Loading...
S.J. Amoroso Construction - Change Order No. 44City of Gilroy Engineering Division 7351 Rosanna St., Gilroy, CA 95020 Phone (408) 846 -0450; Fax (408) 846 -0429 CHANGE ORDER NO. 044 To contract for : New Gilroy Police Facility Project No. 03 -CDD -114 Contractor: S.J. Amoroso Construction Contract Date: 8/16/2004 This order shall become effective when it has been signed by the City Administrator, City Engineer, Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned to him as his authority to proceed with the work. Description of Work Item 44A: Contractor to provide for blocking and angle material for mansard roof termination in accordance with responseto RFI -649 and RFQ- 92 .......................................................... ............................... .....................$2,365.00. (CPE #267) Item 4413: Shared cost of additional move -in of LVI for fireproofing of steel associated with pilaster repairs and completion of walker duct installations ................................................. ............................... .....................$1,567.00. (CPE #265) Jf Item 44C: Additional cost for curb re- grading at North Hanna due to elevation conflicts, and removal of concrete cap over existing storm drain line into curb inlet at Seventh / Hanna ............. ............................... .....................$5,015.00. (CPE #220.2) Item 441): Contractor to provide for solid wood corners to all W -2 panels in accordance with WLC review comments underSubmittal # 130 ............................................................................. ............................... .....................$2,403.00. (CPE #276) Item 44E: Contractor to provide for security ceiling addition and light fixture changes at J 1465 147 in accordance with RFQ- 94 ................................................................................................... ............................... .....................$5,162.00. (CPE 4274 A &B) Item 44F: Contractor to provide for change to wall/finish above jail doors at J1275128 in accordance with response to RFI -657R and RFQ- 91 ............................................................................. ............................... .....................$2,629.00. (CPE #262) Item 44F: Fabrication cost of tube steel columns for elevator guide rail support at S 101 /S 107 in accordance with response to RFI -593.2 and FD- 46R2 ......................................................... ............................... .....................$4,726.00. (CPE #231 A) All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this Change Order. The contract time shall not extend unless expressly provided for in this Change Order. Page 1 of 2 RECOMMENDED ACCEPTED BY: Page 2 of 2 Cost Percent I (We) agree to make the above change Original Contract Price $22,377,000.00 subject to the terms of this Change Order Previous Change Orders to Date $885,494.00 4.0% for the NET INCREASE of $23,867.00 Total to Date $23,262,494.00 This Change Order $23,867.00 Total Change Orders to Date $909,361.00 4.1% Revised Contract Price $23,286,361.00 S.J. Amoroso Construction Co., Inc. Contractor *Requires emergency authorization if greater than 25 %. fBy: RECOMMENDED ACCEPTED BY: Page 2 of 2