HomeMy WebLinkAboutResolution No. 2026-33 | FY 2027 SB1 Project List Resolution | Adopted 05/18/2026
RESOLUTION NO. 2026-33
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF GILROY ADOPTING A LIST OF PROJECTS FOR
FISCAL YEAR 2026-2027 FUNDED BY SB 1: THE ROAD
REPAIR AND ACCOUNTABILITY ACT OF 2017
WHEREAS, Senate Bill 1 (SB 1), the Road Repair and Accountability Act of 2017
(Chapter 5, Statutes of 2017) was passed by the Legislature and Signed into law by the Governor
in April 2017 to address the significant multi-modal transportation funding shortfalls statewide;
and
WHEREAS, SB 1 includes accountability and transparency provisions to ensure the
residents of the City of Gilroy are aware of the projects proposed for funding in our community
and which projects have been completed each fiscal year; and
WHEREAS, the City of Gilroy must adopt by resolution a list of projects proposed to
receive Fiscal Year 2026–27 funding from the Road Maintenance and Rehabilitation Account
(RMRA), which must include a description and location of each project, schedule, and useful
life; and
WHEREAS the City of Gilroy will receive an estimated $ 1,745,381 in RMRA funding
for Fiscal Year 2026–27; and
WHEREAS, this is the tenth year in which the City of Gilroy is receiving SB 1 funding
and will enable the City of Gilroy to continue essential road maintenance and rehabilitation
projects, safety improvements, repairing and replacing aging bridges, and increasing access and
mobility options for the traveling public that would not have otherwise been possible without SB
1; and
WHEREAS, the City has undergone a robust public process to ensure public input into
our community’s transportation priorities/the project list, including the implementation of an
online service request portal called “Gilroy Connect” which is available on the City’s website
and as a standalone mobile application, and allows residents to submit, track, and monitor
requests, including requests for street maintenance and rehabilitation; and
WHEREAS, the City of Gilroy used a Pavement Management System to develop the SB
1 project list to ensure revenues are being used on the most high-priority and cost-effective
projects that also meet the communities’ priorities for transportation investment; and
WHEREAS, the funding from SB 1 will help the City maintain and rehabilitate
approximately 145,000 square feet of pavement on major collectors and arterials and work
towards implementing the complete streets ordinance; and
WHEREAS, the 2023 California Statewide Local Streets and Roads Needs Assessment
found that the City’s streets and roads are in good condition, and this revenue will help us
increase the overall quality of our road system and keep our streets and roads in good cond ition;
and
Docusign Envelope ID: D93173EB-057A-8230-82A1-4E35FEC0AC53
Resolution No. 2026-33
Gilroy FY 2026-27 SB 1 Road Projects Resolution
City Council Regular Meeting | May 18, 2026
Page 2 of 3
WHEREAS, the SB 1 project list and overall investment in our local streets and roads
infrastructure with a focus on basic maintenance and safety, investing in complete streets
infrastructure, and using cutting-edge technology, materials and practices, will have significant
positive co-benefits for those who live, work, and visit the City of Gilroy.
NOW, THEREFORE IT IS HEREBY RESOLVED, ORDERED AND FOUND by
the City Council of the City of Gilroy, as follows:
1. The foregoing recitals are true and correct.
2. The following list of newly proposed projects will be funded in-part or solely with Fiscal
Year 2026-27 Road Maintenance and Rehabilitation Account revenues:
Project Title: FY26 Citywide Pavement Rehabilitation Project
Project Description: Milling and placement of asphalt concrete pavement; adjacent
curb ramp upgrades; adjustment of utilities to grade; roadway striping, signage,
and markings; traffic signal loop replacement; and other incidental work.
Project Location: The following locations identified are subject to change based on
priority needs or available funding: Mantelli Dr from Rancho Hills Dr to Muir Dr
and
Monterey Rd from Monterey Frontage Rd to approximately 580 feet south of Garlic
Farm Dr
Estimated Project Schedule: Start 12/26 - Completion 07/27 based on the component
being funded with RMRA funds
Estimated Project Useful Life: 15 years
PASSED AND ADOPTED this 18th day of May 2026 by the following roll call vote:
AYES: COUNCIL MEMBERS: BRACCO, CLINE, HILTON, MARQUES,
RAMIREZ, BOZZO
NOES: COUNCIL MEMBERS: NONE
ABSTAIN: COUNCIL MEMBERS: NONE
ABSENT: COUNCIL MEMBERS: FUGAZZI
Docusign Envelope ID: D93173EB-057A-8230-82A1-4E35FEC0AC53
Resolution No. 2026-33
Gilroy FY 2026-27 SB 1 Road Projects Resolution
City Council Regular Meeting | May 18, 2026
Page 3 of 3
APPROVED:
______________________________
Greg Bozzo, Mayor
ATTEST:
_____________ _________________
Kim Mancera, City Clerk
CERTIFICATE OF THE CLERK
I, KIM MANCERA, City Clerk of the City of Gilroy, do hereby certify that the attached
Resolution No. 2026-33 is an original resolution, or true and correct copy of a City Resolution,
duly adopted by the Council of the City of Gilroy at a Regular Meeting of said Council held on
Monday, Date, with a quorum present.
IN WITNESS WHEREOF, I have hereunto set my hand and affixed the Official Seal of
the City of Gilroy this Wednesday, May 20, 2026.
____________________________________
Kim Mancera
City Clerk of the City of Gilroy
Docusign Envelope ID: D93173EB-057A-8230-82A1-4E35FEC0AC53