S.J. Amoroso Construction - Change Order No. 41City of Gilroy
Engineering Division 10
7351 Rosanna St., Gilroy, CA 95020
Phone (408) 846 -0450; Fax (408) 846 -0429
CHANGE ORDER NO. 041
To contract for : New Gilroy Police Facility Project No. 03 -CDD -114
Contractor: S.J. Amoroso Construction
Contract Date: 8/16/2004
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Item 41A: Provide /install framing clips for vertical alignment of CMU and plaster wall exteriors in accordance with
response to RFI-5 3 7/5 3 7. 1 and Field Directive No. 24 .......................... ............................... .....................$5,812.00.
(CPE #181.1 -R2)
Item 41 B: Provide /install framing clips for attachment to C- channel in accordance with response to RFI -522 and RFQ-
63 ........................................................................................................... ............................... .....................$1,143.00.
(CPE #181R)
Item 41 C: Provide /install flashing at fascia panel joint in accordance with response to RFI -592.1 and Field Directive No.
59 ............................................................................................................ ............................... .......................$907.00.
(CPE #260)
Item 41 D: Revise VAV -2 & 3 inlet sizes in accordance with Submittal # 192 review comments and Field Directive No.
57 ........................................................................................................... ............................... .....................$1,152.00.
(CPE #257)
Item 41E: Contractor to provide for deck slab reinforcing changes to accommodate walker duct transition in accordance
with- ................................................... ............................... .
(CPE #237)
Item 41 F: Contractor to provide for parapet wall extension in accordance with response to RFI- 605.1/605.1 R, RFQ -77,
andField Directive No. 36 ....................................................................... ............................... .....................$5,644.00.
(CPE #227 -R2)
Item 41 G: Provide for fire protection of converted storage area under north stair as identified under WLC Instruction
Bulletin #8, RFQ -60, and Field Directive No. 58 ..................................... ............................... .....................$3,862.00.
(CPE #151B)
Page 1 of 2
All requirements of the original Contract Documents shall apply to the above work except as specifically
modified by this Change Order. The contract time shall not extend unless expressly provided for in this
Change Order.
Cost Percent
I (We) agree to make the above change Original Contract Price $22,377,000.00
subject to the terms of this Change Order Previous Change Orders to Date $758,154.00 3.4%
for the NET INCREASE of $19,863.00 Total to Date $23,135,154.00
This Change Order $19,863.00
Total Change Orders to Date $778,017.00 3.5% OW—
Revised
Contract Price $23,155,017.00
S.J. Amoroso Construction Co., Inc.
Contractor *Requires emergency authorization if greater than 25 %.
ByAi /Ie� Date: W, 7 a
RECOMMENDED BY:
ACCEPTED BY:
r - (^
City Eng' er
Project Engineer •
Page 2 of 2
Date
Male
Date
Date