S.J. Amoroso Construction - Change Order No. 27City of Gilroy
Engineering Division
7351 Rosanna St., Gilroy, CA 95020 _
Phone (408) 846 -0450; Fax (408) 846 -0429 OCT 6 2005
CHANGE ORDER NO. 027
To contract for: New Gilroy Police Facility Project No. 03 -CDD -114
Contractor: S.J. Amoroso Construction
Contract Date: 8/16/2004
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Item 27A: Provide for CLSM backfill material at recommendation of Soils Engineer and RFI -271 response, where
sewage ejector and sand/oil separator are within the zone of building foundation influence ..... ....................$11,303.00.
(CPE #59)
Item 2713: Additional field labor cost to taper /trim column flanges to eliminate overhang on beams. Time acknowledged
byEarth Systems inspector ........................................................................ ............................... .....................$1,266.00.
(CPE #188)
Item 27C: Additional field labor cost to shorten six beams and revise beam connections to coincide with 12" masonry
wall constructed (8" wall referenced on structurals) in accordance with response to RFI -485 .. .....................$1,065.00.
(CPE # 166)
Item 27D: Additional field labor cost to modify elevator support column for beam connection at Line 1/E.5 (no beam
pocket shown) in accordance with response to RFI- 486 / 486. 1 ................. ............................... .....................$1,639.00.
(CPE # 167)
Item 27E: Provide for revised plaster base detail in accordance with response to RFI -347 and Harris Field Memo No.
144 .................................................................................................................................... ............................... $2,570.00.
(CPE # 121 R)
All requirements of the original Contract Documents shall apply to the above work except as specifically
modified by this Change Order. The contract time shall not extend unless expressly provided for in this
Change Order.
I (We) agree to make the above change
subject to the terms of this Change Order
for the NET INCREASE of $17,843.00
Original Contract Price
Previous Change Orders to Date
Total to Date
This Change Order
Total Change Orders to Date
Revised Contract Price
Page 1 of 2
Cost
$22,377,000.00
$443,922.00
$22,820,922.00
$17,843.00
$461,765.00
$22,838,765.00
Percent
2.0%
2.1%
S.J. Amoroso Construction Co., Inc.
Contractor * equires emergency authorization if greater than 25 %.
BY i"' //� ��'� Date: rL7
RECOMMENDED BY
ACCEPTED BY:
Page 2 of 2