S.J. Amoroso Construction - Change Order No. 46City of Gilroy`'
Engineering Division!;' ,
7351 Rosanna St., Gilroy, CA 95020
Phone (408) 846 -0450; Fax (408) 846 -0429
CHANGE ORDER NO. 046
To contract for : New Gilroy Police Facility Project No. 03 -CDD -114
Contractor: S.J. Amoroso Construction
Contract Date: 8/16/2004
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Item 46A: Provide for all miscellaneous roofing items (added insulation/flashing, metal studs /plaster, and fix for bathtub
condition at east roof) in accordance with WLC Memo No. 34 and RFQ -93 ............................ ....................$17,351.00.
(CPE #269A -R3)
Item 4613: Contractor to provide for signage changes to Submittal #152 as noted by WLC and in accordance with
ClarificationLetter No. 15 ............................................................................ ............................... .....................$7,946.00.
(CPE # 171 R)
All requirements of the original Contract Documents shall apply to the above work except as specifically modified by
this Change Order. The contract time shall not extend unless expressly provided for in this Change Order.
Cost Percent
I (We) agree to make the above change Original Contract Price $22,377,000.00
subject to the terms of this Change Order Previous Change Orders to Date $934,860.00 4.2%
for the NET INCREASE of $25,297.00 Total to Date $23,311,860.00
This Change Order $25,297.00
Total Change Orders to Date $960,157.00 4.3%
Revised Contract Price $23,337,157.00
S.J. Amoroso Construction Co., Inc.
Contractor *Requires emergency authorization if greater than 25 %.
By: �;; �� ( V2cX� -s�C. Date:
Page 1 of 2
RECOMMENDED
ACCEPTED BY:
Page 2 of 2