HomeMy WebLinkAboutDevcon Construction - Library Construction - Change Order No. 4 City of Gilroy Engineering Division 7351 Rosanna St., Gilroy, CA 95020 Phone (408) 846-0451; Fax (408) 846-0429 CHANGE ORDER NO.4 To contract for: New Gilroy Library Project, Phase 2 Contractor: Devcon Construction Contract Date: 6/15/2010 This order shall become effective when it has been signed by the City Administrator, City Engineer, Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned to him as his authority to proceed with the work. Description of Work This Change Order provides for the following: Revisions required per Bulletin #5. 47 Floor Mats and Frames Bulletin #5: Deletion of floor mat at Door 111 B. 53 Mechanical WestBay Mechanical: Revisions required per Bulletin #5. ($500.00) ($500.00) ($4,523.00) ($4,523.00) Subtotal 68 Fee Total 70 Amount applied to Contingency 71 Amount applied to OT Allowance Net change order amount ($5,023.00) $0.00 ($5,023.00) $0.00 / $0.00 V ($5,023.00) All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this Change Order. The contract time shall not extend unless expressly provided for in this Change Order. By signing this Change Order, Contractor acknowledges and agrees that the adjustments to cost and time contained herein are in full satisfaction and accord, and are accepted as payment in full, for any and all costs and expenses associated with this Change Order, (the "Extra Work"), including but not limited to labor, materials, overhead and profit, delay, disruption, loss of efficiency and any and all other direct and/or indirect costs or expenses associated with the Extra Work and hereby waives any right to claim any further cost and time impacts at any time during and after completion of the Contract associated with the Extra Work. I (W e) agree to make the above change subject to the terms of this Change Order for the NET INCREASE of -$5,023.00 Original Contract Price Previous Change Orders Total to Date This Change Order Total Change Orders to Date Revised Contract Price Cost Percentage Initial $18,177,226.00 $206,423.00", 1.14% $18,383,649.00 -$5,023.00 $201,400.00 ~ 1.11% $18,378,626.00 ~ ~J-. .--V"~ CONTRACTOR By: 9M~~U. Date: \!I~,A t \J (GE, fW;LOetJr r; ~V (;O,..J RECOMMENDED BY: ACCEPTED BY: ;?/t-.-- Change Proposal Request: 22 ~~ Project: Gilroy Community Library Devcon Job #: 10-296 Date: 12/3/2010 We submit for your approval the following estimate of changes in work: Revisions required per Bulletin #5. 47 Floor Mats and Frames Bulletin #5: Deletion of floor mat at Door 111 B. 53 Mechanical WestBay Mechanical: Revisions required per Bulletin #5. ($500.00) ($500.00) ($4,523.00) ($4,523.00) Subtotal 68 Fee Total 70 Amount applied to Contingency 71 Amount applied to OT Allowance Net change order amount ($5,023.00) $0.00 ($5,023.00) $0.00 $0.00 ($5,023.00) D We have proceeded with this change per the direction of: o We will not proceed with this change until receipt of a signed copy of this proposal. o This proposal must be accepted by: xx/xx/xx in order to avoid additional extension or expense. D These changes will add approximately xx working ,days to the completion date. Submitted by: Date: Devcon -Daisy Pereira Approved by: Date: Owner's Representative; David Marks, Nova Partners Devcon Construction Inc. 690 Gibraltar Dr. Milpitas, CA 95035 P.(408)942-8200 F. (408)262-2342 Lie. #399163 WESTBAY ~II M E C H A N I C A L liD Add J Change Order 1725 De La Ouz Blvd. Suite 4 ! Sanla Clara. CA 95050 408 969 0050 0 408 969 0070 , We N" 835511 CO#: DATE: 12/8/10 TO: Devcon .tin: Andre lumsey REF # Bulletin 5 ITEM #2 PROJECT: GDroy Ubrary Potential schedule Impact: YES I NO circle one DESCRIPTION: Item 2 - Air Intake Ductwork - MAU2 Delete the intake shroud and ductwork between the louvered wall opening and MAU2. D No Cost Change D COlt Change To Follow (or unknown) [i] Cost Change Is DEDUCT -$1,896.20 Breakdown Materials Tax Labor Overhead & Profit TOTAL: -$1,106.52 -$102.35 -$440.00 -$247.33 -$1,896.20 PRINT NAME SIGNED: Authorized Signature to proceed DATE: WESTBAY iilll M E C H A N I C A L. liD Add I Change Order 1725 De La Cruz Blvd. Suite 4 j Santa Clara. CA 95050 408 969 0050 0 400 969 0070 . Uc N" 835511 CO#: DATE: 12/8/10 TO: Oevcon attn: Andre Lumsey REF '1# Bulletin 5 ITEM #3 PROJECT: Gilroy Library Potential schedule impact: YES I NO circle one DESCRIPTION: Item 3 - Air Intake Ductwork - MAU1 Delete the louvered intake wall opening, shroud, and the 1S"x1S" ductwork between the louvered wall opening and MAU1. Add an 1S"x1S" intake duct sufficient to put Intake minimum 10' from MAU1 exhaust. o No Cost Change o COlt Change To Follow (or unknown) [iJ Cost Change Is DEDUCT -$2,626.67 Breakdown Materials Tax labor Overhead & Profit TOTAL: -$983.12 -$90.94 -$1,210.00 -$342.61 -$2.626.67 PRINT NAME SIGNED: DATE: Authorized Signature to proceed