S.J. Amoroso Construction - Change Order No. 82City of Gilroy Engineering Division Phone (408) 846 -0450; Fax (408) 846 -0429 CHANGE ORDER NO. 082 To contract for: New Gilroy Police Facility Project No. 03 -CDD -114 Contractor: S.J. Amoroso Construction Contract Date 8/16/2004 This order shall become effective when it has been signed by the City Administrator, City Engineer, Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned to him as his authority to proceed with the work. Description of Work Item 82A: Contractor to provide for electrical power to microwave at Rm 1041 in accordance with response to RFI -971 andField Directive No. 199 ...................................................................... ............................... .....................$1,657.00. (CPE #483) Item 8213: Contractor to provide /install access door at east tower in accordance with response to RFI -253.7 and Field DirectiveNo. 37 (not paid in CCO- 55) ......................................................... ............................... .......................$535.00. (CPE #200.4) ' Item 82C: Contractor to provide /install Ice & Water Shield over the mechanical roof pads in accordance with Field DirectiveNo. 47 ............................................................................................ ............................... .....................$1,847.00. (CPE #247.1) Item 82D: Contractor to provide /install revised brackets for TV in accordance with response to RFI -540.4 and Field DirectiveNo. 174 ........................................................................................ ............................... .....................$7,874.00. (CPE #439) Item 82E: Contractor to add flashing at skylights in accordance with response to RFI -960.1 and Field Directive No. 195 .................................................................................................................. ............................... .....................$1,238.00. (CPE #467) Item 82F: Contractor to provide for all changes issued under WLC IB -19 (BOC changes), RFQ -131, and Field Directive No. 120 ........................................................................................................ ............................... ....................$13,507.00. (CPE #370R) Item 82G: Contractor to provide for motor starters /switches at boiler pumps in accordance with response to RFI -322.4 andField Directive No. 165 ............................................................................ ............................... .....................$4,798.00. (CPE #412B) Page 1 of 2 All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this Change Order. The contract time shall not extend unless expressly provided for in this Change Order. RECOMMEN ACCEPTED] Page 2 of 2 PM Cost Percent Initial I (We) agree to make the above change Original Contract Price $22,377,000.00 subject to the terms of this Change Order Previous Change Orders to Date $1,951,560.00 8.7% for the NET INCREASE of $31,456.00 Total to Date $24,328,560.00 This Change Order $31,456.00 Total Change Orders to Date $1,983,016.00 8.9% Revised Contract Price $24,360,016.00 S.J. Amoroso Construction Co., Inc. Contractor *Requires emergency authorization if greater than 25 %. By: iO O /j l/�—�Y Date: O RECOMMEN ACCEPTED] Page 2 of 2