S.J. Amoroso Construction - Change Order No. 29-50
City of Gilroy
Engineering Division ,'' US
7351 Rosanna St., Gilroy, CA 95020
Phone (408) 846 -0450; Fax (408) 846 -0429
CHANGE ORDER NO. 029
To contract for: New Gilroy Police Facility Project No. 03 -CDD -114
Contractor: S.J. Amoroso Construction
Contract Date: 8/16/2004
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Item 29A: Provide for cost difference between wall louver specified (L -3 -992 Chevron Style) and revised model SLD -6
DrainableStyle per Submittal 184 ......................................................... ............................... .....................$2,545.00.
(CPE #183)
Item 29B: Provide for changes to structural steel for boiler roof framing in accordance with response to RFI -348 and
348. 1 ...................................................................................................... ............................... .....................$6,348.00.
(CPE #195)
Item 29C: Additional cost for sandblasting slab joints between concrete deck pours at first floor in accordance with
responseto RFI- 490 ................................................................................ ............................... .....................$3,432.00.
(CPE #189)
Item 29D: Restaking costs for grades along Seventh Street and remobilization cost for grading on Dowdy due to
elevationrevisions .................................................................................. ............................... .....................$1,565.00.
(CPE #212)
Item 29E: Provide for Pop -out at Information Records in accordance with partial drawing 3A and 3B issued under RFQ-
63 .............................................................................................................. ............................... .....................$1,390.00.
(CPE #148AR)
All requirements of the original Contract Documents shall apply to the above work except as specifically
modified by this Change Order. The contract time shall not extend unless expressly provided for in this
Change Order.
Page 1 of 2
I (We) agree to make the above change
subject to the terms of this Change Order
for the NET INCREASE of $15,280.00
S.J. Amoroso Construction Co., Inc.
Original Contract Price
Previous Change Orders to Date
Total to Date
This Change Order
Total Change Orders to Date
Revised Contract Price
Cost
$22,377,000.00
$486,976.00
$22,863,976.00
$15,280.00
$502,256.00
$22,879,256.00
Contractor *Requires emergency authorization if greater than 25 %.
By: Date: to
RECOMMENDED l
ACCEPTED BY:
Page 2 of 2
Percent
2.2%
2.2% U