Resolution 1981-98
It
~.
.
.
RESOLUTION NO. 81-98
A RESOLUTION OF THE COUNCIL OF THE CITY
OF GILROY ESTABLISHING AN OVERLAY DRAINAGE
ZONE ENCOMPASSING STORM DRAIN AREA "B" FOR
FINANCING AN INTERIM DRAINAGE PROJECT.
WHEREAS, a report of the Director of Public Works
recommends an overlay zone providing for additional unit
charges for all development in Storm Drain Area "B" so as
to recover the cost of construction of an interim drainage
project in that area and so as provide reimbursement to those
developers now providing the funds to build the interim drainage
project.
THE COUNCIL OF THE CITY OF GILROY DOES HEREBY RESOLVE:
(a) An overlay drainage zone is hereby established
in Storm Drain Area "B" to assist in the financing of an
interim drainage project designed to accommodate 1.000 residential
units for that area.
(b) All environmental report, administration. design,
construction and other costs for the proposed project will be
paid by the several developers who wish to build in Storm
Drain Area liB", with all funding to be provided initially by
agreement among those who now wish to build, hereafter called
"Current Developers".
(c) If the project proceeds to completion, the
total sum of all costs therefore shall be divided by the
1.000 units to be served to determine the per unit charge
required to finance the project, and this per unit drainage
charge shall be assessed in addition to the development fees
charged in Resolution No. 81-76 and collected by the City
against all construction in Storm Drain Area "B" on the
-1-
RESOLUTION NO. 81-98
t
!!
.
.
following basis:
One drainage unit charge per detached
single family residence.
Six-tenths drainage unit charge per
single story multiple residence dwelling
unit.
Thirty-three hundredths drainage unit
charge per multi-story multiple residence
dwelling unit.
Seven drainage unit charges per acre of
commercial development.
(d) The City shall reimburse the current Developers
who provided project funding from the drainage unit charges
collected. When 1,000 drainage unit charges have been collected
and paid over, the Current Developers will have recovered all
funds advanced, the interim drainage project will be at
capacity, and the overlay zone and unit charges will be terminated.
At that time, no further development in Storm Drain Area liB"
will be permitted unless or until the drainage is further improved
by the federal 566 or other project.
(e) Current Developers shall include only those
who contribute their pro-rata shares of the proposed project
financing within 30 days of the award of the contract. All
other later developers shall pay their per unit charges plus
a ten percent surcharge, or their per unit charges as increased
by indexing to the Engineer's News Record Cost of Construction
Index, whichever is greater.
(f) No further building permits will be issued to
any developer in Storm Drain Area "B" until full payment
of the above charges, and until the interim drainage project
is functional.
-2-
RESOLUTION NO. 81-98
.!'
.
.
PASSED AND ADOPTED this 26th day of October,
1981 by the following vote:
AYES:
NOES:
ABSENT:
COUNCILMEMBERS:
CUNNINGHAM HUGHAN LINK
PATE, TAYL6R AND G60DRICH
NONE
NONE
COUNCILMEMBERS:
COUNCILMEMBERS:
APPROVED:
~
~
ayor
~~~~
(' t er
-3-
RESOLUTION NO. 81-98
~
.
.
"
I, SUSANNE E. STEINMETZ, City Clerk of the City of Gilroy, do
hereby certify that the attached Resolution No. 81-98 is an
original resolution, duly adopted by the Council of the City of
Gilroy at a regular meeting of said Council held on the 26th
day of October , 19 ~, at which meeting a quorum was
present.
IN WITNESS WHEREOF, I have hereunto set my hand and affixed the
Official Seal of the City of Gilroy this 20th day of November
, 19~.