S.J. Amoroso Construction - Change Order No. 79City of Gilroy Engineering Division Phone (408) 846 -0450; Fax (408) 846 -0429 CHANGE ORDER NO. 079 To contract for : New Gilroy Police Facility Project No. 03 -CDD -114 Contractor: S.J. Amoroso Construction Contract Date: 8/16/2004 This order shall become effective when it has been signed by the City Administrator, City Engineer, Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned to him as his authority to proceed with the work. Description of Work Item 79: Provide for all labor costs associated with installation of directional tiles /warning strips, survey /staking, sidewalk and electrical excavation at traffic circle, temp fence rental, and 1 tree removal in accordance with Hanna Street changes by City, RFQ -117R, and Field Directive No. 118 ............. ............................... ....................$48,451.00. (CPE #321B -R2) All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this Change Order. The contract time shall not extend unless expressly provided for in this Change Order. P.M. Cost Percent Initial I (We) agree to make the above change Original Contract Price $22,377,000.00 subject to the terms of this Change Order Previous Change Orders to Date $1,838,097.00 8.2% for the NET INCREASE of $48,451.00 Total to Date $24,215,097.00 This Change Order $48,451.00 Total Change Orders to Date $1,886,548.00 8.4% Revised Contract Price $24,263,548.00 S.J. Amoroso Construction Co., Inc. Contractor *Requires emergency authorization if greater than 25 %. By. � Date: le-A11,07 RECOMMEND)= ACCEPTED BY Page 1 of 1