S.J. Amoroso Construction - Change Order No. 84City of Gilroy
Engineering Division
7351 Rosanna St., Gilroy, CA 95020
Phone (408) 846 -0450; Fax (408) 846 -0429
CHANGE ORDER NO. 084
To contract for : New Gilroy Police Facility Project No. 03 -CDD -114
Contractor: S.J. Amoroso Construction Contract Date: 8/16/2004
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Item 84A: Contractor to provide for routing/connection of conduits for future street/parking lot lighting in accordance
withField Directive No. 13 .................................................................. ............................... .....................$2,151.00.
(CPE #147)
Item 8413: Contractor to provide for added sports flooring base and backing in accordance with response to RFI -902.1
and Field Directive No. 175 ................................................................... ............................... .....................$2,395.00.
(CPE #432)
Item 84C: Contractor to remove existing concrete cap as required to facilitate placement of new concrete flatwork in
accordance with response to RFI -862.1 and Field Directive No. 127 ........ ............................... .....................$6,399.00.
(CPE #214.1R2)
Item 841): Contractor to provide /install combination motor starters at exhaust fan units in accordance with response to
RFI- 322.1, RFQ -138, and Field Directive No. 147R ................................. ............................... ....................$19,382.00.
(CPE #412A)
All requirements of the original Contract Documents shall apply to the above work except as specifically modified by
this Change Order. The contract time shall not extend unless expressly provided for in this Change Order.
Page 1 of 2
Page 2 of 2
PM
Cost
Percent Initial
I (We) agree to make the above change Original Contract Price
$22,377,000.00
subject to the terms of this Change Order Previous Change Orders to Date
$2,008,527.00
9.0%
for the NET INCREASE of $30,327.00 Total to Date
$24,385,527.00
This Change Order
$30,327.00
Total Change Orders to Date
$2,038,854.00
9.1%
Revised Contract Price
$24,415,854.00
S.J. Amoroso Construction Co., Inc.
Contractor *Requires emergency authorization if greater
than 25 %.
By: 1; Date: d
Page 2 of 2