HomeMy WebLinkAboutDevcon Construction - Library Construction - Change Order No. 28City of Gilroy
Engineering Division
7351 Rosanna St., Gilroy, CA 95020
Phone (408) 846 -0451; Fax (408) 846 -0429
CHANGE ORDER NO. 28
To contract for : New Gilroy Library Project, Phase 2
Contractor: Devcon Construction
Contract Date: 6/15/2010
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
This Chnnoe Orrlrr nrnvirles fnr the fnllnwino-
Paseo Pavers Base section
10 Unit Pavers
European Paving
Subtotal $55,010.00
69 Fee
Total
Paseo Pavers Base section
71 Amount applied to Contingency
72 Amount applied to OT Allowance
Net change order amount
$55,010.00
$55,010.00
10.00% $5,501.00
$60,511.00
$0.00
$0.00
$60,511.00
All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this
Change Order. The contract time shall not extend unless expressly provided for in this Change Order.
By signing this Change Order, Contractor acknowledges and agrees that the adjustments to cost and time contained herein
are in full satisfaction and accord, and are accepted as payment in full, for any and all costs and expenses associated with this
Change Order, (the "Extra Work "), including but not limited to labor, materials, overhead and profit, delay, disruption, loss
of efficiency and any and all other direct and/or indirect costs or expenses associated with the Extra Work and hereby waives
any right to claim any further cost and time impacts at any time during and after completion of the Contract associated with
the Extra Work.
I (We) agree to make the above change Original Contract Price
subject to the terms of this Change Order Previous Change Orders
for the NET INCREASE of $60,511.00 Total to Date
This Change Order
Total Change Orders to Date
Aly6ok Revised Contract Price
CONTRACTOR
By: Date: Z
Cost Percentage Initial
$18,177,226.00
$1,260,400.00 6.93 %,? 1Z
$19,437,626.00
$60,511.00
$1,320,911.00 7.27% �r
$19,498,137.00
RECOMMENDED BY
ACCEPTED BY:
CPR 155
Project: Gilroy Community Library
Devcon Job #: 10 -296
Date: 3/9/2012
We submit for your approval the following estimate of changes in work:
Paseo Pavers Base section
10 Unit Pavers
European Paving : Paseo Pavers Base section
Subtotal
69 Fee
Total
71 Amount applied to Contingency
72 Amount applied to OT Allowance
Net change order amount
$55,010.00
$55,010.00
$55,010.00
10.00% $5,501.00
$60,511.00
$0.00
$0.00
$60,511.00
❑ We have proceeded with this change per the direction of:
❑ We will not proceed with this change until receipt of a signed copy of this proposal.
❑ This proposal must be accepted by: xx/xx/xx in order to avoid additional extension or expense.
❑ These changes will add approximately xx working days to the completion date.
Submitted by:
Approved by:
Devcon -Bob Roseberry
Owner's Representative: James Kuhn, Nova Partners
Date:
Date:
Devcon Construction Inc. 690 Gibraltar Dr. Milpitas, CA 95035 P.(408)942 -8200 F. (408)262 -2342 Lic. #399163
Professional installations of precast pavers since 1980
Member of the Interlocking Concrete Pavement Institute
ICPI Certified Installer
Change Order Request -- R05
Date: March 8, 2012
Contractor: Devcon Consruction Ph: 408 -519 -8424
Attn: Bob Roseberry IFax: 408- 262 -2342
Email: boseberry @Devcon- const.com
WE ARE SENDING YOU: ❑X ATTACHED I pages total
THE FOLLOWING ITEMS: COST BREAKDOWN
HELD TAGS
THIS WORK: RX Has Has been completed and we are awaiting an Executed Change Order
not been completed and is Pending based on receipt of Change Order
COPIES DATE NO, DESCRIPTION
Project: Gilroy Public Library
Contractor Job No.: D10 -296 #23 EPD Job No.: PSI -1668
Reference:
1. Delta 13 Plan Check Revisions dtd 2 -27 -12 (Pasco)
a. Sheet A2.201A
i. Installation of crushed rock sub -base & base sections for prox 8,768 sf of new paver
areas
2. Rework of existing pavers and crushed rock sections at transition of Paseo
a. Prox 1,000 sf to revised grades
3. Provision of various temporary paver areas and crushed rock base sections for occupancy
a. Prox 500 sf
Cost Impact : Add $55,010
Inclusions:
1. Additional crushed rock installation at prox 10,268 of paver areas per Delta 13, field directed added pavers
and rework of existing pavers upon mobilization for the Delta 13 work
European Paving Designs, Inc. 1474 Berger Drive,San Jose, Ca. 95112
ph: 408 -283 -5230 fx: 408 - 298 -2633
Pricing is valid for 30 days from date of COK