S.J. Amoroso Construction - Change Order No. 38City of Gilroy
Engineering Division
7351 Rosanna St., Gilroy, CA 95020 JAN 19 2W6
Phone (408) 846 -0450; Fax (408) 846 -0429
CHANGE ORDER NO. 038
To contract for : New Gilroy Police Facility Project No. 03 -CDD -114
Contractor: S.J. Amoroso Construction
Contract Date: 8/16/2004
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Item 38A: Contractor to provide for relocation of 6" RWL hangers in accordance with response to RFI -186.1 and 536.1
in compliance with Field Directive No. 43 .................................................... ............................... .....................$1,157.00.
(CPE #235.1)
Item 3813: Additional cost for crane rigging time to manuver mechanical equipment into penthouse due to framing/roof
closein while floor design was being modified .............................................. ............................... .....................$4,859.00.
(CPE #215C)
Item 38C: Additional cost for crane rigging time to manuver plumbing equipment into penthouse due to framing/roof
closein while floor design was being modified ................................................ ............................... .....................$1,863.00.
(CPE #215D)
Item 381): Provide for jail operation changes requested by Owner in accordance with WLC Instruction Bulletin #13
issued under RFQ -86 and Field Directive No. 54 ........................................... ............................... ....................$12,670.00.
(CPE #244)
Item 38E: Contractor to provide for changes to hot water piping and heat trace system in accordance with response to
RFI- 589.Iand RFQ- 84 .................................................................................... ............................... .......................$753.00.
(CPE #236A)
Item 38F: Contractor to provide for framing to support the 22 ga. sheet metal closure soffit panel at rake fascia in
accordance with response to RFI- 6. 1 .............................................................. ............................... .....................$1,776.00.
(CPE #248)
All requirements of the original Contract Documents shall apply to the above work except as specifically modified by
this Change Order. The contract time shall not extend unless expressly provided for in this Change Order.
Page 1 of 2
Cost Percent
I (We) agree to make the above change Original Contract Price $22,377,000.00
subject to the terms of this Change Order Previous Change Orders to Date $697,438.00 3.1%
for the NET INCREASE of $23,078.00 Total to Date $23,074,438.00
This Change Order $23,078.00
Total Change Orders to Date $720,516.00 3.2% Rui
Revised Contract Price $23,097,516.00
S.J. Amoroso Construction Co., Inc.
Contractor *Requires emergency authorization if greater than 25 %.
By: / G
RECOMMENDED BY:
ACCEPTED BY:
�a a_-�.�
Engineer
&- Afl-
Project
Page 2 of 2
Date
Date
Date J
Date