S.J. Amoroso Construction - Change Order No. 91City of Gilroy
Engineering Division
7351 Rosanna St., Gilroy, CA 95020
Phone (408) 846 -0450; Fax (408) 846 -0429
CHANGE ORDER NO. 091
To contract for : New Gilroy Police Facility Project No. 03 -CDD -114
Contractor: S.J. Amoroso Construction Contract Date:
8/16/2004
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Item 91A: Contractor to provide /install added exit signs in accordance with response to RFI -962, and Field Directive No.
197 ............................................................................................................... ............................... .......................$855.00.
(CPE #473)
Item 91B: Contractor to provide for vent/water piping relocation at loading dock in accordance with WLC IB #16, FD -96,
andFM- 521 ................................................................................................... ............................... .....................$3,674.00.
(CPE #305B)
Item 91C: Contractor to provide /install two additional camera poles in accordance with response to RFI -136.2 and Field
DirectiveNo. 189 ............................................................................................. ............................... ....................$13,364.00.
(CPE #465)
Item 91 D: Contractor to provide /install end wall closure angles in accordance with response to RFI -872, RFQ -135, and
FieldDirective No. 151 .................................................................................... ............................... .....................$3,683.00.
(CPE #386)
Item 91E: Credit to contract for payment of generator operational permit paid to BAAQMD by City Purchase Order No.
70685, as noted under FM- 495 ......................................................................... ............................... ...................($1,390.00).
All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this
Change Order. The contract time shall not extend unless expressly provided for in this Change Order.
Page 1 of 2
RECOMMENDEL
ACCEPTED BY:
Page 2 of 2
PM
Cost
Percent Initial
I (We) agree to make the above change
Original Contract Price
$22,377,000.00
!.�
subject to the terms of this Change Order
Previous Change Orders to Date
$4,063,920.00
18.2% 4`4
for the NET INCREASE of $20,186.00
Total to Date
$26,440,920.00
This Change Order
$20,186.00
�� / j�
Total Change Orders to Date
$4,084,106.00
18.3% '�/4
Revised Contract Price
$26,461,106.00
S.J. Amoroso Construction Co., Inc.
Contractor
*Requires emergency authorization if greater
than 25 %.
By:
Date:
RECOMMENDEL
ACCEPTED BY:
Page 2 of 2