S.J. Amoroso Construction - Change Order No. 02City of Gilroy
COMMUNITY DEVELOPMENT DEPARTMENT
Planning Division (408) 846 -0440; fax (408) 846 -0429
Engineering Division (408) 846 -0450; fax (408) 846 -0429
Building, Life & Environmental Safety (408) 846 -0430; fax (408) 846 -0429
Housing & Community Development (408) 846 -0290; fax (408) 846 -0429
CHANGE ORDER NO. 00002
To contract for: New Police Facility Project
Contractor: S.J. Amoroso Construction Co.. Inc.
Contract Date: 8/16/04
This order shall become effective when the City Administrator, City Engineer, Project Engineer, and Contractor have signed it. All
copies forwarded to Contractor for signature shall be returned to the City of Gilroy properly filled out. Upon acceptance by the City,
the Contractor's copy will be returned to him as his authority to proceed with the work.
DESCRIPTION OF WORK:
Add to the contract a credit amount of $8,751 for negotiated cost differential associated with acceptance of Contractor's
Substitution Request #36. This change was initiated under RFQ No. 1, and responded to under Contractor's CPE #4. A
time extension is not warranted nor required, and all other provisions of Section 08210 Wood Doors remain unchanged.
This change order constitutes full and complete compensation for all labor, equipment, materials, overhead, profit, any
and all indirect costs, associated with acceptance of the above substitution.
I (We) hereby agree to make the above Original Contract Price $ 22,377,000.00
changes subject to the terms of this
Change Order for NET DECREASE OF Previous Change Orders $ 0.00
By:
S.J. Amoroso
Date:
RECOMMENDED BY:
TOTAL TO DATE
This Change Order
Revised Contract Price
4,4 Originals to:
CITY:
CONTR:
$ 22,377,000.00
($8,751.00)
$ 22,368,249.00
(2) Originals
(1) Original