S.J. Amoroso Construction - Change Order No. 12City of Gilroy
Engineering Division
7351 Rosanna St., Gilroy, CA 95020
Phone (408) 846 -0450; Fax (408) 846 -0429
CHANGE ORDER NO. 012
To contract for: New Gilroy Police Facility Project No. 03 -CDD -114
Contractor: S.J. Amoroso Construction Contract Date: 8/16/2004
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Contractor to provide for all foundation changes to the jail core area in accordance with RFQ No. 13 and direction
therein issued 11/ 5/ 04 .................................................................... ............................... ....................$20,633.00.
(CPE #19CR2)
All requirements of the original Contract Documents shall apply to the above work except as specifically
modified by this Change Order. The contract time shall not extend unless expressly provided
for in this
Change Order.
Cost
Percent
I (We) agree to make the above change
Original Contract Price
$22,377,000.00
subject to the terms of this Change Order
Previous Change Orders to Date
$131,633.00
0.6%
for the NET INCREASE of $20,633.00
Total to Date
$22,508,633.00
This Change Order
$20,633.00
Total Change Orders to Date
$152,266.00
0.7%
Revised Contract Price
$22,529,266.00
S.J. Amoroso Construction Co., Inc.
Contractor
*Requires emergency authorization if greater than 25 %.
By:
Date:
ACCEPTED : -��`�1
Ci a Date
n r Date 1 5
(/Project Engineer Date
Page 1 of 1
City of Gilroy
Engineering Division
7351 Rosanna St., Gilroy, CA 95020
Phone (408) 846 -0450; Fax (408) 846 -0429
CHANGE ORDER NO. 012
To contract for : New Gilroy Police Facility Project No. 03 -CDD -114
Contractor: S.J. Amoroso Construction Contract Date: 8/16/2004
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Contractor to provide for all foundation changes to the jail core area in accordance with RFQ No. 13 and direction
thereinissued 11/ 5/ 04 .................................................................... ............................... ....................$20,633.00.
(CPE #19CR2)
All requirements of the original Contract Documents shall apply to the above work except as specifically
modified by this Change Order. The contract time shall not extend unless expressly provided for in this
Change Order.
Cost Percent
I (We) agree to make the above change Original Contract Price $22,377,000.00
subject to the terms of this Change Order Previous Change Orders to Date $131,633.00 0.6%
for the NET INCREASE of $20,633.00 Total to Date $22,508,633.00
This Change Order $20,633.00 0 * �_
Total Change Orders to Date $152,266.00 0.7%
Revised Contract Price $22,529,266.00
S.J. Amoroso Construction Co., Inc.
Contractor *Requires emergency authorization if greater than 25 %.
By: Date:
RECOMMENDED BY:
ACCEPTED BY:
41 (tog
Manager Date
trat Date
�11141,�J-r
TlatP
Page 1 of 1
City of Gilroy
New Police Facility Project
TRANSMITTAL NO. 00365
= I Harris & Associates
TO: Bill Headley DATE: 4/l/2005
City of Gilroy
7351 Rosanna St. REF: CCO No. 12
Gilroy, CA 95020
Phone: (408) 846 -0450 Fax: (408)846 -0460
WE ARE SENDING:
SUBMITTED FOR:
❑ hop Drawings
ADDroval
❑ Approved mi d
❑ Resubmit 0 Copies for Approval
❑ Letter
❑ Your Use/information
❑ Approved as Noted
❑ Submit 0 Copies for Distribution
❑ Prints
❑ As Requested
❑ Returned After Loan
❑ Returned 0 Copies Corr. Print
lir Change Order
❑ Review and Comment
❑ Returned for Corrections
❑ Plans
SENT VIA:
❑ Samples
❑ Hand Delivered
❑ Specifications
❑ U.S. Mail
❑ Other:
I ❑ Overnight: ❑ Faxed:
ITEM NO. COPIES DATE ITEM NUMBER DESCRIPTION STATUS
1 3 CCO CCO No. 12
Remarks:
Bill, please have the attached change order executed and return copy to Harris office ASAP. The Contractor has declined to accept
this change order due to disagreement in cost and time, therefore we will issue it unilaterally. We need to pay for the work
performed, so that SJA cannot accuse us of non - payment of change order work. Thanks
Signed: Dated: �7`--
Scott ric
Copies To: Transmittal and Attachments:
HA Project Files:
File: 9810312.02.063.Transmittal #00365
Issue File:
Page I of I
178 -C Second Street Gilroy, CA 95020 Phone (408) 842 -5777 FAX (408) 842 -5758 sgilpatric @harris- assoc.com
f a_tr_01