers/Elevr Hoist Beams $25,225.00 $19,361.00 Executed 42,57 257,474 $19,361.00
19 Add LCP/Drain Relo/Door Changes $27,364.00 $25,193.00 Executed 40,46 357,464 $24,347.00
20 Foundation Changes at Elevr S107 $40,412.00 $24,874.00 Executed 17 161,162R $24,874.00
21 S103/S101 & Generator Ftg Changes $31,687.00 $22,162.00 Executed 17,36 161,162R $22,162.00
22 Pad Repairs/Remob Cost/Gate Adds $47,060.00 $17,213.00 Executed 230,447 $17,213.00
23 7 CD Time Extension/Deck Shoring $32,615.00 $32,615.00 Executed 521R $32,615.00
24 PAC Closets/Create Storage at CMU $41,602.00 $24,352.00 Executed 30,43,60 26,353 $24,352.00
25 Pneumatic Tube/Clips in lieu of Track $32,065.00 $22,014.00 Executed 62 484.5 $22,014.00
26 Grind Mill Scale/Revise Lobby Framin~ $30,819.00 $25,071.00 Executed 253,498 $25,071.00
27 CLSM Fndtn Backfill/Steel Revisions $19,240.00 $17,843.00 Executed 271,347 $17,843.00
28 Route Conduits from Rm 1019 to 114S $47,058.00 $25,211.00 City to sign 45 385 $25,211.00
29 Steel Changes/Sandblast Slab Joints $16,594.00 $15,280.00 City to sign 63 348,490 $15,280.00
30 Fire Treated Ply/Revise Steel at Gen $25,788.00 $24,044.00 Executed 70,75,80 550,529 $24,044.00
31 Revise Steel Dwgs/Relo Air Compo $26,205.00 $24,369.00 Executed 64,73,81 358,474 $24,369.00
32 Operational Changes by PO $29,998.00 $24,129.00 Executed 65 $24,129.00
33 Excess Excv/Revised Lighting at Gar $27,010.00 $24,489.00 Executed 25 $24,489.00
34 Grind Cone Cap/Casework Revisions $58,715.00 $23,196.00 Executed 59 $24,458.00
35 Remove AC/Meter By-Pass/Doors $25,240.00 $24,024.00 Executed 79 253,413 $24,024.00
CCO SJA H&A RFQ RFI CCO
NO. DESCRIPTION PROPOSAL ESTIMATE STATUS No. No. AMOUNT
36 Soffit Attachment/Modify SDMH $71,805.00 $24,948.00 Executed 63 484,491 $24,948.00
37 Main Stair Ftg/Remove (E) SD & Cap $27,947.00 $24,721.00 Executed 67 $24,721.00
38 Jail Operation Changes/Crane Riggin~ $23,078.00 $23,078.00 Executed 84,86 6.1,536 $23,078.00
39 Extend (E) Conduits/Bkfl Elec Trench $26,608.00 $25,253.00 Executed FD-8 $25,253.00
40 Add Dry Wells/Ejector Alarm Elect $24,660.00 $12,385.00 Executed 32,68,85 582,260 $12,385.00
41 Alignment Clips/Parapet Extension $47,499.00 $19,863.00 Executed 60,63,77 537,612 $19,863.00
42 29 CD Time Extn - Roof Pads/Curbs $114,811.00 $57,405.00 Voided FD-25 555 $0.00
43 Roof Pad/Curb Change - T&M $50,360.00 $50,072.00 Executed FD-25 555 $50,072.00
44 Secur Ceil Add/Hanna S1. Extras $25,434.00 $23,867.00 Executed 91,92,94 593.2 $23,867.00
45 Elevr TS/Fire Prot at Roof Attics $26,513.00 $25,499.00 Executed 87 593.2 $25,499.00
46 Misc Roofing Items/Signage Changes $28,005.00 $25,297.00 Executed 93 $25,297.00
47 Relo FSD/Duct/OD Drain, Col Dowels $15,306.00 $13,630.00 Executed 71,83,89 617,590 $13,630.00
48 Secur Grilles/Lobby Soffit/Heat Trace $23,372.00 $22,418.00 Executed 78,84,95 413.4 $22,418.00
49 Pilaster Repair/Metal Deck Stops $32,770.00 $24,778.00 Executed 93 502,687 $24,778.00
50 Boiler Rm Fir Rev/Revise Alcoves $29,781.00 $28,861.00 Executed 72,99,104 577,661 $28,861.00
51 Entry Telephone/Conduits to Evidence . $46,873.00 $38,668.00 Executed 35,97 135.1 $38,668.00
52 Boiler Rm Form/Reinf - Labor/Mtrls $19,715.00 $19,715.00 Executed 72 577 $19,715.00
53 Boiler Rm EleclWalk-treads/SS Top $17,738.00 $15,018.00 Executed 98,107 756 $15,018.00
54 Add/Relo CR's/Jail Planks/Presets $24,176.00 $22,939.00 Executed 66,93 661,701 $22,939.00
55 Light Fixt Changes/Relo TV Equip Rm $28,707.00 $24,286.00 Executed 1s8,110,11! 253,626 $24,286.00
56 Elevator Power Revisions $44,897.00 $31,307.00 Executed 102 706 $31,307.00
57 Lower Ceilings/Angle Closure/Conduit $28,433.00 $24,241.00 City to sign 52,97,118 4.1,446.2 $24,241.00
58 Add Shutoff Valves/Revise SD Piping $24,340.00 $20,330.00 City to sign 90,98,127 294.2 $20,330.00
59 IT Added Racks and ISO Platforms $24,580.00 $21,591.00 City to sign $21,591.00
60 Cable Upgrade/Add Conduit/IT Extras $33,796.00 $30,464.00 City to sign 109R $30,464.00
$1,755,758.00 $1,278,248.00 $1,240,998.00
TOTAL CHANGE ORDER COST:
PERCENT CHANGE ORDERS:
$1,240,998.00
5.5% *
* Percentage based on original contract value.
Contingency @4%:
Change Order Cost:
Balance:
$890,000.00
$1,240,998.00
($350,998.00)
(Change Order No. 12 executed unilaterally)
NEW GILROY POLICE FACILITY
CITY OF GILROY
8/31/06
. . . . . . . . . . . . . . . . . . . . . .. ... . . . . . . . . .
::. :..::.::.....PENb.tNt;.CostttSMs/ISSUES.:..H....H.:::....?......:...
. ......
. . . . . . .
ITEM
TYPE
DESCRIPTION
A Explosn Proof Sewage Motors/Elect
B Hanna Streetscape Redesign
A Cost for Multiple Colors at Lockers
A Add Mechanical Platform
A Grind Ext Block for Card Readers
A Added Flashing at Wall Base
A Relo Verizon VaulUExtnd Conduits
A Changes to Railing/CMU at Balcony
A Relo Help Buttons/lC Devices
A Revise Light Fixtures at Hallway 1104
A Gypboard Soffits at Room 1109
A Route 2" Conduits inside P111 to "PA"
A AN Provisions at Rm 1024/1075
A L3x3 Angle for Stud Attachment
A Cost for Island Lockers at Rm P123
A Diag Bracing/Boiler Rm Roof Frame
A 4" Water Meter Type Cost Ditt.
A Nailable Insul/Mansard Roof Valley
A Add ConduiUCol Chase at City Hall
A Revised Tie-in to Existing PD
A Duct Pressure Testing Cost
A Cut Wall Header at P111/Switchgear
A Adhesive for Parapro 123 Flashing
A New Door/Frame/Lock at J128
A Relo SAD at Room J 123
A Roofing Detail Issues/Changes
SJA
PROPOSAL
$0.00
$1,907.00
$12,318.00
$9,162.00
$1,638.00
$1,656.00
$5,459.00
$7,715.00
$1,447.00
$3,660.00
$29,703.00
$36,302.00
$29,957.00
$7,055.00
. ..... ..
.. .
H&A
ESTIMATE
STATUS
.'''';::;:' ....
. ....
. ....
. ....
. ..
. .
....,........ .
....,........ .
.......... ....
RFQ RFI
No. No.
$5,000.00 SJA to submit 12B 55
$0.00 See RFQ-117R 74 107
$0.00 Denied
$2,500.00 SJA to submit
$1,000.00 SJA to submit
$10,997.00 I (Approved ./
$7,159.00 In Review
$4,000.00 SJA to submit
$2,500.00 SJA to submit
$1 ,638.00.....j....---1I;pprOVed ")
$0.00 LJCIIICU
$1,500.00 T&M
$5,000.00 T&M
$2,402.00 SJA to advise
$0.00 Denied
$725.00 SJA to advise
WVlf NOr ~
O,J ~(iO LoG /
.:...:..::....\..
V
CCO
AMOUNT
$0.00
327
FD-48 349 ($10,997.00D
FD-11 398.1
391.1
51 ( ~,638.00D
52 446.3
417 ~
FD-20 519
FD-23 538
389
319
$0.00 Denied
$18,000.00 T&M FD-40 552.1
$25,000.00 SJA to submit 122
$0.00 SJA to submit 123
$0.00 Denied 614.1
$3,500.00 T&M FD-35 608
$20,000.00 T&M FD-41 399.1
$6,564.00 SJA to advise FD-105
$2,000.00
T&M
$8,000.00
T&M
FD-104 786
FD-47 624
ITEM SJA H&A RFQ RFI CCO
TYPE DESCRIPTION PROPOSAL ESTIMATE STATUS No. No. AMOUNT
A Form Bulkhead for Walker Duct Pour $1,529.00 $876.00 rApprovecL-, 90 512.2 (' $876.00 )
---
A Cement Plaster Ceiling/South Entry $6,021.00 $0.00 Denied
A Siplast Roofing Issues/WLC Changes $15,790.00 $9,405.00 SJA to advise FD-62 638
A Added Curf/Flashg at Pilaster $5,000.00 T&M FD-63 637R
A Delete Epoxy Coating/Add Padding -$1,000.00 SJA to submit 120 -
A Waterproofing at Slab/4 to 6 Line $37,436.00 $37,100.00 l.r-APproved~ FD-101 781 ('$37,100.00
A Revise Return Air Duct at J 111 $1,000.00 8$'[0 aavise FD-93 111.1
A Replace Wet Soil at Hanna $8,042.00 $0.00 Denied
A Revise Wall Type at P100 $625.00 $0.00 T&M FD-67 619
A Smoke Door Wall at Elevr S101 $1,500.00 T&M FD-91 593.3
A Closure Angle at High Roof Eaves $3,046.00 $2,795.00 SJA to advise 118 766
A Reframe Opening for Drying Cabinets $1,500.00 T&M FD-86 738.1
A Change South Wall Type at J123 $1,776.00 $0.00 Denied
A Added Cost for Photo Imaging $8,227.00 $0.00 Denied
B Add Elec Outlets at Rm 1155 $2,500.00 T&M FD-70
A Add Mech Piping btwn FCU-2/CU-2 $8,644.00 $4,000.00 T&M FD-80 685
A Revise IC's at Rm 1115 Window $2,000.00 SJA to submit 101 698
A Lath/SOFP at CMU Blockout $2,000.00 T&M FD-82 743
A Elevr Cab Channel SupportlS 103 $2,000.00 T&M FD-74
A SE/SW Penthouse Roof Corners $4,000.00 T&M FD-75
A Alternate Mount of Smoke Detectors $9,289.00 $5,000.00 T&M FD-79 707
A Condensate Drain Pipe Revisions $12,152.00 $7,520.00 SJA to advise FD-84 720
A Mansard Support at N. High Roof $2,500.00 T&M FD-81 649
B BOC Items for Correction/Change $16,064.00 $7,528.00 SJA to advise FD-92
A Add Elec for Switch/Rm 1108 to EF-1 $2,218.00 $2,095.00 SJA to advise 111 730
A Insul Cap at Return Air Openings $3,500.00 T&M FD-100 604
A Add Saddle Flashing at CMUlPlast $2,937.00 $2,600.00 ~proved') FD-89 754.1 C. $2,600.00 )
A Revise Roof Eave/Add Fascia Pnl $55,237.00 $38,899.00 SJA to advise FD-87 749.1
A Delete (4) Floor Closers/1116A Doors -$1,000.00 SJA to submit 115 762
A Mount Rooftop Disconn to Units $5,000.00 SJA to submit 116 755
B Hanna Street Changes Rev-2 $389,412.00 $389,412.00 In Review FD-118
B Traffic Plan for North Hanna Street $1,030.00 $1,030.00 ~roved ") FD-102 G1030.00
A SD Size Changes/Future Lightg at Lot $9,075.00 $6,631.00 Pending FD-90R .......- --
761,773
B Landscapellrrig Adds - Hanna St. $37,900.00 $37,900.00 In Review 121
ITEM SJA H&A RFQ RFI CCO
TYPE DESCRIPTION PROPOSAL ESTIMATE STATUS No. No. AMOUNT
A Add Grille at RA Opening/Rm 1145 $1,000.00 T&M FD-107 788.1
B Add Entry Phone/Revise Cameras $5,000.00 T&M FD-108
A Revise Light Fixt at Rm 1114A/B $188.00 $188.00- / Approved ') 125 824 /$188.00 )
A Fill Void at Slab Edge/S. Penthouse $1,500.00 SJATo submit 126 823
A Delete Shower Accessories -$1,000.00 SJA to submit 128 820
A Flashing under Mansard/S. Penthouse $17,226.00 $10,000.00 T&M FD-116 819
B Additional Survey at Hanna St. $5,000.00 T&M FD-123
A Alternate for Perimeter Angle Bracing $1,412.00 $1,327.00 / ~pproved ./ FD-11 0 834 ~)27.00 )
A Add Dowels/Reinf for Gate Piers $3,000.00 Ies.M FD-111 837
A Relocate T -stat & Strobe at 1116 $2,000.00 T&M FD-122 831.1 R
A Fur Out at Mixing Valve CabineUJail $1,500.00 T&M FD-113 851
B BOC Changes/Jail Cell Safety $5,000.00 SJA to submit 131
A Putty Pads at Rated Wall Assemblies $4,303.00 $0.00 Denied
A Access Doors/Added Lights at Lobby $5,000.00 T&M FD-115 831.1
A Add Wall/Floor Stops at 11 Jail Doors $1,500.00 T&M FD-117 850
A Metal Flashing at Balcony Edge $2,000.00 T&M FD-119 802
B BOC Changes/Jail Cell Safety $10,000.00 T&M FD-120
A Excv/Compact Subgrade at Prkg Lot $50,000.00 In Review FD-114
A Provide Power to LEK at Jail Sliders $10,000.00 In Review FD-121 861
A Add Drain at E-Line/West Patio $2,500.00 T&M FD-124 798.3
A Add Door Closers/One Stop at Jail $2,000.00 T&M FD-125 850.1
A Change Door Swing at Rm 1048 $1,200.00 T&M FD-126 833
. -.
/
$797,558.00 $829,491.00 ( $55,756.00
'-.--.......
CONTINGENCY AMOUNT:
TOTALS TO DATE:
(includes estimated & CCO-1 thru 60)
CONTINGENCY BALANCE:
PERCENT CHANGE ORDERS:
A = Design Change (conflict,omission)
8 = Owner Requested Change
(Values in Italics are Best Guess)
$890,000.00 (4% of contract sum)
$2,070,489.00 (96% construction)
-$1,180,489.00
9.3% (percent of contract sum)
..
NEW GILROY POLICE FACILITY
CITY OF GILROY
8/31/06
1::'..):>.I$.:eQYf$:i$$pg$tqQ$t$:j::::~ .::.'
......... .
........ ..........
... ....
',' ',", .......
. ... . ..
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . '1
~~~1~!\~~1~j~jjj~~~!~~~!1!1!11f~1!1!f1111!~!1i1~jljj~!111!11~!)f!i1!11~!1111j!1!~jlj1
ITEM SJA H&A RFQ RFI ISSUE
TYPE DESCRIPTION COST V ALUA TION STATUS No. No. NOTES
A FWS Claim Cost/Jail Core Area $20,960.00 $8,603.00 Unresolved 13B
A FWS Claim/Extra Excv/OT Cost $7,628.00 $0.00 Denied
A Jail Core Fndtn - 8 CD Delay $31,672.00 $0.00 Denied 13
A Roof Pads/Curbs - 29CD Delay $114,811.00 $67,303.00 Unresolved FD-25 555 (1 )
A Patch Monocoat at Trapeze Supports $8,462.00 $0.00 Unresolved FD-32 600 (1 )
A Roof Deck Inserts/Hangers/Supports $246,065.00 $152,404.00 Unresolved FD-32 600 (1 )
A Roof Deck Inserts/Hangers/Supports $52,307.00 $31,365.00 Unresolved FD-32 600 (1 )
A Roof Deck Inserts/Hangers/Supports $27,317.00 $17,224.00 Unresolved FD-32 600 (1 )
A Roof Deck Inserts - 56CD Delay $221,704.00 $0.00 Unresolved FD-32 600 (1 )
A R&R Gyp w/Mold at North Exterior $169,182.00 $4,831.00 Denied
A R&R Plaster/Gyp at E,W, & S. Elev $570,853.00 $0.00 Denied
A Built-Up Roofing - 100CD Delay $395,900.00 $0.00 Denied FD-62
$1,866,861.00 $281,730.00
(1) Resolution pending submission of subcontractor delay cost by SJA.
I J;J ] 't'i.!
._)
-
-
Harris & Associates
Program Managers
Construction Managers
Civil Engineers
June 13,2007
Bill Headley
City of Gilroy
7351 Rosanna St.
Gilroy, CA 95020
Re: City of Gih'oy
New Police Facility
Pl'oject No. 03-CDD-114
Disposition of Disputed Cost Items
Dear Bill:
This letter is to provide you with the outcome of our meeting with S.J. Amoroso held yesterday at
1 :00. Ed Kozlowski, Bill Little, Paul Mason, Mike Cleveland and myself met to discuss the four
(4) remaining cost issues. After detailed discussion of each item, the following summary of cost
was arrived at:
Submitted Cost
Settlement
1. Removal of Wet Soil at Hanna St.
2. Sprinkler Revisions/Ceiling Changes
3. Duct Pressure Testing Costs
4. Atrium Smoke Control
$ 8,042.00
$ 2,601.00
$36,302.00
$46,074.00
$ 3,500.00
$ 1,500.00
$27,000.00
$35,000.00
Totals:
$93,019.00
$67,000.00
Items 2, 3, and 4 all have to do with WLC design. The $67,000 number is the amount that the
Contractor will accept as final closeout cost for the project. Should the City seek legal recourse
against the Architect, the costs associated with these items should be inclusive of that action.
Please let me know how you would like to proceed with these cost issues.
Very truly yours,
HARRIS & ASSOCIATES
,
~~~
Scott Gilpatric, CCM
Associate / Project Manager
120 Mason Circle Concord, California 94520-1214 925.827.4900 FAX 925.827.4982 www.harris-assoc.com
NEW GILROY POLICE FACILITY
CITY OF GILROY
6/13/07
I... ...........QI$PQT~P~~AINt~P$[$...................
... .. .,.............
...... ".'.. '.'....'.....
.,...... ... .........
. .......... ..'......
............. .....
. . . . . . . . . . . . . '.' . .
. . . . . . . . . . . . .. .
............. .
.,...,...... .
. . . . . . . . . . .
. . . . . . . . . .
................ .......................................U/...U..........1
ITEM SJA COST MEETING REVIEW RFQ RFI CCO
TYPE DESCRIPTION SUBMISSION REVIEWS STATUS FD No. No. AMOUNT
A Curb Cales for AC-1 thru 3 Anchors $585.00 $0.00 Resolved FD-25 555 $0.00
A Duct Pressure Testing Cost $36,302.00 $27,000.00 Pending 614.1
A Cement Plaster Ceil/South Entry $6,021.00 $0.00 Resolved $0.00
Replace Wet Soil at Hanna $8,042.00 $3,500.00 Pending
A Change South Wall Type at J123 $1,776.00 $0.00 Resolved $0.00
A Add Custom Color Sheets/Mansard $5,698.00 $0.00 Resolved $0.00
A Revise Paint Scheme at Lobby $4,196.00 $0.00 Resolved 137 $0.00
A Ceiling Changes/WLC Site Visits $2,601.00 $1,500.00 Pending
A Tile Wainscot Additional Cost $7,840.00 $0.00 Resolved 808 $0.00
A Wall Tile Extra at Rm 1135 $3,495.00 $0.00 Resolved $0.00
Irrig/Planting Escalation Costs $12,535.00 $0.00 Resolved $0.00
A Add Floor Tile at Rm 1126 $1,900.00 $0.00 Resolved $0.00
A Add Tile at Rms 1127/1128/1130 $6,046.00 $0.00 Resolved $0.00
A Atrium Smoke Control Syst - Mech $46,074.00 $35,000.00 Pending FD-73R 854.2
$143,111.00 $67,000.00
CONTINGENCY AMOUNT:
CCO TOTAL THRU #95:
$890,000.00
$4,194,865.00
PERCENT CHANGE ORDERS:
18.7%
A = Design Change (conflict,omission)