S.J. Amoroso Construction - Change Order No. 93City of Gilroy
Engineering Division
7351 Rosanna St., Gilroy, CA 95020
Phone (408) 846 -0450; Fax (408) 846 -0429
CHANGE ORDER NO. 093
To contract for :
New Gilroy Police Facility
Project No.
03 -CDD -114
Contractor:
S.J. Amoroso Construction
Contract Date:
8/16/2004
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Item 93A: Contractor to provide for the changes issued under WLC IB #21 (duct enclosure and added electrical) in
accordance with Field Directive No. 205 ..................................................... ............................... ....................$11,038.00.
(CPE #485)
Item 9313: Contractor to provide for closure angle at domed mirror installed in J131 as noted/requested by CSA inspection
(work added under Field Directive No. 205 ............................................ ............................... .......................$634.00.
(CPE #407.1)
Item 93C: Contractor to provide for added entry telephone /connections and revised camera connections issued under
WLCIB #18, and Field Directive No. 108 ................................................... ............................... .....................$7,652.00.
(CPE #354)
Item 93D: Contractor to provide for grade adjustment of existing SDMH at North Hanna not included under Field
DirectiveNo. 117R costs .................................................................................. ............................... .......................$767.00.
(CPE #500)
Item 93E: Contractor to adjust/replace sheave for EF -13 to reduce fan RPM in accordance with response to RFI -953 and
FieldDirective No. 201 ....................................................................................... ............................... .......................$942.00.
(CPE #461)
Item 93F: Contractor to provide for integration of the clean agent system with mechanical controls in accordance with
response to RFI- 967/967.1 and Field Directive Nos. 203 / 211 ....................... ............................... .......................$658.00.
(CPE #480)
All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this
Change Order. The contract time shall not extend unless expressly provided for in this Change Order.
Page 1 of 2
I (We) agree to make the above change
subject to the terms of this Change Order
for the NET INCREASE of $21,691.00
Original Contract Price
Previous Change Orders to Date
Total to Date
This Change Order
Total Change Orders to Date
Revised Contract Price
$4,127,865.00 18.4%
$265504,865.00
S.J. Amoroso Construction Co., Inc.
Contractor *Requires emergency authorization if greater than 25 %.
By: A" Date: Wei 014)
RECOMMENDED W
ACCEPTED BY:
a
Page 2 of 2
PM
Cost
Percent Initial
$22,377,000.00
$4,106,174.00
18.3% '"
$26,483,174.00
$21,691.00
$4,127,865.00 18.4%
$265504,865.00
S.J. Amoroso Construction Co., Inc.
Contractor *Requires emergency authorization if greater than 25 %.
By: A" Date: Wei 014)
RECOMMENDED W
ACCEPTED BY:
a