S.J. Amoroso Construction - Change Order No. 21City of Gilroy
Engineering Division
7351 Rosanna St., Gilroy, CA 95020
Phone (408) 846 -0450; Fax (408) 846 -0429
CHANGE ORDER NO. "021
To contract for: New Gilroy Police Facility Project No. 03 -CDD -114
Contractor: S.J. Amoroso Construction Contract Date: 8/16/2004
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Item 21A: Additional cost to effect foundation changes at elevator 5103 in accordance with response to RFI -126, 161,
162R, 174, Submittal 926 revisions, and RFQ- 17 ..................................... ............................... .....................$8,850.00.
(CPE #2913)
Item 2113: Additional cost to effect foundation changes at elevator S101 in accordance with response to RFI -126, 161,
162R, 174, Submittal #26 revisions, and RFQ- 17 ...................................... ............................... .....................$7,434.00.
(CPE #29A)
Item 21 C: Contractor to provide for generator /fuel tank footing changes and additions in accordance with RFQ -36 and
FieldDirective No. 5 .................................................................................. ............................... .....................$5,878.00.
(CPE #77R3)
All requirements of the original Contract Documents shall apply to the above work except as specifically
modified by this Change Order. The contract time shall not extend unless expressly provided for in this
Change Order.
Page 1 of 2
Cost Percent
I (We) agree to make the above change Original Contract Price $22,377,000.00
subject to the terms of this Change Order Previous Change Orders to Date $300,495.00 1.3%
for the NET INCREASE of $22,162.00 Total to Date $22,677,495.00
This Change Order $22,162.00
Total Change Orders to Date $322,657.00 1.4%
Revised Contract Price $22,699,657.00
S.J. Amoroso Construction Co., Inc.
Contractor *Requires emergency authorization if greater than 25 %.