S.J. Amoroso Construction - Change Order No. 96 FinalCity of Gilroy
Engineering Division
7351 Rosanna St., Gilroy, CA 95020
Phone (408) 846 -0450; Fax (408) 846 -0429
CHANGE ORDER NO. 096 (FINAL)
To contract for : New Gilroy Police Facility Project No. 03 -CDD -114
Contractor: S.J. Amoroso Construction
Contract Date: 8/16/2004
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Item 96A: Contractor to provide for fire sprinkler drop adjustments due to ceiling height changes to accommodate MEP
installations through field direction by WLC .............................................. ............................... .....................$1,500.00.
(CPE #427)
Item 96B: Contractor to provide for removal of wet soil due to weather impacts resulting from design changes affecting
pavingoperations and schedule ..................................................................... ............................... .....................$3,500.00.
(CPE #220.1)
Item 96C: Contractor to provide for all additional costs incurred associated with duct pressure testing resulting from
ambiguous and/or conflicting design and test criteria in contract documents .............................. ....................$27,000.00.
(CPE #246R)
Item 96D: Contractor to provide for all additional costs incurred associated with installation /operation of the FSCP
system in accordance with response to RFI -854.2 and Field Directive No. 73R ........................ ....................$35,000.00.
(CPE #264)
All requirements of the original Contract Documents shall apply to the above work except as specifically modified by
this Change Order. The contract time shall not extend unless expressly provided for in this Change Order.
Page 1 of 2
I (We) agree to make the above change
subject to the terms of this Change Order
for the NET INCREASE of $67,000.00
Cost
Original Contract Price $22,377,000.00
Previous Change Orders to Date $4,194,865.00
Total to Date $26,571,865.00
This Change Order $67,000.00
Total Change Orders to Date $4,261,865.00
Revised Contract Price $26,638,865.00
S.J. Amoroso Construction Co., Inc.
Contractor *Requires emergency authorization if greater than 25 %.
By: Date: V( ,1 V-0 7
RECOMMENDED BY:
Project Engineer
Page 2 of 2
PM
Percent Initial
18.7% &A'
19.0% UAW
City of Gilroy
Engineering Division
7351 Rosanna St., Gilroy, CA 95020
Phone (408) 846 -0450; Fax (408) 846 -0429
CHANGE ORDER NO. 096 (FINAL)
To contract for : New Gilroy Police Facility Project No. 03 -CDD -114
Contractor: S.J. Amoroso Construction
Contract Date: 8/16/2004
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
Item 96A: Contractor to provide for fire sprinkler drop adjustments due to ceiling height changes to accommodate MEP
installations through field direction by WLC .............................................. ............................... .....................$1,500.00.
(CPE #427)
Item 9613: Contractor to provide for removal of wet soil due to weather impacts resulting from design changes affecting
pavingoperations and schedule ..................................................................... ............................... .....................$3,500.00.
(CPE #220.1)
Item 96C: Contractor to provide for all additional costs incurred associated with duct pressure testing resulting from
ambiguous and/or conflicting design and test criteria in contract documents .............................. ....................$27,000.00.
(CPE #246R)
Item 96D: Contractor to provide for all additional costs incurred associated with installation /operation of the FSCP
system in accordance with response to RFI -854.2 and Field Directive No. 73R ........................ ....................$35,000.00.
(CPE #264)
All requirements of the original Contract Documents shall apply to the above work except as specifically modified by
this Change Order. The contract time shall not extend unless expressly provided for in this Change Order.
Page 1 of 2
I (We) agree to make the above change
subject to the terms of this Change Order
for the NET INCREASE of $67,000.00
Original Contract Price
Previous Change Orders to Date
Total to Date
This Change Order
Total Change Orders to Date
Revised Contract Price
Cost
$22,377,000.00
$4,194,865.00
$26,571,865.00
$67,000.00
$4,261,865.00
$26,638,865.00
S.J. Amoroso Construction Co., Inc.
Contractor *Requires emergency authorization if greater than 25 %.
By: ` % %G %� Date: ll 7
PM
Percent Initial
18.7%W-424
19.0%
Page 2 of 2