S.J. Amoroso Construction - Change Order No. 60City of Gilroy
Engineering Division
7351 Rosanna St., Gilroy, CA 95020
Phone (408) 846 -0450; Fax (408) 846 -0429
CHANGE ORDER NO. 060
To contract for : New Gilroy Police Facility Project No. 03 -CDD -114
Contractor: S.J. Amoroso Construction
Contract Date: 8/16/2004
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Item 60: Contractor to provide for City IT requested changes in communication provisions; cable upgrade, added
conduit runs, and all added/revised items (1 thru 9) listed in Semans letter of 4/14/06 in accordance with WLC
Instruction Bulletin #17 and RFQ- 109R .................................................. ............................... ....................$30,464.00.
(CPE #306R)
All requirements of the original Contract Documents shall apply to the above work except as specifically modified by
this Change Order. The contract time shall not extend unless expressly provided for in this Change Order.
ACCEPTED BY:
Page 1 of 1
q-,2 ef '--
P.M.
Cost
Percent Initial
I (We) agree to make the above change
Original Contract Price
$22,377,000.00
subject to the terms of this Change Order
Previous Change Orders to Date
$1,210,534.00
5.4% Ott
for the NET INCREASE of $30,464.00
Total to Date
$23,587,534.00
This Change Order
$30,464.00
Total Change Orders to Date
$1,240,998.00
5.5%
Revised Contract Price
$23,617,998.00