CHANGE ORDER NO. 014
To contract for: New Gilroy Police Facility Project No. 03 -CDD -114
Contractor: S.J. Amoroso Construction Contract Date: 8/16/2004
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Item 14A: Credit to contract for use of slip track systems in lieu of continuous metal plate at wall to deck connections in
accordance with response to RFI -187.2 and RFQ- 39 ........................... ............................... ..................($11,381.00).
(CPE #89)
Item 1413: Excavate to expose conduits adjacent to existing PGE vault not shown, and lower vault to conform with new
finish grades at north parking area. Work performed under T &M and RFQ- 28 ................ .....................$9,872.00.
(CPE #47)
Item 14C: Contractor to provide for light fixture relocations and added access door to Tower Attic in accordance with
WLCMemo #1 and RFQ- 38 ............................................................. ............................... .....................$4,428.00.
(CPE #87)
Item 141): Contractor to provide for lighting electrical at lobby elevator 5107 not shown in accordance with response to
RFI -383 and RFQ- 44 ............................................................................. ............................... .....................$2,310.00.
(CPE # 102)
Item 14E: Contractor to provide for changes /additions to Fire Alarm submittal #118 in accordance with review
commentsby Fire Marshal ................................................................... ............................... .....................$7,361.00.
(CPE #124)
Item 14F: Contractor to provide for compressed air line size changes in accordance with response and direction provided
inRFI- 363 ............................................................................................ ............................... .....................$1,382.00.
(CPE #98)
Item 14G: The contract completion date is hereby revised from January 25, 2006 to February 5, 2006 due to inclement
weather conditions as follows: 3/1/05 -half day impact, 3/2/05 -half day impact, 3/3/05 -half day impact, 3/4/05 -full day,
3/19/05 -full day, 3/21/05 -full day, 3/22/05 -full day, 3/23/05 -half day impact, 3/28/05 -half day impact, 3/29/05 -full day.
Total time of 7.5 work days, or 11 calendar days.
All requirements of the original Contract Documents shall apply to the above work except as specifically
modified by this Change Order.
Page 1 of 2
I (We) agree to make the above change
subject to the terms of this Change Order
for the NET INCREASE of $13,972.00
S.J. Amoroso Construction Co., Inc.
Contractor
By: Date
RECOMMENDS
ACCEPTED BY;
Original Contract Price
Previous Change Orders to Date
Total to Date
This Change Order
Total Change Orders to Date
Revised Contract Price
Cost Percent
$22,377,000.00
$170,031.00 0.8%
$22,547,031.00
$13,972.00
$184,003.00 0.8%
$22,561,003.00