S.J. Amoroso Construction - Change Order No. 94City of Gilroy
Engineering Division
7351 Rosanna St., Gilroy, CA 95020
Phone (408) 846 -0450; Fax (408) 846 -0429
CHANGE ORDER NO. 094
To contract for : New Gilroy Police Facility Project No. 03 -CDD -114
Contractor: S.J. Amoroso Construction
Contract Date: 8/16/2004
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Item 94A: Contractor to provide /install additional door sweeps at exterior locations in accordance with response to RFI-
995 and Field Directive No. 215 ........................................................................ ............................... .....................$1,249.00.
(CPE #498)
Item 94B: Contractor to provide for all changes under WLC IB #22 required by CSA in accordance with Field Directive
No. 202 ................................................................................................................................ ............................... $2,638.00.
(CPE #484)
Item 94C: Contractor to provide for added sheet flashing under mansard roof in accordance with response to RFI -819,
RFQ -129, and Field Directive No. 116 ............................................................. ............................... ....................$10,244.00.
(CPE #348R)
Item 94D: Contractor to provide for all tree changes, palm tree to 3 bambusa at the atrium stair, per verbal field direction
byArchitect ................................................................................................... ............................... .....................$2,120.00.
(CPE #477)
Item 94E: Contractor to provide /install additional flashing and fastener to conceal angle iron at mansard ridge in
accordancewith response to RFI- 842 ........................................................... ............................... .....................$7,769.00.
(CPE #373)
Item 94F: Contractor to provide for hardware changes to doors 1083/1089 and stainless steel channels at lobby counter
glass in accordance with response to RFI- 990/991, and FD- 212 ................ ............................... .....................$7,229.00.
(CPE #494)
Item 94G: Full settlement of cost associated with low voltage electrical for keyswitch at jail cell doors (not required) and
cover plates provided in response to RFI- 861/861.1, FD -121, and FM- 484 .... ............................... .....................$5,500.00.
(CPE #377)
Page 1 of 2
All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this
Change Order. The contract time shall not extend unless expressly provided for in this Change Order.
I (We) agree to make the above change
subject to the terms of this Change Order
for the NET INCREASE of $36,749.00
Original Contract Price
Previous Change Orders to Date
Total to Date
This Change Order
Total Change Orders to Date
Revised Contract Price
S.J. Amoroso Construction Co., Inc.
Contractor *Requires emergency authorization if greater than 25 %.
By: a %� Date: 6 7
Page 2 of 2
PM
Cost
Percent Initial
$22,377,000.00
f�
$4,127,865.00
18.4% 114
$26,504,865.00
$36,749.00
',i
$4,164,614.00
18.6% W
$26,541,614.00
S.J. Amoroso Construction Co., Inc.
Contractor *Requires emergency authorization if greater than 25 %.
By: a %� Date: 6 7
Page 2 of 2