S.J. Amoroso Construction - Change Order No. 26City of Gilroy
Engineering Division
7351 Rosanna St., Gilroy, CA 95020
Phone (408) 846 -0450; Fax (408) 846 -0429 -62005
CHANGE ORDER NO. 0262nC
To contract for: New Gilroy Police Facility Project No. 03 -CDD -114
Contractor: S.J. Amoroso Construction
Contract Date: 8/16/2004
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Item 26A: Modify steel beams and woven rod mesh over emergency generator to facilitate generator exhaust in
accordance with response to RFI- 529 .............................................................. ............................... .....................$5,426.00.
(CPE #185)
Item 26B: Additional cost agreed to for removal of mill scale at column faces to beam flange for welded connection.
Field labor hours acknowledged by Earth Systems inspector ......................... ............................... .....................$5,345.00.
(CPE #170, 170.1)
Item 26C: Provide for additions and framing revisions to high roof lobby area in accordance with response to RFI Nos.
253.2, 253.3 and 253.4 .................................................................................... ............................... .....................$8,669.00.
(CPE #200R)
Item 26D: Provide /install deck support plates (107) at roof mansard column locations in accordance with response to
RFI -4 9 8 .......................................................................................................... ............................... ..................... $5,631.00.
(CPE #163)
All requirements of the original Contract Documents shall apply to the above work except as specifically
modified by this Change Order. The contract time shall not extend unless expressly provided for in this
Change Order.
Cost
I (We) agree to make the above change Original Contract Price $22,377,000.00
subject to the terms of this Change Order Previous Change Orders to Date $418,851.00
for the NET INCREASE of $25,071.00 Total to Date $22,795,851.00
This Change Order $25,071.00
Total Change Orders to Date $443,922.00
Revised Contract Price $22,820,922.00
S.J. Amoroso Construction Co., Inc.
Contractor *Requires emergency authorization if greater than 25 %.
By: Date:
Page 1 of 2
Percent
1.9%
2.0% %) ,
RECOMMENDED
ACCEPTED BY:
Page 2 of 2