S.J. Amoroso Construction - Change Order No. 86City of Gilroy
Engineering Division
7351 Rosanna St., Gilroy, CA 95020
Phone (408) 846 -0450; Fax (408) 846 -0429
CHANGE ORDER NO. 086
To contract for : New Gilroy Police Facility Project No. 03 -CDD -114
Contractor: S.J. Amoroso Construction Contract Date:
8/16/2004
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Item 86A: Contractor to provide for 13 revised door thresholds in accordance with response to RFI -935 and Field
DirectiveNo. 176 ................................................................................. ............................... .....................$1,377.00.
(CPE #437)
Item 8613: Contractor to provide for revised column enclosures at garage area in accordance with response to RFI -617.2
through 617.4 and Field Directive No. 128R ........................................ ............................... .....................$8,485.00.
(CPE #391)
Item 86C: Contractor to provide for additional concrete and wire mesh at deck topping slabs in accordance with
response to RFI -798 through 798.6 and Field Directive No. 124R ........ ............................... ....................$18,258.00.
(CPE #380A)
Item 861): Contractor to provide /install magnetic hold -open and door closer at I I 03 in accordance with WLC IB #20,
RFQ -140, and Field Directive No. 158R ................................................. ............................... .....................$2,295.00.
(CPE #422)
Item 86E: Contractor to provide /install epoxy flooring at J I I in accordance with response to RFI -961, and Field
DirectiveNo. 191 ..................................................................................... ............................... .....................$1,575.00.
(CPE #462)
All requirements of the original Contract Documents shall apply to the above work except as specifically modified by
this Change Order. The contract time shall not extend unless expressly provided for in this Change Order.
Page 1 of 2
RECOMMENDED I
ACCEPTED BY:
Page 2 of 2
PM
Cost
Percent Initial
I (We) agree to make the above change
Original Contract Price
$22,377,000.00
subject to the terms of this Change Order
Previous Change Orders to Date
$3,888,854.00
17.4%
for the NET INCREASE of $31,990.00
Total to Date
$26,265,854.00
This Change Order
$31,990.00
Total Change Orders to Date
$3,920,844.00
17.5%
Revised Contract Price
$26,297,844.00
S.J. Amoroso Construction Co., Inc.
Contractor
*Requires emergency authorization if greater
than 25 %.
Date: o
By: