Loading...
S.J. Amoroso Construction - Change Order No. 07� r R To contract for Contractor: City of Gilroy Engineering Division 7351 Rosanna St., Gilroy, CA 95020 Phone (408) 846 -0450; Fax (408) 846 -0429 CHANGE ORDER NO. 007 New Gilroy Police Facility Project No. 03 -CDD -114 S.J. Amoroso Construction Contract Date: 8/16/2004 This order shall become effective when it has been signed by the City Administrator, City Engineer, Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned to him as his authority to proceed with the work. Description of Work Item 7A: Contractor to provide /install electric range at Room 1155 not specified, and miscellaneous kitchen component items as identified in response to RFI -166 and RFQ No. 24 .......................... .....................$2,311.00. (CPE #41) Item 713: Contractor to provide for changes to jail door sizes /types, revise masonry walls, to accommodate installation headboxes and door operation in accordance with RFQ- 4 ........... ............................... ...................($1,269.00). (CPE #09) Item 7C: Contractor to provide /install added tube steel columns/bolts not shown, in accordance with response to RFI -46 and 91 under RFQ- 9 ............................................ ............................... .....................$1,758.00. (CPE #18.2R) Item 71): Contractor to provide /install added steel columns/beams not shown, in accordance with response to RFI -57 andRFQ- 9 ............................ ............................... ... ............................... .....................$3,266.00. (CPE #18.1R) Item 7E: Contractor to provide for deletion of steel in accordance with response to RFI Nos. 10, 13, 20.1, 144 and Field MemoNo. 44 ................................................... ............................... .....................($948.00). (CPE #35) Item 7F: Contractor to provide for size change to drain line and horizontal piping in accordance with response to RFI- 116 and RFQ- 29 .................................................... ............................... .....................$3,082.00. (CPE #27) Item 7G: Contractor to provide /install floor drain and piping at Room 1084 not shown on plumbing drawings, in accordance with response to RFI -213 and Field Memo No. 62 .. ............................... .....................$8,446.00. (CPE #5682) All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this Change Order. The contract time shall not extend unless expressly provided for in this Change Order. 0 0 I (We) agree to make the above change subject to the terms of this Change Order for the NET INCREASE of $16,646.00 Contractor Original Contract Price Previous Change Orders to Date Total to Date This Change Order Total Change Orders to Date Revised Contract Price Cost Percent $22,377,000.00 $41,778.00 0.2% $22,418,778.00 $16,646.00 $58,424.00 0.3% $22,435,424.00 *Requires emergency authorization if greater than 25 %. By:z16 Date: // 2. 4v—s RECOMMENDED BY: — t,`— •'►'— ZTr'3'� Construction Maudker ate ACCEPTED BY: �i/0 Iii WHE _ \' ate • . �.