Monterey Peninsula Engineering - 1st Street Water Utility Improvements - Change Order No. 4City of Gilroy
Engineering Division
7351 Rosanna St., Gilroy, CA 95020
• Phone (408) 846-0450; Fax (408) 846-0429
CHANGE ORDER NO.4
To contract for: City of Gilroy First Street Water Utility Improvements Project No. 16-PW-217
Contractor: Monterey Peninsula Engineering
Contract Date: June 18, 2018
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be
returned to him as his authority to proceed with the work.
Description of Work
1) Cal Trans Permit Reimbursement per section 01060 2.1. Cost $1,640
2) Three (3) additional contract calendar days issued due to lack of applicable permit at time of Notice to Proceed on July 18,
2018. Contractor was unable to start pothole activities until Caltrans permit was received on August 17, 2018.
All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this
Change Order. The contract time shall not extend unless expressly provided for in this Change Order.
By signing this Change Order, Contractor acknowledges and agrees that the adjustments to cost and time contained herein are
in full satisfaction and accord, and are accepted as payment in full, for any and all costs and expenses associated with this
Change Order, (the "Extra Work"), including but not limited to labor, materials, overhead and profit, delay, disruption, loss
of efficiency and any and all other direct and/or indirect costs or expenses associated with the Extra Work and hereby waives
any right to claim any further cost and time impacts at any time during and after completion of the Contract associated with the
Extra Work.
Monterey Peninsula Engineering hereby agrees to
make the above changes
subject to the terms of this Change Order
for the NET INCREASE of $1,640.00
t CONTRACTO
Date: 11Z? f /9
RECOMMENDED BY:
Percentage
Initial Cost
Original Contract Price $5,451,990.00
Previous Change Orders $23,858 0.44%
Total to Date $5,475,848.00
This Change Order $1,640
Total Change Orders to Date $25,498
Revised Contract Price $5,477,488
Construct on Manager Date
ACCEPTED BY: City Administrator Date
y / Z-- 6 // y
ity Engineer Date
Project Engineer Date
0.47%
GaV