HomeMy WebLinkAboutDevcon Construction - Library Construction - Change Order No. 29City of Gilroy Engineering Division 7351 Rosanna St., Gilroy, CA 95020 Phone (408) 846 -0451; Fax (408) 846 -0429 CHANGE ORDER NO. 29 To contract for : New Gilroy Library Project, Phase 2 Contractor: Devcon Construction Contract Date: 6/15/2010 This order shall become effective when it has been signed by the City Administrator, City Engineer, Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned to him as his authority to proceed with the work. Description of Work This Change Order provides for the following: mowbands. - flatwork and circular seat wall concrete co 7 Cement Concrete Paving Landavazzo Brothers : Curbs, mowbands, flatwork and circular seat wall concrete complete. Subtotal 69 Fee Total $98,327.00 71 Amount applied to Contingency 72 Amount applied to OT Allowance Net change order amount $89,388.00 $89,388.00 $89,388.00 10.00% $8,939.00 $0.00 0.00 $98,327.00 All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this Change Order. The contract time shall not extend unless expressly provided for in this Change Order. By signing this Change Order, Contractor acknowledges and agrees that the adjustments to cost and time contained herein are in full satisfaction and accord, and are accepted as payment in full, for any and all costs and expenses associated with this Change Order, (the "Extra Work "), including but not limited to labor, materials, overhead and profit, delay, disruption, loss of efficiency and any and all other direct and/or indirect costs or expenses associated with the Extra Work and hereby waives any right to claim any further cost and time impacts at any time during and after completion of the Contract associated with the Extra Work. I (We) agree to make the above change Original Contract Price subject to the terms of this Change Order Previous Change Orders for the NET INCREASE of $98,327.00 Total to Date This Change Order /} Total Change Orders to Date /z,/ o ^ l Revised Contract Price (� '/ CONTRACTOR By: Date: AT Z Cost Percentage Initial $18,177,226.00 $1,320,911.00 7.27`%"_ $19,498,137.00 $98,327.00 $1,419,238.00 7.81% $19,596,464.00 RECOMMENDED BY: ACCEPTED BY: v CPR 156 Project: Gilroy Community Library Devcon Job #: 10 -296 Date: 3/8/2012 We submit for your approval the following estimate of changes in work: Curbs, mowbands, flatwork and circular seat wall concrete complete. 7 Cement Concrete Paving Landavazzo Brothers : Curbs, mowbands, flatwork and circular seat wall concrete complete. Subtotal 69 Fee Total 71 Amount applied to Contingency 72 Amount applied to OT Allowance Net change order amount $89,388.00 $89,388.00 $89,388.00 10.00% $8,939.00 $98,327.00 $0.00 $0.00 $98,327.00 ❑ We have proceeded with this change per the direction of: ❑ We will not proceed with this change until receipt of a signed copy of this proposal. ❑ This proposal must be accepted by: xx/xx/xx in order to avoid additional extension or expense. ❑ These changes will add approximately xx working days to the completion date. Submitted by: Approved by: Devcon -Bob Roseberry Owner's Representative: James Kuhn, Nova Partners Date: Date: Devcon Construction Inc. 690 Gibraltar Dr. Milpitas, CA 95035 P.(408)942 -8200 F. (408)262 -2342 Lic. #399163 Landavazo Bros. Inc. 29280 Pacific St. Hayward ca. 94544 GC Devcon Project Gilroy Library ATTN Bob Roseberry DIESCRIPMON ,OIL PROPOSAL Paseo / added site work Inclusions: Labor Form work Concrete Rebar Truncated domes (a) Material (b) Labor (c) Unit Price (d) Exclusions: Baserock or compaction Survey Permits, fees, or inspections Any misc iron or embeds Precast cap at seat wall Any demo (e) Subcontractor's Overhead & Profit 15% (f) (k) PROPOSED CHANGE ORDER PCO No. RFI Date: 3/6/12 EXTRA CREDIT $ 77,729 $ - Subtotal $ 77,729 $ - $ 11,659 $ - Subtotal $ 89,388 $ TOTAL $89,388 By: John Landavazo Landavazo Bros. Inc. PROJECT. Gilroy Library I7EM DESCRIPTION QUANTITY UNIT LABOR MAT'L UNIT LABOR MATERIAL UNIT$ TOTAL EXTRA 4" thick Sidewalk paving 4,100 sf $ 7.00 $ - $ - $ 28,700 $ 28,700 6" bands for pavers 505 If $ 28.50 $ - $ - $ 14,393 $ 14,393 12" band at seatwall 76 If $ 32.00 $ - $ - $ 2,432 $ 2,432 Seat wall with ftg 70 If $ 325.00 $ - $ - $ 22,750 $ 22,750 HC ramp with truncated domes 2 ea $ 1,500.00 $ - $ - $ 3,000 $ 3,000 6" vertical curb 204 If $ 28.50 $ - $ - $ 5,814 $ 5,814 Curb and gutter 20 If $ 32.00 $ - $ - $ 640 $ 640 $ $ $ $ Total Extra $ - $ - $ 77,729 $ 77,729 CREW $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ Total Credit 5 - $ - $ - $ HIP