HomeMy WebLinkAboutDevcon Construction - Library Construction - Change Order No. 22City of Gilroy
Engineering Division
7351 Rosanna St., Gilroy, CA 95020
Phone (408) 846 -0451; Fax (408) 846 -0429
CHANGE ORDER NO. 22
To contract for : New Gilroy Library Project, Phase 2
Contractor: Devcon Construction
Contract Date: 6/15/2010
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work
This Change Order provides for the following:
Demolition of Paseo area per preliminary plans by Hanna - Brunetti
4 Piped Utilities
Robinson & Moretti, Inc: Demolition of Paseo area per
preliminary plans by Hanna - Brunetti
Subtotal
69 Fee
$50,000.00
$50,000.00
�i5u,uuu.uu
10.00% $5,000.00
Total $55,000.00
71 Amount applied to Contingency $0.00
72 Amount applied to OT Allowance $0.00
Net change order amount $55,000.00
These changes will add approximately 10 working days to the completion date.
All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this
Change Order. The contract time shall not extend unless expressly provided for in this Change Order.
By signing this Change Order, Contractor acknowledges and agrees that the adjustments to cost and time contained herein
are in full satisfaction and accord, and are accepted as payment in full, for any and all costs and expenses associated with this
Change Order, (the "Extra Work "), including but not limited to labor, materials, overhead and profit, delay, disruption, loss
of efficiency and any and all other direct and/or indirect costs or expenses associated with the Extra Work and hereby waives
any right to claim any further cost and time impacts at any time during and after completion of the Contract associated with
the Extra Work.
I (We) agree to make the above change
subject to the terms of this Change Order
for the NET INCREASE of $55,000.00
C TRACTOR
Glr
By: �,:u Date: /L
f
v
Original Contract Price
Previous Change Orders
Total to Date
This Change Order
Total Change Orders to Date
Revised Contract Price
Cost Percentage Initial
$18,177,226.00
$930,929.00 5.12% hh-
$19,108,155.00
$55,000.00
$985,929.00 5.42% 04-
$19,163,155.00
RECOMMENDED BY:
ACCEPTED BY: City 46min / f/� Date
G
Date
// (� / / Z-
Project Engineer`/ I Date
CPR 145
Project: Gilroy Community Library
Devcon Job #: 10 -296
Date: 2/9/2012
We submit for your approval the following estimate of changes in work:
Demolition of Paseo area per preliminary plans by Hanna - Brunetti
4 Piped Utilities
Robinson & Moretti, Inc: Demolition of Paseo area per
preliminary plans by Hanna - Brunetti
Subtotal
69 Fee
Total
71 Amount applied to Contingency
72 Amount applied to OT Allowance
Net change order amount
$50,000.00
$50,000.00
$50,000.00
10.00% $5,000.00
$55,000.00
$0.00
$0.00
$55,000.00
❑ We have proceeded with this change per the direction of:
• We will not proceed with this change until r eipt of a signed copy of this proposal.
• This proposal must be accepted by: xx/ xx in order to avoid additional extension or expense.
x These changes will add approximate 10 working days to the completion date.
Submitted by:
Approved by:
-Bob Roseberry
mes Kuhn, Nova Partners
Date:
Date:
Devcon Construction Inc. 690 Gibraltar Dr. Milpitas, CA 95035 P.(408)942 -8200 F. (408)262 -2342 Lic. #399163
Robinson & Moretti, Inc.
* A Land Improvement Contractor
7780 Holsclaw Road
Gilroy, California 95020
Phone No. (408) 842 -5593 Fax No. (408) 842 -7763
Owner/ Contractor: Devcon
Attn: Bob Roseberry
POJECT NAME: LIBRARY PLAZA DEMO DATE: 2/8/ 2012
DEMO IMPROVEMENTS: $50,000.00
- DEMO PER PRELIMINARY PLANS BY HANNA - BRUNETTI
PROJECT TOTAL: $50,000.0
PROJECT EXCL USIONS. contaminated soil export, permits, encroachment permits, submittals, grinding by others, overlay by others, slurry seal by others
"DUE TO VOLATILITY OF LIQUID ASPHALT AND NATURAL GAS PRICING, THE HOT MIX ASPHALT PRICE QUOTED WILL BE IN EFFECT FOR
ASPHALT PURCHASED WITHIN 30 DAYS AFTER THIS QUOTATION. AFTER THAT TIME THE HOT MIX ASPHALT PRICE WILL BE ADJUSTED IN
RELATION TO ANY MATERIAL CHANGE IN THE MARKET PRICE OF LIQUID ASPHALTAND NATURAL GAS AND THAT COST WILL BE PASSED
ON TO CONTRACTOR $xxx /ton."
Excludes: soils testing, staking, & permits. Fees or expenses related to additional insurance requirements; such as waiver ofsubrogation, wrap insurance
program or additional certificates.
WE PROPOSE to furnish labor and material -- complete in accordance with above specifications, and subject to conditions found on
this agreement, for the sum of :_ dollars (US $)
Net 30 -days
Terms of payment: days
ACCEPTED. The above prices, specifications and conditions are satisfactory Respectfully Submitted,
and are hereby accepted. You are authorized to do the work as specified.
Payment will be made as outlined above. Robinson & Moretti Inc., License No. 418843A
Date of Acceptance
By: /S/ Rich Robinson/ Alex Mango, P.E.
By
Note: We may withdraw this proposal if not accepted within 30 days.