Loading...
S.J. Amoroso Construction - Change Order No. 34City of Gilroy Engineering Division 7351 Rosanna St., Gilroy, CA 95020 Phone (408) 846 -0450; Fax (408) 846 - 04291,E CHANGE ORDER NO. 034 To contract for: New Gilroy Police Facility Project No. 03 -CDD -114 Contractor: S.J. Amoroso Construction Contract Date: 8/16/2004 This order shall become effective when it has been signed by the City Administrator, City Engineer, Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned to him as his authority to proceed with the work. Description of Work Item 34A: Additional costs to grind down concrete cap over existing SD line down Hanna Street to conform with new paving elevations in accordance with Field Directive No. 33 ............. ............................... ....................$16,560.00. (CPE #214R) Item 3413: Additional cost to effect casework changes per WLC submittal #130 review comments in accordance with RFQ -59 and Field Memo No. 178 ....................................................... ............................... .....................$7,898.00. (CPE #150R2) All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this Change Order. The contract time shall not extend unless expressly provided for in this Change Order. I (We) agree to make the above change subject to the terms of this Change Order for the NET INCREASE of $24,458.00 Original Contract Price Previous Change Orders to Date Total to Date This Change Order Total Change Orders to Date Revised Contract Price Cost Percent $22,377,000.00 $599,287.00 2.7% $22,976,287.00 $24,458.00 $623,745.00 2.8% $23,000,745.00 S.J. Amoroso Construction Co., Inc. Contractor *Requires emergency authorization if greater than 25 %. By: Date: RECEIVED DEC 1 3 2005 § iNEERING Page 1 of 2 n RECOMMENDED B'y ACCEPTED BY: Page 2 of 2