S.J. Amoroso Construction - Change Order No. 53-` AS
City of Gilroy , R Soy,
Engineering Division
aECEIVEp
7351 Rosanna St., Gilroy, CA 95020 JUN 2 6 2(706 co
Phone (408) 846 -0450; Fax (408) 846 -0429
CHANGE ORDER NO. 053
To contract for : New Gilroy Police Facility Project No. 03 -CDD -114
Contractor: S.J. Amoroso Construction Contract Date: 8/16/2004
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Item 53A: Contractor to provide for switching of Corridor 1106 lighting in accordance with response to RFI -756 and
RFQ- 112 ............................................................................................................................. ............................... $424.00.
(CPE #320)
Item 53B: Contractor to provide for stainless steel tops added in Room 1112 in accordance with RFQ -59 (not paid for in
CPE# 150R2) ............................................................................................. ............................... .....................$1,098.00.
(CPE # 150.1)
Item 53C: Provide /install additional roof walk -tread in accordance with Lower Roof Plan -Walk Tread Layout issued
underRFQ- 107 ............................................................................................ ............................... .....................$5,112.00.
(CPE #304)
Item 531): Provide for all electrical changes /additions (WLC Bulletin No. 15, Items 15.1 through 15.3 only) in
accordancewith RFQ- 98 .............................................................................. ............................... .....................$8,384.00.
(CPE #296R)
All requirements of the original Contract Documents shall apply to the above work except as specifically modified by
this Change Order. The contract time shall not extend unless expressly provided for in this Change Order.
Page 1 of 2
P.M.
Cost
Percent Initial
I (We) agree to make the above change
Original Contract Price
$22,377,000.00
subject to the terms of this Change Order
Previous Change Orders to Date
$1,050,822.00
4.7%
for the NET INCREASE of $15,018.00
Total to Date
$23,427,822.00
This Change Order
$15,018.00
�}
Total Change Orders to Date
$1,065,840.00
4.8% W1p'W
Revised Contract Price
$23,442,840.00
S.J. Amoroso Construction Co., Inc.
Contractor
*Requires emergency authorization if greater
than 25 %.
IL
Date:
Page 1 of 2
RECOMMENDED BY
ACCEPTED BY:
C (Aa rig p OrJ C r y Page 2 of 2