CHANGE ORDER NO. 24
To contract for : New Gilroy Library Project, Phase 2
Contractor: Devcon Construction
Contract Date: 6/15/2010
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work This Change Order provides for the following:
Additional Landscaping work per FO # 38
11 Planting Work
$10.220.00
Collishaw Constructior. Inc. Additiona Landscaping
S10,220.00
work per FCC 4 38
Subtotal
$10,220.00
69 Fee
10.00% S1.022.00
Total
$11,242.00
71 Amount applied to Contingency
S0.00
72 Amount applied to OT Allowance
S0.00
Net change order amount
s $11,242.00
Move 5 existing Crepe Myrtle trees to new locations and hand water for 120 days
11 Planting Work
$35,450.00
Collishaw Constructior., Inc.: Move 5 existing Crepe
$35,450.00
Myrtle trees to'new localicns and hand water for 120
days
Subtotal
$35,450.00
69 Fee
10.00°/ $3,545.00
Total
$38,995.00
71 Amount applied to Contingency
$0.00
72 Amount applied to OT Allowance
$0.00
Net change order amount
$38,995.00
C
These Changes will add approximately 10 working days to the completion date.
All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this
Change Order. The contract time shall not extend unless expressly provided for in this Change Order.
By signing this Change Order, Contractor acknowledges and agrees that the adjustments to cost and time contained herein
are in full satisfaction and accord, and are accepted as payment in full, for any and all costs and expenses associated with this
Change Order, (the "Extra Work "), including but not limited to labor, materials, overhead and profit, delay, disruption, loss
of efficiency and any and all other direct and/or indirect costs or expenses associated with the Extra Work and hereby waives
any right to claim any further cost and time impacts at any time during and after completion of the Contract associated with
the Extra Work.
I (We) agree to make the above change
subject to the terms of this Change Order
for the NET INCREASE of $50,237.00
C�1TR�CTOR
By: // vw Date: Vi L
i
Original Contract Price
Previous Change Orders
Total to Date
This Change Order
Total Change Orders to Date
Revised Contract Price
Cost Percentage Initial
$18,177,226.00
$1 ,044,779.00 5.75 %_
$19,222,005.00
$50,237.00
$1,095,016.00 6.02 %_
$19,272,242.00
$0.00
RECOMMENDED BY:
ACCEPTED BY:
■ . , a
L
Project: Gilroy Community Library
Devcon Job #: 10 -296
Date: 3/5/2012
We submit for your approval the following estimate of changes in work:
Move 5 existing Crepe Myrtle trees to new locations and hand water for 120 days
�f
11 Planting Work
Collishaw Construction, Inc.: Move 5 existing Crepe
Myrtle trees to new locations and hand water for 120
days
Subtotal
69 Fee
Total
71 Amount applied to Contingency
72 Amount applied to OT Allowance
Net change order amount
$35,450.00
$35,450.00
$35,450.00
10.00% $3,545.00
$38,995.00
$0.00
$0.00
$38,995.00
❑ We have proceeded with this change per the direction of:
❑ We will not proceed with this change until receipt of a signed copy of this proposal.
❑ This proposal must be accepted by: xx/xx/xx in order to avoid additional extension or expense
x These changes will add approximately 10 working days to the completion date.
Submitted by: Date.
,rte' Devcon -Bob Roseberry
Approved by: ` C/ Date: 2° Z
Ow rs Representative: James Kuhn, Nova Partners
Devcon Construction Inc. 690 'Gibraltar Dr. Milpitas, CA 95035 P.(408)942 -8200 F. (408)262 -2342 Lic. #399163
OLLISHAW
ONSTRUCTION, Inc.
Site Development
March 1, 2012
ATTN: BOB ROSEBERRY
RE: GILROY LIBRARY
Transplanting Trees
Dear Mr. Roseberry,
Our pricing for the above mentioned project is as follows:
Prune, dig, relocate, auger, fertilize, stake and provide positive drainage $18,500
at the bottom of the root ball for (4) Lagerstroemias. Price includes digging
the trees with a 72" root Ball and providing soil mix and drainage material
for replanting. Also, includes Collishaw Construction laborers helping out
With the process
120 Day maintenance for the 4 trees only $ 9,860
TOTAL: $ 28,360
Please call me with any questions or concerns.
Respect illy,
Robert Jimenez Jr.
t0�0 //-
1125 Mabury Road . San Jose, CA 95133 • (408) 995 -3404 • Fax (408) 294 -4586
Mailing Address: P.O. Box 611718 • San Jose, CA 95161 -1718
"An Equal Opportunity Employer" State License #449324
CPR 151
i
Project: Gilroy Community Library
Devcon Job #: 10 -296 y
Date: 3/5/2012 s
We submit for your approval the following estimate of changes in work:
Additional Landsca
nq work per FO # 38
11 Planting Work $10,220.00
Collishaw Construction, Inc.: Additional Landscaping $10,220.09
work per FO # 38
Subtotal
69 Fee
Total
71 Amount applied to Contingency
72 Amount applied to OT Allowance
Net change order amount
$10,220.00
10.0061. $1,022.00
$11,242.00
$0.00
$0.00
$11,242.00
❑ We have proceeded with this change per the direction of:
❑ We will not proceed with this change until receipt of a signed copy of this proposal.
❑ This proposal must be accepted by: xxlxxlxx in order to avoid additional extension or expense.
❑ These changes will add approximately xx working days to the completion date.
Submitted by: Date:
Devcon -Bob Roseberry
Approved by: Date:
Own s Representative: James Kuhn, Nova Partners j
t, �` VLj/tiSi �2ptG:
!:
{
i
i
i t
i
t
Devcon Construction Inc. 690 Gibraltar Dr. Milpitas, CA 95035 P.(408)942 -8200 F. (408)262 -2342 Lic. #399163
Project Name: Gilroy Public Library
City Of Gilroy
7387 Rosanna Sheet
Gilroy, CA 95020
FIELD ORDER
FIELD ORDER NO. 38
Project Name:
Gilroy Public Library
Contract Date:
07/26/2010
To Contractor:
Devcon Construction Incorporated
Address:
690 Gibraltar Drive
Milpitas, CA 95035
DESCRIPTION OF WORK:
Project No: 010 -CDD -173
2/8/2012
LANDSCAPE
Item 1:
In the courtyard area up against the stucco wall the orginial plans call for 23 Leymus condensatus
`Cayon Prince' and 5 Festuca callfornica. Due to the height of the wall and the coverage of the solar
panels please substitute these plants for 28 Diyopterls arrgttta — California Wood Fern in 5 gallon
size.
Item 2: d >L4 A ��
On the new parking lot side of the Wheeler Building some existing Star Jasmine was ren oved. Please add
another 21 Star Jasmine in I gallon size to.the 30 that are already called out on the plans.
Item3: ECHO
On the new parking lot side of the Wheeler Building some existing Ra }wood Ash trees were removed.
Aitken and Associates will tag (2) 36" Box Arbutus trees from Bonfonte Tree Nursery.
Item 4:.Ib``t{.�
Chris Weske has requested that two new valves be installed to supply water to the two planter on the front
side of the Wheeler building. Also connect the planter strip closest to the building tivith the new drip
irrigation system. Install new drip line and emitters to the existing plants in the planters.
Item 5: LtG 1 l>
3 Existing Sycamore trees were removed in the parking lot area nearest the new libaray. Those trees are to
be replaced with 36" box Platanus acerifolin. Aitken Associates will tag these trees from $onfonte Tree
Nursery. If the other (4) Platanus acerifolia have not been purchased please notify the landscape architect
and we will tag those trees from Bonfonte as well.
Estimated Adjustment Estimated Adjustment ` j t of "XI C:
of Contract Sum: TBD of Contract Time: 0