Loading...
S.J. Amoroso Construction - Change Order No. 25City of Gilroy Engineering Division 7351 Rosanna St., Gilroy, CA 95020 —6 ft Phone (408) 846 -0450; Fax (408) 846 -0429 CHANGE ORDER NO. 025 ��•RO`I To contract for : New Gilroy Police Facility Project No. 03 -CDD -114 Contractor: S.J. Amoroso Construction Contract Date: 8/16/2004 This order shall become effective when it has been signed by the City Administrator, City Engineer, Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned to him as his authority to proceed with the work. Description of Work Item 25A: Provide for added pneumatic tube route /station in accordance with RFQ -62 (WLC IB #9), Harris Field Memo Nos. 219, 229, and 246 ................................................................................. ............................... ....................$19,807.00. (CPE #168R) Item 25B: Install CRC clips in lieu of 16ga track for soffit attachment at steel beams in accordance with response to RFI- 484.5 and Field Memo Nos. 242 and 243 ..................................................... ............................... .....................$2,207.00. (CPE #148.1R) All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this Change Order. The contract time shall not extend unless expressly provided for in this Change Order. I (We) agree to make the above change subject to the terms of this Change Order for the NET INCREASE of $22,014.00 S.J. Amoroso Construction Co., Inc. Contractor *Requires emergency authorization if greater than 25% By: , Date: Page 1 of 2 Cost Percent Original Contract Price $22,377,000.00 Previous Change Orders to Date $396,837.00 1.8% Total to Date $22,773,837.00 This Change Order $22,014.00 Total Change Orders to Date $418,851.00 1.9% Revised Contract Price $22,795,851.00 *Requires emergency authorization if greater than 25% By: , Date: Page 1 of 2 R RECOMMENDED ACCEPTED BY: Page 2 of 2