S.J. Amoroso Construction - Change Order No. 05w
To contract for
Contractor:
City of Gilroy
Engineering Division
7351 Rosanna St., Gilroy, CA 95020
Phone (408) 846 -0450; Fax (408) 846 -0429
CHANGE ORDER NO. 005
New Gilroy Police Facility Project No. 03 -CDD -114
S.J. Amoroso Construction Contract Date: 8/16/2004
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Item 5A: Contractor to provide /install floor drains and piping at Room 1127 not shown on plumbing drawings, in
accordance with response to RFI 128. 1 ................................. ............................... .....................$9,055.00.
(CPE #46R)
Item 513: Contractor to provide /install trap primer and piping for FD -1 at Room P122 not shown on plumbing drawings,
in accordance with response to RFI- 180 ........................................ ............................... .....................$1,994.00.
(CPE #37R)
Item 5C: Contractor to provide /install floor drain and piping at Room 1113 not shown on plumbing drawings, in
accordance with response to RFI -120. Revise waste pipe size for FS -1 in Room 1153 in accordance with response to
RFI -13 9 ............................................................................................................... ............................... $ 9,429.00.
(CPE #36R)
Item 5D: Credit for deletion of FD -3 and piping at Room J111 in accordance with response to RFI -150 and Field Memo
No. 63 ............... .............................................................................. ............................... ($2, 046.00).
(CPE #44R2)
All requirements of the original Contract Documents shall apply to the above work except as specifically
modified by this Change Order. The contract time shall not extend unless expressly provided for in this
Change Order.
I (We) agree to make the above change
subject to the terms of this Change Order
for the NET INCREASE of $18,432.00
Contractor
Original Contract Price
Previous Change Orders to Date
Total to Date
This Change Order
Total Change Orders to Date
Revised Contract Price
Cost Percent
$22,377,000.00
$8,083.00 0.0%
$22,385,083.00
$18,432.00
$26,515.00 0.1%
$22,403,515.00
*Requires emergency authorization if greater than 25 %.
BYG %% �1 �Date: �l D
,36!
RECOMMENDED BY:
ACCEPTED BY:
�zl�C�