S.J. Amoroso Construction - Change Order No. 18City of Gilroy
Engineering Division
7351 Rosanna St., Gilroy, CA 95020
Phone (408) 846 -0450; Fax (408) 846 -0429
CHANGE ORDER NO. 018
To contract for : New Gilroy Police Facility Project No. 03 -CDD -114
Contractor: S.J. Amoroso Construction
Contract Date: 8/16/2004
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Item 18A: Contractor to provide for center door operation of elevator S103 in accordance with Field Memo #143 and
#153 ................................................................................................................. ............................... .....................$2,965.00.
(CPE #114)
Item 1813: Add card readers, door alarm contacts/hardware, and control system programming in accordance with
InstructionBulletin #5 and RFQ- 42 ................................................................. ............................... ....................$16,469.00.
(CPE #97)
Item 18C: Provide and install elevator hoist beams and extend CMU walls of elevator S 107 to underside of structure in
accordance with response to RFI -34.1, 257 and 445 ...................................... ............................... .....................$2,306.00.
(CPE #61R)
Item 18D: Revise air compressor and air dryer equipment items in accordance with response to RFI -474, Instruction
Bulletin#7, and RFQ- 57 ................................................................................ ............................... ...................($2,379.00).
(CPE # 140)
All requirements of the original Contract Documents shall apply to the above work except as specifically
modified by this Change Order. The contract time shall not extend unless expressly provided for in this
Change Order.
Cost Percent
I (We) agree to make the above change Original Contract Price $22,377,000.00
subject to the terms of this Change Order Previous Change Orders to Date $231,913.00 1.0%
for the NET INCREASE of $19,361.00 Total to Date $22,608,913.00
This Change Order $19,361.00
Total Change Orders to Date $251,274.00 1.1%
Revised Contract Price $22,628,274.00
S.J. Amoroso Construction Co., Inc.
Contractor *Requires emergency authorization if greater than 25 %.
Page 1 of 2
RECOMM
ACCEPTE
•& . A
Page 2 of 2