Loading...
S.J. Amoroso Construction - Change Order No. 49City of Gilroy Engineering Division 7351 Rosanna St., Gilroy, CA 95020 Phone (408) 846 -0450; Fax (408) 846 -0429 CHANGE ORDER NO. 049 To contract for : New Gilroy Police Facility Project No. 03 -CDD -114 Contractor: S.J. Amoroso Construction Contract Date: 8/16/2004 This order shall become effective when it has been signed by the City Administrator, City Engineer, Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned to him as his authority to proceed with the work. Description of Work Item 49A: Contractor to provide /install deck closure pieces at north, south, and west penthouse roofs in accordance with responseto RFI -687 and RFQ- 93 .............................................................. ............................... .....................$2,047.00. (CPE #269B) Item 4913: Cost agreement to provide /install wet concrete stops at metal decking in accordance with Harris Field Memo No. 274 ...................................................................................................... ............................... .....................$8,159.00. (CPE #190) ea r�. r.:. Item 49C: Direct costs to effect repairs at fractured pilasters in accordance with response to RFI -502 and Field Directive No. 29 (T &M cost only for performance of repairs) .................................... ............................... ....................$14,572.00. (CPE #157) All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this Change Order. The contract time shall not extend unless expressly provided for in this Change Order. Page 1 of 2 Cost Percent I (We) agree to make the above change Original Contract Price $22,377,000.00 subject to the terms of this Change Order Previous Change Orders to Date $996,205.00 4.5% for the NET INCREASE of $24,778.00 Total to Date $23,373,205.00 This Change Order $24,778.00 Total Change Orders to Date $1,020,983.00 4.6% " Revised Contract Price $23,397,983.00 S.J. Amoroso Construction Co., Inc. Contractor *Requires emergency authorization if greater than 25 %. By Date: Page 1 of 2 RECOMMENDEI ACCEPTED BY: Page 2 of 2