S.J. Amoroso Construction - Change Order No. 17r • ►
City of Gilroy
Engineering Division
7351 Rosanna St., Gilroy, CA 95020
Phone (408) 846 -0450; Fax (408) 846 -0429
CHANGE ORDER NO. 017
To contract for : New Gilroy Police Facility Project No. 03 -CDD -114
Contractor: S.J. Amoroso Construction
Contract Date: 8/16/2004
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Item 17A: Contractor to provide for stub wall change to CMU at J112 in accordance with response to RFI -443.1 and
FieldMemo # 38 ...................................................................................... ............................... .....................$1,366.00.
(CPE #126)
Item 1713: Upsize glazing thickness at skylights to meet UL 972 requirements for Buglar Resistance in accordance with
City Ordinance 85 -17 and RFQ- 47 ........................................................... ............................... .....................$2,539.00.
(CPE #111)
Item 17C: Actual costs submitted for epoxy of dowels to receive CMU at thickened slab of jail core area and associated
splice bars related to RFQ -13, RFI -171R and RFI- 365 ............................ ............................... ....................$13,519.00.
(CPE #I 9CA-R and #7913)
Item 171): Additional costs for revising fittings and hangers in relocation of mechanical duct shaft at gridline B & 9 to
avoid interference in accordance with response to RFI Nos. 173, 173. 1 ............................... .....................$2,365.00.
(CPE #82 -R2)
Item 17E: Contractor to provide for lighting and window changes at Lobby S 107A in accordance with Clarification
Letter No. 8 and Submittal # 109 review comments ............................... ............................... .....................$1,102.00.
(CPE #133)
Item 17F: Contractor to provide for off -site striping improvements at Gilroy Family Center Lot on corner of 7th and
Rosanna in accordance with RFQ- 54 ...................................................... ............................... .....................$1,005.00.
(CPE #136)
Item 17G: Credit for deletion of 2" compressed air riser to mechanical equipment room in accordance with response to
RFI -3 60 ...................................................................................................... ............................... ..................... ($250.00).
(CPE #101)
Item 171-1: Credit for deletion of two floor sinks with piping at equipment room and downsize line in accordance with
responseto RFI- 351 ................................................................................... ............................... ...................($4,747.00).
(CPE #115)
Page 1 of 2
0004
All requirements of the original Contract Documents shall apply to the above work except as specifically
modified by this Change Order. The contract time shall not extend unless expressly provided for in this
Change Order.
Cost Percent
I (We) agree to make the above change Original Contract Price $22,377,000.00
subject to the terms of this Change Order Previous Change Orders to Date $215,014.00 1.0%
for the NET INCREASE of $16,899.00 Total to Date $22,592,014.00
This Change Order $16,899.00
Total Change Orders to Date $231,913.00 1.0% ALL
Revised Contract Price $22,608,913.00 how
S.J. Amoroso Construction Co., Inc.
yyContractor /f *Requires emergency authorization if greater than 25 %.
By: /'�Zl���,.v ! Date: J� i T
RECOMMENDED BY:
ACCEPTED BY:
Project Engineer
Page 2 of 2