S.J. Amoroso Construction - Change Order No. 04307
City of Gilroy
Engineering Division
7351 Rosanna St., Gilroy, CA 95020
Phone (408) 846 -0450; Fax (408) 846 -0429
CHANGE ORDER NO. 004
To contract for : New Gilroy Police Facility Project No. 03 -CDD -114
Contractor: S.J. Amoroso Construction Contract Date: 8/16/2004
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Item 4A: Contractor to provide /install sump pit and grate at elevators S101 /S107 in accordance with RFQ No. 27 and
CityPolicy II- 18 ........................................................................ ............................... .....................$1,245.00.
(CPE #28)
Item 413: Contractor to provide for concrete curb /pad for stud wall support at E.5 between Lines 1 and 2 not shown, in
accordance with response to RFI- 190 ............................................... ............................... .......................$441.00.
(CPE #43)
Item 4C: Contractor to provide for steel angle and slab edge at Line 4 between Lines H and J not shown, in accordance
withresponse to RFI- 191 ....................................... ............................... .......................$499.00.
(CPE #50)
Item 41): Contractor to provide /install added beams and reinforcing for deck support between Lines F/G and 4/5 not
shown, in accordance with response to RFI- 133 ............... ... ............................... .....................$2,121.00.
(CPE #45R)
Item 4E: Contractor to provide /install added door thresholds not shown, in accordance with Submittal #73 comments
andRFQ- 16 .............................................................. ............................... .....................$1,058.00.
(CPE #30)
Item 417: Contractor to provide /install tube steel antenna support not shown, in accordance with response to RFI -147
and225 ....................................................................... ............................... .......................$624.00.
(CPE #38)
Item 4G: Contractor to provide for wall changes /additions at detention areas, in accordance with response to RFI-
105/106 and RFQ- 8R ......................................................................... ............................... .......................$855.00.
(CPE #17)
All requirements of the original Contract Documents shall apply to the above work except as specifically
modified by this Change Order. The contract time shall not extend unless expressly provided for in this
Change Order.
Cost Percent
I (We) agree to make the above change Original Contract Price $22,377,000.00
subject to the terms of this Change Order Previous Change Orders to Date $1,240.00 0.0%
for the NET INCREASE of $6,843.00 Total to Date $22,378,240.00
This Change Order $6,843.00
Total Change Orders to Date $8,083.00 0.0%
,R wised Contract Price $22,385,083.00
Contractor *Requires emergency authorization if greater than 25 %.
Date: j A
RECOMMENDED BY:
ACCEPTED B`.