S.J. Amoroso Construction - Change Order No. 73City of Gilroy
Engineering Division
7351 Rosanna St., Gilroy, CA 95020
Phone (408) 846 -0450; Fax (408) 846 -0429
CHANGE ORDER NO. 073
To contract for : New Gilroy Police Facility Project No. 03 -CDD -114
Contractor: S.J. Amoroso Construction Contract Date:
8/16/2004
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Item 73A: Complete electrical power to control panels in accordance with response to RFI -900 and Field Directive No.
146R..................................................................................................................................... ............................... $769.00.
(CPE #413.1)
Item 73B: Contractor to provide electrical for added pneumatic tube station in accordance with response to RFI -927R
andField Directive No. 180 ............................................................................ ............................... .....................$3,273.00.
(CPE #438)
Item 73C: Contractor to provide for ceramic tile borders at toilet accessories in accordance with response to RFI -886
andField Directive No. 136 ............................................................................. ............................... .....................$2,539.00.
(CPE #400)
Item 73D: Contractor to provide for relocation of supply air diffuser at J123 in accordance with response to RFI -786 and
FieldDirective No. 104 ................................................................................. ............................... .......................$370.00.
(CPE #342)
Item 73E: Contractor to provide /install batt insulation cap at return air openings above ceilings in accordance with
response to RFI -604 and Field Directive No. 100 ......................................... ............................... .....................$3,764.00.
(CPE #338)
Item 73F: Contractor to provide for added uplights and relocation of lobby receptacle in accordance with response to
RFI- 831.1/831.2, and Field Directive No. 115R ......................................... ............................... ....................$13,179.00.
(CPE #357A)
All requirements of the original Contract Documents shall apply to the above work except as specifically modified by
this Change Order. The contract time shall not extend unless expressly provided for in this Change Order.
Page 1 of 2
I (We) agree to make the above change
subject to the terms of this Change Order
for the NET INCREASE of $23,894.00
S.J. Amoroso Construction Co., Inc.
Contractor
0
RECOMMEN
ACCEPTED E
Cost
Original Contract Price $22,377,000.00
Previous Change Orders to Date $1,714,360.00
Total to Date $24,091,360.00
This Change Order $23,894.00
Total Change Orders to Date $1,738,254.00
Revised Contract Price $24,115,254.00