S.J. Amoroso Construction - Change Order No. 78City of Gilroy
Engineering Division
7351 Rosanna St., Gilroy, CA 95020
Phone (408) 846 -0450; Fax (408) 846 -0429
CHANGE ORDER NO. 078
To contract for : New Gilroy Police Facility Project No. 03 -CDD -114
Contractor: S.J. Amoroso Construction Contract Date: 8/16/2004
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Item 78A: Contractor to provide for added deck drains in accordance with response to RFI -798.3 thru 798.5, and Field
DirectiveNo. 124- R3 ....................................................................................... ............................... ....................$10,941.00.
(CPE #380 -BR)
Item 7813: Contractor to provide for all wall /ceiling access doors in accordance with response to RFI -711, 711.1B, 711.2
and711. 3 .......................................................................................................... ............................... .....................$7,500.00.
(CPE #311)
Item 78C: Contractor to remove disposal at Room 1154 and re -plumb for proper drainage in accordance with Field
Directive No. 185, turn over disposal to Owner ................................................. ............................... .......................$551.00.
(CPE #457)
Item 78D: Contractor to provide for joints at main exterior stairs in accordance with response to RFI -797 and Field
DirectiveNo. 106 .............................................................................................. ............................... .......................$475.00.
(CPE #345R)
Item 78E: Contractor to provide for footing /pads for exterior tree planters in accordance with response to RFI -897, RFQ-
139, and FD- 162 ........................................................................................... ............................... .....................$2,216.00.
(CPE #411)
All requirements of the original Contract Documents shall apply to the above work except as specifically modified by
this Change Order. The contract time shall not extend unless expressly provided for in this Change Order.
Page 1 of 2
PM
Cost Percent Initial
I (We) agree to make the above change Original Contract Price $22,377,000.00 44
subject to the terms of this Change Order Previous Change Orders to Date $1,816,414.00 8.1%
for the NET INCREASE of $21,683.00 Total to Date $24,193,414.00
This Change Order $21,683.00 1 ,
Total Change Orders to Date $1,838,097.00 8.2% WO
Revised Contract Price $24,215,097.00
S.J. Amoroso Construction Co., Inc.
Contractor *Requires emergency authorization if greater than 25 %.
` Date:,
RECOMMENDS
ACCEPTED BY
.0
Page 2 of 2