S.J. Amoroso Construction - Change Order No. 80City of Gilroy
Engineering Division
Phone (408) 846 -0450; Fax (408) 846 -0429
CHANGE ORDER NO. 080
To contract for: New Gilroy Police Facility Project No. 03 -CDD -114
Contractor: S.J. Amoroso Construction Contract Date: 8/16/2004
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Item 80A: Contractor to provide for saddle flashings at penthouses in accordance with response to RFI -916.1 and Field
DirectiveNo. 154 .......................................................................................... ............................... .....................$1,402.00.
(CPE #425)
Item 8013: Contractor to seal off void space at south penthouse slab edge in accordance with response to RFI -823, RFQ-
126 and FD- 198 ............................................................................................. ............................... .....................$2,595.00.
(CPE #353)
Item 80C: Additional survey /staking for revised alignment/grades on Hanna Street performed on initial design changes
issuedunder RFQ- 74 .................................................................................. ............................... .....................$2,998.00.
(CPE #220 -R2)
Item 801): Contractor to provide for gate security contacts in accordance with response to RFI -951 and Field Directive
No. 194 ......................................................................................................... ............................... .......................$754.00.
(CPE #468)
Item 80E: Contractor to provide for removal/capping of plumbing piping through elevator machine room P 120 in
accordance with response to RFI- 305/908 and FD- 157 .................................. ............................... .......................$764.00.
(CPE #419)
Item 80F: Contractor to provide for drywall cants at elevator S103 shaft in compliance with State requirements, response
toRFI -921, and FD- 178 ................................................................................ ............................... .....................$1,686.00.
(CPE #436)
Item 80G: Contractor to provide for breaker changes and 208v electrical for heat trace system in accordance with
responseto RFI- 693.1, and FD- 193 .................................................................. ............................... .....................$4,750.00.
(CPE #469)
Page 1 of 2
Item 80H: Contractor to provide for revised help buttons at jail area in accordance with response to RFI -945 and Field
DirectiveNo. 184 ......................................................................................... ............................... .....................$1,745.00.
(CPE #455)
Item 80I: Contractor to provide for all changes to conduit tie -in at the existing Police Department in accordance with
response to RFI- 742.1/828, RFQ -123 and FD- 152R ................................... ............................... ....................$15,845.00.
(CPE #344)
All requirements of the original Contract Documents shall apply to the above work except as specifically modified by
this Change Order. The contract time shall not extend unless expressly provided for in this Change Order.
RECOMMENDEI
ACCEPTED BY:
Page 2 of 2
PM
Cost
Percent Initial
I (We) agree to make the above change
Original Contract Price
$22,377,000.00
0#4
subject to the terms of this Change Order
Previous Change Orders to Date
$1,886,548.00
8.4%
for the NET INCREASE of $32,539.00
Total to Date
$24,263,548.00
This Change Order
$32,539.00
U4
Total Change Orders to Date
$1,919,087.00
8.6%
Revised Contract Price
$24,296,087.00
S.J. Amoroso Construction Co., Inc.
Contractor
*Requires emergency authorization if
greater than 25 %.
By. L %6G�
�( Date: d
RECOMMENDEI
ACCEPTED BY:
Page 2 of 2