Monterey Peninsula Engineering - 1st Street Water Utility Improvements - Change Order No. 3City of Gilroy
y • Engineering Division
7351 Rosanna St., Gilroy, CA 95020
Phone (408) 846-0450; Fax (408) 846-0429
CHANGE ORDER NO. 3
To contract for: City of Gilroy First Street Water Utility Improvements Project No. 16-PW-217
Contractor: Monterey Peninsula Engineering Contract Date: June 18, 2018
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be
returned to him as his authority to proceed with the work.
Descriution of Work
This change order provides for the following: Credit for all labor, equipment and material for elimination of the requirement to
install Polywrap around the new ductile iron pipe, as set forth in the contract documents, revised per RFI 004.
All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this
Change Order. The contract time shall not extend unless expressly provided for in this Change Order.
By signing this Change Order, Contractor acknowledges and agrees that the adjustments to cost and time contained herein are
in full satisfaction and accord, and are accepted as payment in full, for any and all costs and expenses associated with this
Change Order, (the "Extra Work"), including but not limited to labor, materials, overhead and profit, delay, disruption, loss
of efficiency and any and all other direct and/or indirect costs or expenses associated with the Extra Work and hereby waives
any right to claim any further cost and time impacts at any time during and after completion of the Contract associated with the
Extra Work.
Monterey Peninsula Engineering hereby agrees to
make the above changes
subject to the terms of this Change Order
for the NET DECREASE of $11,500
CONTR-ACTO
11c-1�rvvb . rrv,,ee�u<x�w
Date: 10 A411 K
RECOMMENDED BY: .% �,e—
Construction Manager
ACCEPTED BY: City Administrator
'ngineer
e.
roject Engineer
Percentaae
Initial Cost
Original Contract Price $5,451,990.00
Previous Change Orders $35,358 0.65%
Total to Date $5,466,939.00
This Change Order $(11,500)
Total Change Orders to Date $23,858 0.43%
Revised Contract Price $5,443,081