S.J. Amoroso Construction - Change Order No. 89City of Gilroy Engineering Division 7351 Rosanna St., Gilroy, CA 95020 Phone (408) 846 -0450; Fax (408) 846 -0429 CHANGE ORDER NO. 089 To contract for : New Gilroy Police Facility Project No. 03 -CDD -114 Contractor: S.J. Amoroso Construction Contract Date: 8/16/2004 This order shall become effective when it has been signed by the City Administrator, City Engineer, Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned to him as his authority to proceed with the work. Description of Work Item 89A: Contractor to provide for electrical to insta -hot water heaters in accordance with response to RFI -985 and FieldDirective No. 209 .................................................................................... ............................... .....................$7,954.00. (CPE #491) Item 8913: Contractor to provide /install motor starters for EF -5 through EF -9 in accordance with response to RFI -981 andField Directive No. 206 ........................................................................... ............................... ....................$12,688.00. (CPE #488) Item 89C: Credit for locking device at mens and womens lockers called out in Section 10505 -2.4, A -6 and Request For QuotationNo. 142 ............................................................................................ ............................... .....................($394.00). Item 891): Contractor to provide /install CAT6 cable for each entry telephone (4) in accordance with response to RFI -901 andField Directive No. 171 .......................................................................... ............................... .....................$8,350.00. (CPE #449) All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this Change Order. The contract time shall not extend unless expressly provided for in this Change Order. Page 1 of 2 RECOMMENDED BY: ACCEPTED BY Date Date / V i Date i Project Engineer Page 2 of 2 PM Cost Percent Initial I (We) agree to make the above change Original Contract Price $22,377,000.00 subject to the terms of this Change Order Previous Change Orders to Date $3,978,621.00 17.8% for the NET INCREASE of $28,598.00 Total to Date $26,355,621.00 This Change Order $28,598.00 Total Change Orders to Date $4,007,219.00 17.9% Revised Contract Price $26,384,219.00 S.J. Amoroso Construction Co., Inc. Contractor *Requires emergency authorization if greater than 25 %. By: W'w Date: 7 RECOMMENDED BY: ACCEPTED BY Date Date / V i Date i Project Engineer Page 2 of 2