HomeMy WebLinkAboutDevcon Construction - Library Construction - Change Order No. 33City of Gilroy
Engineering Division
7351 Rosanna St., Gilroy, CA 95020
Phone (408) 846 -0451; Fax (408) 846 -0429
CHANGE ORDER NO. 33
To contract for : New Gilroy Library Project, Phase 2
Contractor:
Devcon Construction
Contract Date: 6/15/2010
This order shall become effective when it has been signed by the City Administrator, City Engineer,
Project Engineer, and Contractor. All copies forwarded to Contractor for signature shall be returned to
The City of Gilroy properly filled out. Upon acceptance by the City, the Contractor's copy will be returned
to him as his authority to proceed with the work.
Description of Work This Change Order provides for the following:
Light Fixtures for Paseo material only.
57 Electrical $69,231.00
Sprig Electric : Light Fixtures for Paseo material only. $69,231.00
Subtotal $69,231.00
69 Fee 10.00% $6,923.00
Total $76,154.00
71 Amount applied to Contingency $0.00
72 Amount applied to OT Allowance $0.00
Net change order amount $76,154.00
All requirements of the original Contract Documents shall apply to the above work except as specifically modified by this
Change Order. The contract time shall not extend unless expressly provided for in this Change Order.
By signing this Change Order, Contractor acknowledges and agrees that the adjustments to cost and time contained herein
are in full satisfaction and accord, and are accepted as payment in full, for any and all costs and expenses associated with this
Change Order, (the "Extra Work "), including but not limited to labor, materials, overhead and profit, delay, disruption, loss
of efficiency and any and all other direct and/or indirect costs or expenses associated with the Extra Work and hereby waives
any right to claim any further cost and time impacts at any time during and after completion of the Contract associated with
the Extra Work.
Cost Percentage Initial
I (We) agree to make the above change
Original Contract Price
$18,177,226.00
subject to the terms of this Change Order
Previous Change Orders
$1,634,108.00 8.99% IFP
for the NET INCREASE of $76,154.00
Total to Date
$19,811,334.00
This Change Order
$76,154.00
Total Change Orders to Date
$1,710,262.00 9.41% 1) IL
!/ G yl�CONTRACTOR
Revised Contract Price
$19,887,488.00
By: Date:
Z
RECOMMENDED BY:
ACCEPTED BY: City
Engineer
Date
Date
/Z—
CPR 162
Project: Gilroy Community Library
Devcon Job #: 10 -296
Date: 3/13/2012
We submit for your approval the following estimate of changes in work:
Light Fixtures for Paseo material only.
57 Electrical $69,231.00
Sprig Electric : Light Fixtures for Paseo material only. $69,231.00
Subtotal
69 Fee
Total
71 Amount applied to Contingency
72 Amount applied to OT Allowance
Net change order amount
$69,231.00
10.00% $6,923.00
$76,154.00
$0.00
$0.00
$76,154.00
❑ We have proceeded with this change per the direction of:
❑ We will not proceed with this change until receipt of a signed copy of this proposal.
❑ This proposal must be accepted by: xx/xx/xx in order to avoid additional extension or expense.
❑ These changes will add approximately xx working days to the completion date.
Submitted by:
Approved by:
Devcon -Bob Roseberry
Owner's Representative: James Kuhn, Nova Partners
Date:
Date:
Devcon Construction Inc. 690 Gibraltar Dr. Milpitas, CA 95035 P.(408)942 -8200 F. (408)262 -2342 Lic. #399163
Igo S. 1G& S�a�' Srtrt��. � >, r' 95112
.d: 4CY- 2�T-S5 ; 2%: i3 2 5 -21 1
Client Address:
DEVCON CONSTRUCTION
Contact: Bob Roseberry
690 Gibraltar Drive
Milpitas, CA 95035
CCN #
41.3
CCN Date
3/12/2012
500/700#
514
Project Name:
GILROY LIBRARY
9; Project Number:
2678
` Page Number:
I`
1
PROPOSED CHANGE ORDER
Work Description
CHANGE ORDER COST FOR GILROY PLAZA TO FURNISH THE FOLLOWING LIGHT FIXTURES PER THE SITE
LIGHTING PLAN # ES- 01----------------------------------------------------------------------- - - - - -- $ 69,231.00
SCOPE OF WORK:
- FURNISH (8) TYPE -S6 FIXTURES
- FURNISH (11) TYPE -S10 FIXTURES
- FURNISH (4) TYPE -S11 FISTURES
We reserve the right to correct this quote for errors and omissions.
This quote covers direct costs only and we reserve the right to claim for impact and consequential costs.
This price is good for acceptance within 10 days from the date of receipt.
We request a time extension of 3 days.
We will supply and install all materials, labor, and equipment as per your instructions on PCO #41.3
I. Exclusions:
Overtime and shift work
Permits
Utility company fees, including Secondary cabling costs
Title 24 and Engineering fees
Temporary power and lighting
Xray of floors or walls
Fire proofing patching
Light pole bases and traffic bollards
Cutting & patching of any type
Demolition of any type
Painting
Temperature control provisions
Dumpster fees
Short circuit and coordination studies
Access panels
Roof patching
Ceiling seismic support wires
Consealed and unforeseen conditions
Upgrade of existing code violations
After -hour inspections
EMF shielding provisions at electrical equipment rooms
Lamp replacement at end of project if fixtures are used for temporary lighting
Provisions for contaminated ground water and trench spoil
Pipe protection posts
Independent testing and inspections
Offsite utility service extensions
ORIGINAL
PROPOSED CHANGE ORDER
Client Address:
DEVCON CONSTRUCTION
690 Gibraltar Drive
Milpitas, CA 95035
Street lighting
Traffic signals
Provisions for contending with hidden obstructions encountered during excavation
Telephone system equipment, cabling and terminations
Computer network equipment, cabling and terminations
Security system equipment, cabling and terminations
Audio Visual system equipment, cabling and terminations
Acoustical box pads and caulking at STC rated walls
Fire rated box pads and caulking at fire rated walls
Energy management system (EMS) provisions
II. Clarifications:
• All work is to be completed between the hours of 7:00am through 3:30pm Monday through Friday.
Ill. General Conditions:
All applicable taxes are included in our submission
The contractor shall not be held liable for errors or omissions in design by others, nor inadequacies of materials and
equipment -specified or supplied by others
• Equipment and materials supplied by the contractor are warranted only to the extent that the same are warranted by the
-manufacturer
The contractor shall not be liable for indirect loss or damage
Unless included in this proposal, all bonding and /or special insurance requirements are supplied at additional cost
If a formal contract is required, its conditions must not deviate from this proposal without our permission
Anything (verbal or written) expressed or implied elsewhere, which is contrary to these conditions shall be null and void
We will not participate in liquidated damage expenses if damages are due to any cause other than our own actions
This quotation is good for ten days, and is based upon our entering into a subcontract with you in a form which is mutually
satisfactory and having conditions which are no more exacting or unfavorable to us than the contract entered into
between the owner and the contractor.
We appreciate the opportunity extended to Sprig Electric in allowing us to submit our proposal for this important project.
Please contact our office if you have any questions for if additional information is needed.
Sincerely,
SPRIG ELECTRIC COMPANY
Ron Piovesan
Senior Project Manager
Itemized Breakdown
Description
Qty
Net Price U
Total Mat($)
Labor U
Total Hours
TYPE -S6
8
280.00 E
2,240.00
0.00 E
0.00
TYPE -S10
11
4,400.00 E
48,400.00
0.00 E
0.00
TYPE -S11
4
1,852.00 E
7,408.00
0.00 E
0.00
Totals
58,048.00
0.00
General Materials
Material Subtotal
Material Tax
Material Markup
(@ 8.250 %)
(@ 10.000 %)
ORIGINAL
58,048.00
58,048.00
4,788.96
6,283.70
PROPOSED CHANGE ORDER
Client Address:
DEVCON CONSTRUCTION
690 Gibraltar Drive
Milpitas, CA 95035
Summary (Cont'd)
Material Total
GENERAL EXPENSES
FORKLIFT (per Day) (1.00 @ 1.00 @ $110.00 + 0.000 %)
Final Amount
ORIGINAL
69,120.66
110.00
$69,231.00