HomeMy WebLinkAboutDevcon Construction - Library Construction - Change Order No. 29City of Gilroy
Engineering Division
7351 Rosanna St., Gilroy, CA 95020
Phone (408) 846 -0451; Fax (408) 846 -0429
CHANGE ORDER NO. 29
To contract for : New Gilroy Library Project, Phase 2
Contractor: Devcon Construction
Contract Date: 6/15/2010
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work This Change Order provides for the following:
mowbands. - flatwork and circular seat wall concrete co
7 Cement Concrete Paving
Landavazzo Brothers : Curbs, mowbands, flatwork and
circular seat wall concrete complete.
Subtotal
69 Fee
Total $98,327.00
71 Amount applied to Contingency
72 Amount applied to OT Allowance
Net change order amount
$89,388.00
$89,388.00
$89,388.00
10.00% $8,939.00
$0.00
0.00
$98,327.00
All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this
Change Order. The contract time shall not extend unless expressly provided for in this Change Order.
By signing this Change Order, Contractor acknowledges and agrees that the adjustments to cost and time contained herein
are in full satisfaction and accord, and are accepted as payment in full, for any and all costs and expenses associated with this
Change Order, (the "Extra Work "), including but not limited to labor, materials, overhead and profit, delay, disruption, loss
of efficiency and any and all other direct and/or indirect costs or expenses associated with the Extra Work and hereby waives
any right to claim any further cost and time impacts at any time during and after completion of the Contract associated with
the Extra Work.
I (We) agree to make the above change Original Contract Price
subject to the terms of this Change Order Previous Change Orders
for the NET INCREASE of $98,327.00 Total to Date
This Change Order
/} Total Change Orders to Date
/z,/ o ^ l Revised Contract Price
(� '/ CONTRACTOR
By: Date: AT Z
Cost Percentage Initial
$18,177,226.00
$1,320,911.00 7.27`%"_
$19,498,137.00
$98,327.00
$1,419,238.00 7.81%
$19,596,464.00
RECOMMENDED BY:
ACCEPTED BY:
v
CPR 156
Project: Gilroy Community Library
Devcon Job #: 10 -296
Date: 3/8/2012
We submit for your approval the following estimate of changes in work:
Curbs, mowbands, flatwork and circular seat wall concrete complete.
7 Cement Concrete Paving
Landavazzo Brothers : Curbs, mowbands, flatwork and
circular seat wall concrete complete.
Subtotal
69 Fee
Total
71 Amount applied to Contingency
72 Amount applied to OT Allowance
Net change order amount
$89,388.00
$89,388.00
$89,388.00
10.00% $8,939.00
$98,327.00
$0.00
$0.00
$98,327.00
❑ We have proceeded with this change per the direction of:
❑ We will not proceed with this change until receipt of a signed copy of this proposal.
❑ This proposal must be accepted by: xx/xx/xx in order to avoid additional extension or expense.
❑ These changes will add approximately xx working days to the completion date.
Submitted by:
Approved by:
Devcon -Bob Roseberry
Owner's Representative: James Kuhn, Nova Partners
Date:
Date:
Devcon Construction Inc. 690 Gibraltar Dr. Milpitas, CA 95035 P.(408)942 -8200 F. (408)262 -2342 Lic. #399163
Landavazo Bros. Inc.
29280 Pacific St. Hayward ca. 94544
GC Devcon
Project Gilroy Library
ATTN Bob Roseberry
DIESCRIPMON ,OIL PROPOSAL
Paseo / added site work
Inclusions:
Labor
Form work
Concrete
Rebar
Truncated domes
(a) Material
(b) Labor
(c) Unit Price
(d)
Exclusions:
Baserock or compaction
Survey
Permits, fees, or inspections
Any misc iron or embeds
Precast cap at seat wall
Any demo
(e) Subcontractor's Overhead & Profit 15%
(f)
(k)
PROPOSED CHANGE ORDER
PCO No.
RFI
Date: 3/6/12
EXTRA CREDIT
$ 77,729 $ -
Subtotal $ 77,729 $ -
$ 11,659 $ -
Subtotal $ 89,388 $
TOTAL $89,388
By: John Landavazo
Landavazo Bros. Inc.
PROJECT.
Gilroy Library
I7EM
DESCRIPTION
QUANTITY
UNIT
LABOR
MAT'L
UNIT
LABOR
MATERIAL
UNIT$
TOTAL
EXTRA
4" thick Sidewalk paving
4,100
sf
$ 7.00
$ -
$ -
$ 28,700
$ 28,700
6" bands for pavers
505
If
$ 28.50
$ -
$ -
$ 14,393
$ 14,393
12" band at seatwall
76
If
$ 32.00
$ -
$ -
$ 2,432
$ 2,432
Seat wall with ftg
70
If
$ 325.00
$ -
$ -
$ 22,750
$ 22,750
HC ramp with truncated domes
2
ea
$ 1,500.00
$ -
$ -
$ 3,000
$ 3,000
6" vertical curb
204
If
$ 28.50
$ -
$ -
$ 5,814
$ 5,814
Curb and gutter
20
If
$ 32.00
$ -
$ -
$ 640
$ 640
$
$
$
$
Total Extra
$ -
$ -
$ 77,729
$ 77,729
CREW
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
Total Credit
5 -
$ -
$ -
$
HIP