S.J. Amoroso Construction - Change Order No. 31City of Gilroy
Engineering Division
7351 Rosanna St., Gilroy, CA 95020
Phone (408) 846 -0450; Fax (408) 846 -0429
CHANGE ORDER NO. 031
To contract for: New Gilroy Police Facility Project No. 03 -CDD -114
Contractor: S.J. Amoroso Construction
Contract Date: 8/16/2004
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Item 31A: Added electrical provisions for relocated air compressor in accordance with response to RFI -474.1 and RFQ-
64 ............................................................................................................... ............................... .....................$4,134.00.
(CPE #176B)
Item 31B: Plumbing provisions to relocate air compressor from P107 to below stairs in Room S106 in accordance with
response to RFI- 474.1, RFQ -64, and Field Memo No. 220 ....................... ............................... .....................$5,526.00.
(CPE #I 76A)
Item 31 C: Provide for plaster soffit framing over south entry in accordance with response to RFI -528.1 and RFQ-
73 ...................................................................................................................................... ............................... $2,825.00.
(CPE # 177)
Item 31D: Provide for keying upgrade to Best's Patented Keyway (Premium) System at the request of the Owner from
the2/15/05 keying meeting ....................................................................... ............................... .....................$3,261.00.
(CPE #233R)
Item 31E: Provide for added electrical in operation of IWH units in accordance with response to RFI- 497.1R and RFQ-
81 ................................................................................................................. ............................... .......................$812.00.
(CPE #158)
Item 31F: Provide for wall framing changes to accommodate door openings in accordance with sketches and response to
RFI- 574 ........................................................................................................................... ............................... $793.00.
(CPE #216)
Item 31 G: Additional cost for shop re- detailing due to T.O.S. beam elevation changes in accordance with response to
RFI -14 5 ......................................................................................................... ............................... ....................... $858.00.
(CPE #191)
Item 31H: Revise shop and erection drawings due to mansard roof slope change (J line between 6 and 7) in accordance
withresponse to RFI- 358/ 358. 1 ................................................................ ............................... .....................$6,160.00.
(CPE # 192)
Page 1 of 2
DECEIVED
DEC 1 3 2005
ENGINEERING
All requirements of the original Contract Documents shall apply to the above work except as specifically
modified by this Change Order. The contract time shall not extend unless expressly provided for in this
Change Order.
Cost Percent
I (We) agree to make the above change Original Contract Price $22,377,000.00
subject to the terms of this Change Order Previous Change Orders to Date $526,300.00 2.4%
for the NET INCREASE of $24,369.00 Total to Date $22,903,300.00
This Change Order $24,369.00
Total Change Orders to Date $550,669.00 2.5%
Revised Contract Price $22,927,669.00
S.J. Amoroso Construction Co., Inc.
Contractor *Requires emergency authorization if greater than 25 %.
By: Date:
RECOMMEND
ACCEPTED BI
Page 2 of 2