S.J. Amoroso Construction - Change Order No. 43�v r
City of Gilroy
Engineering Division JA +N 31
7351 Rosanna St., Gilroy, CA 95020
Phone (408) 846 -0450; Fax (408) 846 -0429
CHANGE ORDER NO. 043
To contract for : New Gilroy Police Facility Project No. 03 -CDD -114
Contractor: S.J. Amoroso Construction
Contract Date: 8/16/2004
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Item 43A: Contractor to provide for all design changes to roof pads /curbs and all direct cost associated with response to
RFI -555, Field Directive No. 25, and Field Memo No. 233 ........................ ............................... ....................$53,893.00.
(CPE #19613)
Item 4313: Credit for original AC unit pad concrete and additional cost for mechanical pad/curb wall anchors in
accordance with response to RFI -555, FD -25, and FM- 233 ......................... ............................... ...................($1,279.00).
(CPE # 196A -R)
Item 43C: Reduction to insulating concrete from change to parapet roof heights in accordance with response to RFI-
588 ................................................................................................................. ............................... ...................($1,695.00).
(CPE #221)
Item 43D: Delete slot diffusers and ductwork at Room 1031 and 1116 in accordance with response to RFI -370 and
370.1 ............................................................................................................... ............................... ..................... ($847.00).
(CPE #203)
All requirements of the original Contract Documents shall apply to the above work except as specifically modified by
this Change Order. The contract time shall not extend unless expressly provided for in this Change Order.
Page 1 of 2
I (We) agree to make the above change
subject to the terms of this Change Order
for the NET INCREASE of $50,072.00
S.J. Amoroso Construction Co., Inc.
Contractor
Original Contract Price
Previous Change Orders to Date
Total to Date
This Change Order
Total Change Orders to Date
Revised Contract Price
Cost Percent
$22,377,000.00
$835,422.00 3.7%
$23,212,422.00
$50,072.00
$885,494.00 4.0%
$23,262,494.00
*Requires emergency authorization if greater than 25 %.
G
By: Date: % b 16
RECOMMENDED B'
ACCEPTED BY:
Page 2 of 2