S.J. Amoroso Construction - Change Order No. 35City of Gilroy Engineering Division 7351 Rosanna St., Gilroy, CA 95020�� Phone (408) 846 -0450; Fax (408) 846 -0429 CHANGE ORDER NO. 035 To contract for : New Gilroy Police Facility Project No. 03 -CDD -114 Contractor: S.J. Amoroso Construction Contract Date: 8/16/2004 This order shall become effective when it has been signed by the City Administrator, City Engineer, Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned to him as his authority to proceed with the work. Description of Work Item 35A: Additional cost for security ceiling diffuser grilles due to change in ceiling type in accordance with response toRFI- 413. 1 ............................................................................................ ............................... .....................$1,378.00. (CPE # 156) Item 35B: Additional cost to remove /regrade existing asphalt encountered during grading for new curb and gutter along Dowdy and Seventh Street in accordance with Field Directive No. 31 ... ............................... .....................$8,317.00. (CPE #211) Item 35C: Additional cost to provide for meter by -pass line for domestic service in accordance with City Standard Drawing WA -14 and field requirements of Water Department ................ ............................... .....................$8,270.00. (CPE #239) Item 35D: Additional cost for new pair door/hardware at the south mechanical room in accordance with response to RFI- 253.5 and RFQ- 79 ................................................................................ ............................... .....................$4,663.00. (CPE #200.1) Item 35E: Additional cost to modify ductwork penetration resulting from relocated wall at E.5/1.7 in accordance with responseto RFI- 253. 6 .......................................................................... ............................... .....................$1,396.00. (CPE #200.2) All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this Change Order. The contract time shall not extend unless expressly provided for in this Change Order. I (We) agree to make the above change subject to the terms of this Change Order for the NET INCREASE of $24,024.00 RECEIVED DEC 1 3 2005 ENGINEERING Original Contract Price Previous Change Orders to Date Total to Date This Change Order Total Change Orders to Date Revised Contract Price Page 1 of 2 Cost Percent $22,377,000.00 $623,745.00 2.8% $23,000,745.00 $24,024.00 n (� $647,769.00 2.9% Y.(h/{V�`� -� $23,024,769.00 S.J. Amoroso Construction Co., Inc. Contractor *Requires emergency authorization if greater than 25 %. i By; Date: ///., S RECOMMENDED BY: ACCEPTED BY: i to Date J121011ar En Date roiect Engineer Date Page 2 of 2 Date